E02D17/04

Method for constructing inner dump type strip mine pit bottom reservoirs section by section

The present invention discloses a method for constructing inner dump type strip mine pit bottom reservoirs section by section, specifically including the following steps: S1: processing end slopes: discarding clay at a lowest step of an inner waste dump of a strip mine; S2: discharging concrete to slope faces of lowest steps of the end slopes on two sides of a pit bottom; S3: sealing the bottom; S4: discarding gravel into a pit of the strip mine; S5: laying geotextile; S6: re-adopting clay on the lowest steps of the end slopes of the inner waste dump, so as to form a reservoir sealing isolation layer; S7: constructing a plurality of reservoirs step by step in an advancing direction of the strip mine; S8: storing water resources: completing installation of water storage wells; S9: completing installation of water fetching wells; S10: storing water resources.

Anchor rod for positioned grouting suitable for prevention and control of engineering seepage damage and construction method thereof

Disclosed is a positioning grouting anchor rod suitable for preventing and controlling an engineering seepage damage and a construction method thereof. The positioning anchor rod comprises an anchor rod, a grouting guide pipe and a grouting pipe. When the seepage failure occurs in the project, a water pump can be connected with a drain pipe interface to realize water drainage, and at the same time, a positioner can be used for positioning grouting in the seepage failure area to improve the accuracy of grouting reinforcement. A drainage channel and a grouting channel involved in the present application are independent of each other and do not interfere with each other, and the drainage and grouting functions are combined on the basis of retaining the original supporting function of the anchor rod.

Anchor rod for positioned grouting suitable for prevention and control of engineering seepage damage and construction method thereof

Disclosed is a positioning grouting anchor rod suitable for preventing and controlling an engineering seepage damage and a construction method thereof. The positioning anchor rod comprises an anchor rod, a grouting guide pipe and a grouting pipe. When the seepage failure occurs in the project, a water pump can be connected with a drain pipe interface to realize water drainage, and at the same time, a positioner can be used for positioning grouting in the seepage failure area to improve the accuracy of grouting reinforcement. A drainage channel and a grouting channel involved in the present application are independent of each other and do not interfere with each other, and the drainage and grouting functions are combined on the basis of retaining the original supporting function of the anchor rod.

METHOD FOR ALTERNATELY CONSTRUCTING UNDERGROUND VERTICAL MEMBERS USING TOP-DOWN CONSTRUCTION METHOD
20220243418 · 2022-08-04 ·

The present invention is provided to shorten a period of underground frame construction in top-down construction method, and more specifically, provides a construction method for alternately constructing underground vertical members downward to lower levels and then constructing remaining vertical members during the same time period after mat and foundation construction, thus making it possible to shorten a construction period of the vertical members and an overall construction period. The method includes a first step of installing the earth retaining wall, constructing the underground pillar post, excavating the first underground level, and constructing the first above-ground level floor; a second step of first constructing the core part of one underground level while constructing the underground level slab downward to support the above-ground level core part which is constructed upward; a third step of alternately constructing an underground vertical member downward; and a step of constructing remaining underground vertical members during the same time period after the construction of the lowest level mat or the foundation, in which the construction period of the underground vertical member is shortened, and thereby the above-ground frame and finishing construction can be started early and an overall construction period is shortened.

METHOD FOR ALTERNATELY CONSTRUCTING UNDERGROUND VERTICAL MEMBERS USING TOP-DOWN CONSTRUCTION METHOD
20220243418 · 2022-08-04 ·

The present invention is provided to shorten a period of underground frame construction in top-down construction method, and more specifically, provides a construction method for alternately constructing underground vertical members downward to lower levels and then constructing remaining vertical members during the same time period after mat and foundation construction, thus making it possible to shorten a construction period of the vertical members and an overall construction period. The method includes a first step of installing the earth retaining wall, constructing the underground pillar post, excavating the first underground level, and constructing the first above-ground level floor; a second step of first constructing the core part of one underground level while constructing the underground level slab downward to support the above-ground level core part which is constructed upward; a third step of alternately constructing an underground vertical member downward; and a step of constructing remaining underground vertical members during the same time period after the construction of the lowest level mat or the foundation, in which the construction period of the underground vertical member is shortened, and thereby the above-ground frame and finishing construction can be started early and an overall construction period is shortened.

Concrete inside interface processing structure and method for secant pile construction

A concrete inside interface processing structure for secant pile construction, including secant concrete pile, formed plain concrete pile, rotary jet grouting piles, steel mesh sheet, ribbed steel bar, Y-shaped connecting piece, reinforced concrete pile, and U-shaped connecting piece; drilled holes are arranged at intervals along axis of the formed plain concrete pile; the ribbed steel bar is anchored in each drilled hole; the steel mesh sheet is formed by connecting longitudinal bars and transverse bars, and driven into a soil body between the formed plain concrete piles; the concrete layer is formed by spraying concrete on the steel mesh sheet; the reinforced concrete pile is cast at outside of the formed plain concrete pile, and tangent to the formed plain concrete pile, and interlocked with the rotary jet grouting piles; the rotary jet grouting piles are tangent to the formed plain concrete pile or secant concrete pile.

Concrete inside interface processing structure and method for secant pile construction

A concrete inside interface processing structure for secant pile construction, including secant concrete pile, formed plain concrete pile, rotary jet grouting piles, steel mesh sheet, ribbed steel bar, Y-shaped connecting piece, reinforced concrete pile, and U-shaped connecting piece; drilled holes are arranged at intervals along axis of the formed plain concrete pile; the ribbed steel bar is anchored in each drilled hole; the steel mesh sheet is formed by connecting longitudinal bars and transverse bars, and driven into a soil body between the formed plain concrete piles; the concrete layer is formed by spraying concrete on the steel mesh sheet; the reinforced concrete pile is cast at outside of the formed plain concrete pile, and tangent to the formed plain concrete pile, and interlocked with the rotary jet grouting piles; the rotary jet grouting piles are tangent to the formed plain concrete pile or secant concrete pile.

DEVICES, ASSEMBLIES, AND METHODS FOR SHORING TEMPORARY SURFACE EXCAVATIONS
20220251795 · 2022-08-11 · ·

An assembly for shoring temporary surface excavations includes a base unit and a first extension unit. The base unit includes features for allowing the assembly to be jacked out of the excavation when hoisting becomes impossible of impractical. The shoring structure may also be jacked into an unstable excavation from above.

DEVICES, ASSEMBLIES, AND METHODS FOR SHORING TEMPORARY SURFACE EXCAVATIONS
20220251795 · 2022-08-11 · ·

An assembly for shoring temporary surface excavations includes a base unit and a first extension unit. The base unit includes features for allowing the assembly to be jacked out of the excavation when hoisting becomes impossible of impractical. The shoring structure may also be jacked into an unstable excavation from above.