CONCRETE TOWERS MANUFACTURING METHOD FOR WIND TURBINES AND CONCRETE TOWER FOR WIND TURBINE
20170247901 ยท 2017-08-31
Inventors
- Luis Carrillo Alonso (Madrid, ES)
- Manuel Biedma Garcia (Madrid, ES)
- Ivan Garcia Maestre (Navarra, ES)
- Teresa Arlaban Gabeiras (Navarra, ES)
- Jose Luis Aristegui Lantero (Navarra, ES)
- Jose Miguel Garcia Sayes (Navarra, ES)
- Miguel Nunez Polo (Navarra, ES)
Cpc classification
Y02P70/50
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
Y02E10/728
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
E04G11/28
FIXED CONSTRUCTIONS
F03D13/10
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
E04H12/341
FIXED CONSTRUCTIONS
Y02E10/72
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
B66C23/207
PERFORMING OPERATIONS; TRANSPORTING
F05B2240/912
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
E04H12/342
FIXED CONSTRUCTIONS
E04G11/20
FIXED CONSTRUCTIONS
E04H12/12
FIXED CONSTRUCTIONS
F05B2230/61
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
International classification
E04H12/34
FIXED CONSTRUCTIONS
E04H12/12
FIXED CONSTRUCTIONS
Abstract
The present invention relates to a manufacturing process in situ of concrete towers for wind turbines which enables executing a design of concrete tower manufactured in situ by means of climbing formwork, which reduces the execution time of the concrete tower, where the invention also relates to the associated concrete tower for wind turbine.
Claims
1. A manufacturing process of concrete towers for wind turbines comprising: an execution stage of a first cylindrical section of concrete tower by means of a first climbing formwork system; and n execution stage of a second cylindrical section of concrete tower by means of the first climbing formwork system so that an outer diameter of the second cylindrical section is smaller than an outer diameter of the first cylindrical section, where the execution stage of the second cylindrical section is carried out at a height greater than the execution stage of the first cylindrical section.
2. The process of claim 1, further comprising: a construction stage of an intermediate transition section before the execution stage of the second cylindrical section of concrete tower.
3. The process of claim 2, wherein the construction stages of the intermediate transition section and the execution stage of the second cylindrical section of concrete tower are repeated until the second cylindrical section is an upper cylindrical section of concrete tower.
4. The process of claim 1, further comprising: an assembly stage of the first climbing formwork system on a lower section of concrete tower manufactured prior to the execution stage of the first cylindrical section of concrete tower.
5. The process of claim 4, wherein the lower section of concrete tower is manufactured in situ on a foundation of the concrete tower.
6. The process of claim 1, wherein the construction stage of the intermediate transition section is carried out on the first cylindrical section.
7. The process of claim 6, further comprising, before the construction stage of the intermediate transition section on the first cylindrical section, an adaptation stage of the first climbing formwork system, for the in situ construction of the intermediate transition section.
8. The process of claim 6 further comprising, before the construction stage of the intermediate transition section on the first cylindrical section, an assembly stage of a first non-climbing formwork system for the in situ construction of the intermediate transition section.
9. The process of claim 1, wherein the construction stage of the intermediate transition section comprises a manufacturing stage of the intermediate transition section in an area close to a base of the concrete tower and an installation stage of the intermediate transition section on the first cylindrical section.
10. The process of claim 1, further comprising, after the construction stage of the intermediate transition section and before the execution stage of the second cylindrical section, an adaptation stage of an outer formwork of the first climbing formwork system to the outer diameter of the second cylindrical section.
11. (canceled)
12. The process of claim 1, wherein the execution stage of the second cylindrical section is carried out so that an inner diameter of the second cylindrical section is smaller than an inner diameter of the first cylindrical section.
13. The process of claim 3, further comprising a construction stage of a top section after the execution stage of the second cylindrical section, where said second cylindrical section is the upper cylindrical section of concrete tower.
14. The process of claim 13, wherein the construction stage of the top section is carried out on the upper cylindrical section of concrete tower.
15. The process of claim 14, further comprising, before the construction stage of the top section on the upper cylindrical section, an assembly stage of a second non-climbing formwork system for the in situ construction of the top section.
16. The process of claim 13, wherein the construction stage of the top section comprises a manufacturing stage of the top section in an area close to a base of the concrete tower, and an installation stage of the top section on the upper cylindrical section.
17. The process of claim 1, wherein the execution stage of the first cylindrical section and/or the execution stage of the second cylindrical section comprise the following sub-stages: a lifting sub-stage of a framework; a fixing sub-stage of the framework to the previously manufactured cylindrical section; a closing sub-stage of the first climbing formwork system; a pouring sub-stage of the concrete inside the first climbing formwork system; an opening sub-stage of the first climbing formwork system; a climbing sub-stage of the first climbing formwork system; where said sub-stages are repeated until all of the first cylindrical section and/or all of the second cylindrical section, respectively, has been executed.
18. The process of claim 1, wherein the execution stage of the first cylindrical section and/or the execution stage of the second cylindrical section comprise a modification sub-stage of an inner formwork of the first climbing formwork system.
19. Concrete tower for wind turbines comprising at least two sections of constant outer diameter, a first cylindrical section and a second cylindrical section, where the second cylindrical section is higher than the first cylindrical section, characterized in that an outer diameter of the second cylindrical section is smaller than an outer diameter of the first cylindrical section.
20. The concrete tower of claim 19, wherein the first cylindrical section and the second cylindrical section are both intended to be executed in situ by means of a first climbing formwork system.
21. The concrete tower of claim 20, further comprising an intermediate transition section disposed between the first cylindrical section and the second cylindrical section.
22. The concrete tower of claim 21, wherein said intermediate transition section is a section which is intended to be executed in situ.
23. The concrete tower of claim 21, wherein the intermediate transition section is a prefabricated concrete element either formed by a single piece or formed by several modules.
24. The concrete tower of claim 19, wherein the intermediate transition section comprises an inner surface with at least one section with truncated cone geometry.
25. (canceled)
26. (canceled)
27. (canceled)
28. The concrete tower of claim 19, wherein the first cylindrical section and/or the second cylindrical section comprise at least one first sub-section with a first inner diameter and a second sub-section with a second inner diameter, where the second sub-section is higher than the first sub-section and where the first inner diameter of the first sub-section is smaller than the second inner diameter of the second sub-section.
29. The concrete tower of claim 19, further comprising a top section disposed on the second cylindrical section or on an upper cylindrical section.
30. The concrete tower of claim 29, wherein the top section is a section which is intended to be executed in situ.
31. The concrete tower of claim 29, wherein the top section is a prefabricated concrete element either formed by a single piece or formed by several modules.
32. (canceled)
33. The concrete tower of claim 19, further comprising a lower section of concrete tower which is lower than the first cylindrical section where said lower section of concrete tower has an outer diameter larger than the outer diameter of the first cylindrical section and where the first cylindrical section is intended to be executed on the lower section of concrete tower.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0037]
[0038]
[0039]
[0040]
[0041]
PREFERRED EMBODIMENT OF THE INVENTION
[0042] The manufacturing process of concrete towers for wind turbines of the present invention shall be detailed below.
[0043] The manufacturing process of concrete towers for wind turbines comprises: [0044] an execution stage of a first cylindrical section (1) of concrete tower by means of a first climbing formwork system (4); and [0045] an execution stage of a second cylindrical section (2) of concrete tower by means of the first climbing formwork system (4) so that an outer diameter of the second cylindrical section (2) is smaller than an outer diameter of the first cylindrical section (1), where the execution stage of the second cylindrical section (2) is carried out at a height greater than the execution stage of the first cylindrical section (1).
[0046] Preferably, the manufacturing process also comprises a construction stage of an intermediate transition section (3) before the execution stage of the second cylindrical section (2) of concrete tower, where the construction stages of the intermediate transition section (3) and execution stage of the second cylindrical section (2) of concrete tower are repeated until the second cylindrical section (2) is an upper cylindrical section of concrete tower. Next, a top section (7) of concrete tower shall be constructed as shall be explained below.
[0047] The manufacturing process comprises an assembly stage of the first climbing formwork system (4) on a lower section (10) of concrete tower manufactured prior to the execution stage of the first cylindrical section (1) of concrete tower, where, preferably, the lower section (10) of concrete tower is manufactured in situ on foundations (11) of the concrete tower.
[0048] In a first example of embodiment, the construction stage of the intermediate transition section (3) is carried out on the first cylindrical section (1). In this way, the intermediate transition section (3) and the first cylindrical section (1) are continuously executed, without horizontal or vertical joints. This construction stage of the intermediate transition section (3) on the first cylindrical section (1) can be carried out in two ways: [0049] Performing, before the construction stage of the intermediate transition section (3) on the first cylindrical section (1), an adaptation stage of the first climbing formwork system (4), for the in situ construction of the intermediate transition section (3), as shown in
[0054] In a second example of embodiment, the construction stage of the intermediate transition section (3) comprises a manufacturing stage of the intermediate transition section (3) in an area close to a base of the concrete tower and an installation stage of the intermediate transition section (3) manufactured in an area close to a base of the concrete tower, on the first cylindrical section (1), preferably using a crane (6) coupled to the first climbing formwork system (4). In this way, it avoids modifying the first climbing formwork system (4) and it dispenses with the concrete setting time as the intermediate transition element (3) is already prefabricated once it is installed on the first cylindrical section (1).
[0055] The manufacturing process of concrete towers for wind turbines comprises, after the construction stage of the intermediate transition section (3) and before the execution stage of the second cylindrical section (2), an adaptation stage of an outer formwork of the first climbing formwork system (4) to the outer diameter of the second cylindrical section (2) and preferably also an adaptation stage of an inner formwork of the first climbing formwork system (4) to an inner diameter of the second cylindrical section (2).
[0056] In a first example of embodiment, the construction stage of the top section (7) of concrete tower performed after the execution stage of the upper section of concrete tower is carried out on the upper cylindrical section of concrete tower. In this way, the upper cylindrical section and the top section (7) are continuously executed, without horizontal or vertical joints. This construction stage of the top section (7) on the upper cylindrical section can be carried out: [0057] Performing, before the construction stage of the top section (7) on the upper cylindrical section, an assembly stage of a second non-climbing formwork system for the in situ construction of the top section (7), where the second non-climbing formwork comprises an inner formwork and an outer formwork, where, preferably, the inner formwork and the outer formwork comprise at least one inclined section, so that they generate an inner surface (41) and an outer surface (42) which enable the connection of one coil of the wind turbine to the tower.
[0058] In a second example of embodiment, the construction stage of the top section (7) of concrete tower comprises a manufacturing stage of the top section (7) in an area close to a base of the concrete tower. Preferably, this construction stage of the top section (7) comprises an installation stage of the top section (7) manufactured in an area close to a base of the concrete tower, on the upper cylindrical section, preferably using a crane (6) coupled to the first climbing formwork system (4). In this way, it dispenses with the concrete setting time as the top section (7) is already prefabricated once installed on the upper cylindrical section.
[0059] The execution stage of the first cylindrical section (1) and/or the execution stage of the second cylindrical section (2) comprise the following sub-stages: [0060] a lifting sub-stage of a framework; [0061] a fixing sub-stage of the framework to the previously manufactured cylindrical section (1, 2); [0062] a closing sub-stage of the first climbing formwork system (4); [0063] a pouring sub-stage of the concrete inside the first climbing formwork system (4); [0064] an opening sub-stage of the first climbing formwork system (4); [0065] a climbing sub-stage of the first climbing formwork system (4);
where said sub-stages are repeated until all of the first cylindrical section (1) and/or all of the second cylindrical section (2), respectively, has been executed.
[0066] Preferably, the execution stage of the first cylindrical section (1) and/or the execution stage of the second cylindrical section (2) comprise a modification sub-stage of the inner formwork of the first climbing formwork system (4), so that the first cylindrical section (1) and/or the second cylindrical section (2) comprise at least one first sub-section with a first inner diameter (51) and a second sub-section with a second inner diameter (52), where the first inner diameter (51) of the first sub-section is smaller than the second inner diameter (52) of the second sub-section, as observed in
[0067] The first climbing formwork system (4) and/or the second climbing formwork system (5) comprise a set of hydraulic jacks each one of which has two climbing heads, an upper climbing head disposed on a moving part of the hydraulic jack and a lower climbing head disposed on a fixed part of the hydraulic jack.
[0068] Each climbing head comprises a system of pins which makes it possible to be temporarily fixed to a mast which is vertically disposed on the tower surface as a guide or to the tower itself, where the upper climbing head of each hydraulic jack is also solidly joined to a main platform of the first formwork system or of the second formwork system.
[0069] The vertical displacement of the first formwork system or of the second formwork system is achieved by means of the actuation of the hydraulic jack combined with the opening and/or closing of the climbing heads.
[0070] Below, the concrete tower for wind turbines of the present invention shall be described in detail.
[0071] The concrete tower comprises at least two sections of constant outer diameter, a first cylindrical section (1) and a second cylindrical section (2), where the second cylindrical section (2) is higher than the first cylindrical section (1) and where an outer diameter of the second cylindrical section (2) is smaller than an outer diameter of the first cylindrical section (1).
[0072] Preferably, the first cylindrical section (1) and the second cylindrical section (2) are both intended to be executed in situ by means of a first climbing formwork system (4).
[0073] Preferably, the concrete tower also comprises an intermediate transition section (3) disposed between the first cylindrical section (1) and the second cylindrical section (2). In a first example of embodiment, the intermediate transition section (3) is a section which is intended to be executed in situ, whilst in a second example of embodiment, the intermediate transition section (3) is a prefabricated concrete element either formed by a single piece or formed by several modules. Preferably, the prefabricated concrete element is intended to be manufactured in an area close to a base of the concrete tower.
[0074] The intermediate transition section (3) comprises an inner surface with at least one section with truncated cone geometry (31), preferably with an upper part and a lower part, where the section with truncated cone geometry has, in the lower part, a larger diameter which is greater than or equal to an inner diameter of the first cylindrical section (1), and in the upper part a smaller diameter which is smaller than or equal to an inner diameter of the second cylindrical section (2). Preferably, the transition section (3) comprises an outer surface with cylindrical (32) or truncated cone geometry. If the transition section (3) comprises an outer surface with truncated cone geometry, said outer surface comprises an upper part and a lower part, where the outer surface with truncated cone geometry of the transition section (3) has, in the lower part, a larger diameter which is equal to an outer diameter of the first cylindrical section (1), and in the upper part a smaller diameter which is greater than or equal to an outer diameter of the second cylindrical section (2).
[0075] The first cylindrical section (1) and/or the second cylindrical section (2) comprise at least one first sub-section (51) with a first inner diameter and a second sub-section (52) with a second inner diameter, where the second sub-section (52) is higher than the first sub-section (51) and where the first inner diameter of the first sub-section (51) is smaller than the second inner diameter of the second sub-section (52), as observed in
[0076] The concrete tower also comprises a top section (7) disposed on the second cylindrical section (2) or on an upper cylindrical section, where, preferably the top section (7) is a section which is intended to be executed in situ, or a prefabricated concrete element either formed by a single piece or formed by several modules. Preferably, the prefabricated concrete element is intended to be manufactured in the area close to the base of the concrete tower.
[0077] The concrete tower also comprises a lower section (10) which is lower than the first cylindrical section (1) where said lower section (10) of concrete tower has an outer diameter larger than the outer diameter of the first cylindrical section (1) and where the first cylindrical section (1) is intended to be executed on the lower section (10) of concrete tower. This lower section (10) may be cylindrical or truncated cone-shaped and is executed in situ preferably by means of non-climbing formworks.