Patent classifications
E02D11/00
Pre-stressed molded wall, and method for creating such a wall
The invention relates to a prestressed diaphragm wall in the ground (10) including a concrete panel (52), at least one anchor tube open at its upper end (38) and closed at its lower end (36) and, embedded at least partially in the concrete panel, at least one cable (60) extending inside the anchor tube (30), a lower portion of the cable (60) being fixed to said tube (30), and a cable anchoring system (90), configured to hold the cable in tension (60) and secure its upper portion (68) to the upper portion of the concrete panel (52). It also relates to a method for making a prestressed diaphragm wall.
Pre-stressed molded wall, and method for creating such a wall
The invention relates to a prestressed diaphragm wall in the ground (10) including a concrete panel (52), at least one anchor tube open at its upper end (38) and closed at its lower end (36) and, embedded at least partially in the concrete panel, at least one cable (60) extending inside the anchor tube (30), a lower portion of the cable (60) being fixed to said tube (30), and a cable anchoring system (90), configured to hold the cable in tension (60) and secure its upper portion (68) to the upper portion of the concrete panel (52). It also relates to a method for making a prestressed diaphragm wall.
BASE BODY OF ELECTRIC TRANSMISSION TOWER USING MICROPILE
Disclosed is a base body of an electric transmission tower using a micropile. The base body of the electric transmission tower using the micropile includes an anchor member coupled to a main pole member of the electric transmission tower, a foundation member coupled to the anchor member and including a plurality of foundations, and the micropile configured to fix the foundation member to the ground and compress the foundation member.
Anchor post
Provided herein are methods, devices and systems comprising an anchor post that has a shaft, at least one stabilizing element attached to the anchor post configured to resist movement of the anchor post, and at least one alignment element.
INSTALLATION AND REMOVAL OF SUBSEA FOUNDATIONS
An underwater pile foundation comprises a pump in fluid communication with an internal chamber of the pile to pump water out of or into the chamber. This reduces or increases the pressure of water in the chamber relative to ambient pressure of water outside the chamber during installation or removal of the pile. While that pumping phase is ongoing, and potentially before or after that pumping phase, a pressure variator in fluid communication with the chamber imparts oscillations in the pressure of the water in the chamber. The resulting pressure waves in water within the chamber reduce resistance to movement of the pile relative to soil in which the pile is embedded.
INSTALLATION AND REMOVAL OF SUBSEA FOUNDATIONS
An underwater pile foundation comprises a pump in fluid communication with an internal chamber of the pile to pump water out of or into the chamber. This reduces or increases the pressure of water in the chamber relative to ambient pressure of water outside the chamber during installation or removal of the pile. While that pumping phase is ongoing, and potentially before or after that pumping phase, a pressure variator in fluid communication with the chamber imparts oscillations in the pressure of the water in the chamber. The resulting pressure waves in water within the chamber reduce resistance to movement of the pile relative to soil in which the pile is embedded.
Apparatus and methods for the placement of pipe piling
Apparatus and methods for the installation of pipe pilings into the ground for use as structural building foundations, geothermal piles, or both, are disclosed. In addition to specialized fittings for pipe pile assemblies, the inventions include specialized drive mechanisms used in conjunction with rotary or vibratory motors. Methods of installing pipe pilings are further improved with the disclosure of methods of adding grout or similar materials during or after installation of the piles.
Apparatus and methods for the placement of pipe piling
Apparatus and methods for the installation of pipe pilings into the ground for use as structural building foundations, geothermal piles, or both, are disclosed. In addition to specialized fittings for pipe pile assemblies, the inventions include specialized drive mechanisms used in conjunction with rotary or vibratory motors. Methods of installing pipe pilings are further improved with the disclosure of methods of adding grout or similar materials during or after installation of the piles.
Fastener for Construction Element
The present invention relates to a fastening tab for a construction element, preferably a beam, a panel or a slab, that is adjustable vertically and relative to the horizontal, that can be screwed to a support with inner thread, preferably a foundation screw, successively comprising: a fastening screw comprising a beveled head and a threaded shank; a metal plate pierced with a beveled opening that can accommodate said fastening screw and comprising fastening means to the construction element; a perforated flexible joint; a screw comprising a machined beveled head with an inner thread corresponding to that of said fastening screw; such that the position of the screw relative to the support, which is obtained by screwing/unscrewing, allows vertical adjustment of the metal plate;
characterized in that the fastening screw, the beveled aperture of the metal plate and the flexible joint cooperate to allow angular adjustment of the metal plate relative to the horizontal plane.
Apparatus and methods for the placement of pipe piling
Apparatus and methods for the installation of pipe pilings into the ground for use as structural building foundations, geothermal piles, or both, are disclosed. In addition to specialized fittings for pipe pile assemblies, the inventions include specialized drive mechanisms used in conjunction with rotary or vibratory motors. Methods of installing pipe pilings are further improved with the disclosure of methods of adding grout or similar materials during or after installation of the piles.