E21F15/02

FILLING MINING METHOD FOR FULLY-MECHANIZED TOP COAL CAVING WORKING FACE

Provided is a filling mining method for a fully-mechanized top coal caving working face, which relates to the field of mining engineering technologies. The method solves the technical problems of roof control of the fully-mechanized top coal caving working face and a large ground deformation of top coal caving mining. The method includes the following steps: at step A, dividing the fully-mechanized top coal caving working face into a filling zone and a top coal caving zone along a strike of the working face, or dividing the working face into a filling zone and a top coal caving zone along a strike and an inclination of the working face; at step B, determining a cycle interval of the working face; at step C, performing supporting for the filling zone before the working face, and completing coal caving in the top coal caving zone and performing round wood supporting in the filling zone; at step D, after the filling zone reaches the filling interval, disposing a filling tarpaulin behind a hydraulic support and pumping the filling paste; at step E, repeating steps C and D to complete mining. A mining method of alternate coal caving and filling is provided to complete the filling mining of the top coal caving working face. In this way, the roof is effectively controlled, ground subsidence is reduced and advantages such as safety and high efficiency are available.

FILLING MINING METHOD FOR FULLY-MECHANIZED TOP COAL CAVING WORKING FACE

Provided is a filling mining method for a fully-mechanized top coal caving working face, which relates to the field of mining engineering technologies. The method solves the technical problems of roof control of the fully-mechanized top coal caving working face and a large ground deformation of top coal caving mining. The method includes the following steps: at step A, dividing the fully-mechanized top coal caving working face into a filling zone and a top coal caving zone along a strike of the working face, or dividing the working face into a filling zone and a top coal caving zone along a strike and an inclination of the working face; at step B, determining a cycle interval of the working face; at step C, performing supporting for the filling zone before the working face, and completing coal caving in the top coal caving zone and performing round wood supporting in the filling zone; at step D, after the filling zone reaches the filling interval, disposing a filling tarpaulin behind a hydraulic support and pumping the filling paste; at step E, repeating steps C and D to complete mining. A mining method of alternate coal caving and filling is provided to complete the filling mining of the top coal caving working face. In this way, the roof is effectively controlled, ground subsidence is reduced and advantages such as safety and high efficiency are available.

METHOD AND APPARATUS FOR USE IN STOPE BACKFILL MINING
20230417142 · 2023-12-28 · ·

A method for forming a passage in stope backfill material includes steps of: a) providing an expandable void forming apparatus at a lower level relative to an unexcavated stope; b) expanding the void forming apparatus, such that a substantially liquid-impermeable seal is formed between the void forming apparatus and the unexcavated stope; c) pouring backfill material into a void formed by the excavation of a stope adjacent to the unexcavated stope, and allowing the backfill material to at least partially cure such that the void forming apparatus forms a passage between the unexcavated stope and the backfill material; and d) contracting the void forming apparatus and removing the void forming apparatus from the passage.

METHOD AND APPARATUS FOR USE IN STOPE BACKFILL MINING
20230417142 · 2023-12-28 · ·

A method for forming a passage in stope backfill material includes steps of: a) providing an expandable void forming apparatus at a lower level relative to an unexcavated stope; b) expanding the void forming apparatus, such that a substantially liquid-impermeable seal is formed between the void forming apparatus and the unexcavated stope; c) pouring backfill material into a void formed by the excavation of a stope adjacent to the unexcavated stope, and allowing the backfill material to at least partially cure such that the void forming apparatus forms a passage between the unexcavated stope and the backfill material; and d) contracting the void forming apparatus and removing the void forming apparatus from the passage.

METHOD OF RECOVERING ROOM-AND-PILLAR COAL PILLAR BY USING EXTERNAL REPLACEMENT SUPPORTS

A method of recovering a room-and-pillar coal pillar by using external replacement supports. In the recovery of a room-and-pillar coal pillar, a cement material wall is formed by performing pouring around a coal pillar having a width to height ratio of less than 0.6, by means of a single-pillar sack arrangement technique, such that a coal pillar resource may be mined while a wall made from a cement filling material supports an overlying stratum. After mining is complete, a coal pillar goaf region is filled with the cement filling material, and after the cement filling material solidifies and is stable, the single pillar can be recovered.

METHOD OF RECOVERING ROOM-AND-PILLAR COAL PILLAR BY USING EXTERNAL REPLACEMENT SUPPORTS

A method of recovering a room-and-pillar coal pillar by using external replacement supports. In the recovery of a room-and-pillar coal pillar, a cement material wall is formed by performing pouring around a coal pillar having a width to height ratio of less than 0.6, by means of a single-pillar sack arrangement technique, such that a coal pillar resource may be mined while a wall made from a cement filling material supports an overlying stratum. After mining is complete, a coal pillar goaf region is filled with the cement filling material, and after the cement filling material solidifies and is stable, the single pillar can be recovered.

Roadway forming method by expanding excavating and filling gangue paste in thick coal seam

Provided is a method of forming a roadway by filling gangue paste during wide roadway excavation of a thick coal seam belonging to the technical field of mining industry. The method comprises: firstly designing a width of a filing strip and a width of a new excavation roadway according to a geological condition of a coal seam; secondly, determining a length of each filling, i.e. a cyclic filling interval, according to an existing excavation technical condition of a mining shaft; when the new excavation roadway is excavated, performing supporting for a roof, a floor and an inner side of a roadway by using a strong bolt and bolt-mesh-cable; then, after the new excavation roadway is excavated for the cyclic filling interval, starting to perform roadway-expanding excavation along an outer side of the roadway; when roadway-expanding excavation is performed, performing temporary supporting for a filling strip and a junction of the filling strip and the new excavation roadway by using a single hydraulic prop in cooperation with a metal articulated roof beam; finally, after roadway-expanding excavation is completed, removing temporary supports and filling the filling strip; afterwards, the above steps are performed alternately. In this way, coal losses caused by reserving coal pillars can be effectively reduced, the impact of the underground pressure during roadway excavation is relieved and the costs of gangue treatment and roadway excavation are lowered.

Roadway forming method by expanding excavating and filling gangue paste in thick coal seam

Provided is a method of forming a roadway by filling gangue paste during wide roadway excavation of a thick coal seam belonging to the technical field of mining industry. The method comprises: firstly designing a width of a filing strip and a width of a new excavation roadway according to a geological condition of a coal seam; secondly, determining a length of each filling, i.e. a cyclic filling interval, according to an existing excavation technical condition of a mining shaft; when the new excavation roadway is excavated, performing supporting for a roof, a floor and an inner side of a roadway by using a strong bolt and bolt-mesh-cable; then, after the new excavation roadway is excavated for the cyclic filling interval, starting to perform roadway-expanding excavation along an outer side of the roadway; when roadway-expanding excavation is performed, performing temporary supporting for a filling strip and a junction of the filling strip and the new excavation roadway by using a single hydraulic prop in cooperation with a metal articulated roof beam; finally, after roadway-expanding excavation is completed, removing temporary supports and filling the filling strip; afterwards, the above steps are performed alternately. In this way, coal losses caused by reserving coal pillars can be effectively reduced, the impact of the underground pressure during roadway excavation is relieved and the costs of gangue treatment and roadway excavation are lowered.

System and method for forming a cavity in a backfilled stope
10774644 · 2020-09-15 · ·

A system for forming a cavity in a backfill mixture comprising granular material and water positioned in an at least partially excavated stope. The system includes a base and a drainage tube assembly in an extended condition thereof. The drainage tube assembly extends between a lower end secured to the base and an upper end positioned above an upper surface of the backfill mixture. The extended drainage tube assembly includes a tube portion thereof with a permeable material and defining the cavity therein into which the water from the backfill mixture is drainable, through the permeable material. The system also includes a drainage pipe, for permitting the water that has drained into the cavity of the extended drainage tube assembly to exit the stope.

System and method for forming a cavity in a backfilled stope
10774644 · 2020-09-15 · ·

A system for forming a cavity in a backfill mixture comprising granular material and water positioned in an at least partially excavated stope. The system includes a base and a drainage tube assembly in an extended condition thereof. The drainage tube assembly extends between a lower end secured to the base and an upper end positioned above an upper surface of the backfill mixture. The extended drainage tube assembly includes a tube portion thereof with a permeable material and defining the cavity therein into which the water from the backfill mixture is drainable, through the permeable material. The system also includes a drainage pipe, for permitting the water that has drained into the cavity of the extended drainage tube assembly to exit the stope.