Y04S10/20
AUTONOMOUS RESTORATION OF POWER SYSTEMS AFTER NATURAL DISASTERS
Systems, methods, and computer-readable media are disclosed for autonomous restoration of power systems after natural disasters. An operating mode of a circuit breaker that is in a power system grid and that is coupled to other circuit breakers in the power system grid via communication channels is determined. Based on determining that the operating mode is a normal operating mode, data to parameterize a plurality of power grid restoration scenarios is collected at the circuit breaker. Based on determining that the operating mode is an exception mode, measurement data that includes current and voltage data is received at the circuit breaker, and one of the power system grid restoration scenarios is initiated at the circuit breaker. The power system grid error restoration scenario is selected based at least in part on a status of the plurality of communication channels coupled to the circuit breaker and on the measurement data.
Converter valve fault warning method and system
Within a predetermined time range, record time information of status indication signals fed back by thyristor control units (TCU) of a converter valve. Perform statistics and comparison of the pieces of time information using a bias statistics method. Mark a thyristor level whose bias exceeds a preset value. And determine a probability of failure in the thyristor according to the marking result.
Recloser Control with Distributed Energy Resource Synchronization
The present disclosure relates to a recloser control that provides autosynchronization of a microgrid to an area electric power system (EPS). For example, a recloser control may include an output connector that is communicatively coupled to a recloser at a point of common coupling (PCC) between the area EPS and the microgrid. The recloser control may include a processor that acquires a first set of measurements indicating electrical characteristics of the area EPS and acquires a second set of measurements indicating electrical characteristics of the microgrid. The recloser control may send synchronization signals to one or more distributed energy resource (DER) controllers to synchronize one or more DERs to the area EPS based on the first set of measurements and the second set of measurements.
METHOD FOR CONTROLLING THE RESTORATION OF A NETWORK
A method for controlling the rebuilding of an electrical supply network, wherein the electrical supply network has a first network section and at least one further network section, at least one wind farm is connected to the first network section, the wind farm can be controlled via a wind farm control room, the first network section is coupled to the at least one further network section via at least one switching device in order to transmit electrical energy between the network sections, the at least one switching device is set up to disconnect the first network section from the at least one further network section in the event of a fault, a network control station is provided for the purpose of controlling the at least one switching device, wherein, in the event of a fault during which a network fault acting on the first network section occurs, the first network section is disconnected from the at least one further network section by the at least one switching device, the wind farm control room interchanges data with the network control station via a control room connection, wherein the control room connection is a failsafe communication connection between the wind farm control room and the network control station and can be operated independently of the electrical supply network, in particular can be operated even in the case of the fault in the first network section, and the wind farm receives data from the network control station via a wind farm connection, wherein the wind farm connection is a failsafe communication connection between the wind farm and the network control station and can be operated independently of the electrical supply network, in particular can be operated even in the case of the fault in the first network section, and further data which are not transmitted via the control room connection and are not transmitted via the wind farm connection are transmitted via a further data connection provided that the latter has not failed.
MICROGRID SERVICE ENTRANCE
The disclosure provides a microgrid service entrance (MSE) and employing an MSE for controlling a microgrid. In one embodiment, the MSE includes: (1) an enclosure, (2) protective relays having bi-directional protection, (3) a communications module communicatively coupled to the protective relays, and (4) a power bus coupled to the protective relays and including a primary disconnect, wherein the protective relays, the communications module, and the power bus are located within the enclosure.
METHODS, SYSTEMS, AND COMPUTER READABLE MEDIA FOR PROTECTING AND CONTROLLING A MICROGRID WITH A DYNAMIC BOUNDARY
Methods, systems, and computer readable mediums for protecting and controlling a microgrid with a dynamic boundary are disclosed. One method includes detecting a fault in a microgrid that includes a dynamic point-of-common-coupling (PCC), in response to determining that the microgrid is operating in a grid-connected mode, isolating the fault by tripping a microgrid side smart switch and a grid side smart switch that are located immediately adjacent to the fault, initiating the reclosing of the grid side smart switch, and initiating the reclosing for the microgrid side smart switch via resynchronization if the grid side smart switch is successfully reclosed, and in response to determining that the microgrid is operating in an islanded mode, isolating the fault by tripping a microgrid side smart switch that is located immediately adjacent to the fault, and initiating the reclosing of the microgrid side smart switch.
FEEDER LINE FAULT RESPONSE USING DIRECT CURRENT INTERCONNECTION SYSTEM
Systems, methods, techniques and apparatuses of feeder line fault response are disclosed. One exemplary embodiment is a method for operating an alternating current (AC) distribution network including a first feeder line, a second feeder line, and a third feeder line. The method includes isolating a faulted portion of the first feeder line from a healthy portion of the first feeder line; closing a tie switch coupled between the healthy portion and the second feeder line in response to isolating the faulted portion from the healthy portion; determining the second feeder line is experiencing an overload condition after closing the tie switch; and transferring AC power including transferring AC power using a direct current (DC) interconnection system coupled to the third feeder line effective to remove the overload condition from the second feeder line.
Feeder line fault response using direct current interconnection system
Systems, methods, techniques and apparatuses of feeder line fault response are disclosed. One exemplary embodiment is a method for operating an alternating current (AC) distribution network including a first feeder line, a second feeder line, and a third feeder line. The method includes isolating a faulted portion of the first feeder line from a healthy portion of the first feeder line; closing a tie switch coupled between the healthy portion and the second feeder line in response to isolating the faulted portion from the healthy portion; determining the second feeder line is experiencing an overload condition after closing the tie switch; and transferring AC power including transferring AC power using a direct current (DC) interconnection system coupled to the third feeder line effective to remove the overload condition from the second feeder line.
Disconnect switch status in a power distribution system
An energy management system receives voltage and current data from each of a plurality of fault indicators. Each fault indicator is positioned on a powerline of a power distribution system immediately upstream of a respective one of a plurality of disconnect switches. The energy management system also determines a status of each disconnect switch based on the voltage and current from the plurality of fault indicators.
Power distribution systems and methods of performing ground fault detection in power distribution systems with a communication network
A method of operating an electrical power distribution system including a plurality of circuit protection devices and an additional circuit protection device communicatively coupled by a communications network is described. The method includes transmitting, by each circuit protection device of the plurality of circuit protection devices, an electrical current communication to the communication network, the electrical current communication including an indication of an electrical current detected by the transmitting circuit protection device formatted according to a network communication protocol of the communication network. The additional circuit protection device receives the electrical current communications from the plurality of circuit protection devices and determines, based on the received electrical current communications, whether a ground fault condition exists in the electrical power distribution system.