Load-moving equipment
11427443 · 2022-08-30
Assignee
- PORTOCEL—TERMINAL ESPECIALIZADO DE BARRA DO RIACHO S.A. (Aracruz, BR)
- FORTEMAR NAVEGAÇÃO LTDA. (Aracruz, BR)
Inventors
Cpc classification
B66C1/62
PERFORMING OPERATIONS; TRANSPORTING
B60P1/00
PERFORMING OPERATIONS; TRANSPORTING
B65B27/12
PERFORMING OPERATIONS; TRANSPORTING
B66C1/427
PERFORMING OPERATIONS; TRANSPORTING
International classification
Abstract
The present invention relates to a load handling equipment and, more specifically, to an equipment for handling load bales tied with wire. The equipment of the present invention comprises at least one locating portion (11, 110, 1100), the locating portion (11, 110, 1100) comprising a gripping element (12, 120, 1200) formed by two gripping parts which move away and approximate to get the tie wire, wherein approaching and moving away the gripping parts is accomplished by means of a pneumatic cylinder (14, 140, 1400).
Claims
1. Load handling equipment configured to engage a tying means of a load bale, wherein the load handling equipment comprises: at least one locating portion comprising at least one gripping element formed by two gripping parts which move away and approach each other for gripping the tying means, wherein the approaching and moving away of the gripping parts is accomplished by means of at least one pneumatic cylinder, the locating portion further comprising a housing portion that protects the locating portion and a projecting column that projects vertically from the housing portion; and a sustaining structure having a tubular element configured to receive the projecting column of the support structure, wherein sliding the projecting column into the tubular element of the sustaining structure allows the vertical displacement of the housing portion.
2. The load handling equipment according to claim 1, wherein each locating portion comprises a structure with two side walls, wherein the gripping element is installed in each side wall of the locating portion.
3. The load handling equipment according to claim 2, wherein each gripping part is arranged on a respective side wall surface of the locating portion.
4. The load handling equipment according to claim 3, wherein a first pneumatic cylinder is arranged to drive the first gripping part and a second pneumatic cylinder is arranged to drive the second gripping part.
5. The load handling equipment according to claim 4, wherein the equipment comprises at least eight parallel beams which are connected to a central beam body extending substantially transverse to the parallel beams, each parallel beam supporting two support structures, each support structure having two locating portions and each locating portion having two gripping parts.
6. The load handling equipment according to claim 3, wherein the equipment comprises at least eight parallel beams which are connected to a central beam body extending substantially transverse to the parallel beams, each parallel beam supporting two support structures, each support structure having two locating portions and each locating portion having two gripping parts.
7. The load handling equipment according to claim 2, wherein the equipment comprises at least eight parallel beams which are connected to a central beam body extending substantially transverse to the parallel beams, each parallel beam supporting two support structures, each support structure having two locating portions and each locating portion having two gripping parts.
8. The load handling equipment according to claim 1, wherein each locating portion comprises a first locating part and a second locating part connected to a pneumatic cylinder, a first gripping part comprising a curved lower projection protruding from the first locating part and a second gripping part comprising a curved lower projection protruding from the second locating part; wherein the approaching and moving away of the gripping parts is accomplished by approaching and moving away the locating parts.
9. The load handling equipment according to claim 1, wherein the locating portion comprises two columns and the sustaining structure comprises two tubular elements, each of the tubular elements being configured to receive a respective column.
10. The load handling equipment according to claim 9, wherein the sustaining structure is coupled to each support structure.
11. The load handling equipment according to claim 10, wherein the equipment further comprises a receptacle connected to the housing portion, the receptacle comprising a first receptacle part hingedly coupled to the housing portion to protect the first locating portion and a second receptacle part hingedly coupled to the housing portion to protect the second gripping part.
12. The load handling equipment according to claim 1, wherein the equipment comprises at least eight parallel beams which are connected to a central beam body extending substantially transverse to the parallel beams, each parallel beam supporting two support structures, each support structure having two locating portions and each locating portion having two gripping parts.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1) The present invention will hereinafter be described in more detail based on exemplary embodiments shown in the drawings. The figures show:
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
(17)
DETAILED DESCRIPTION OF THE FIGURES
(18)
(19) The equipment of the present invention may be used for lifting and moving load bales such as, for example, cellulose bales. Load bales are packets of material that are tied with a tying means such as, for example, steel strings or wires.
(20) In the first embodiment, the equipment comprises a support structure 10 supporting a locating portion 11 with at least one gripping element 12 and at least one pneumatic cylinder 14.
(21) The locating portion 11 comprises a structure with two side walls wherein a gripping element 12 is installed on each side wall 11a of the locating portion 12.
(22) The gripping element 12 is formed by two gripping parts 12a and 12b, and each gripping part 12a and 12b is arranged on a side wall surface 11a of locating portion 12. Thus, as best illustrated in
(23) As best illustrated in
(24) As best illustrated in
(25) The central beam 20 is preferably configured to engage with any type of hoisting equipment such as cranes or arms. Thus, the handling equipment of the present invention can be easily coupled to the handling equipment known in the prior art.
(26)
(27) For lifting the bale, the central beam 20 is lowered so that the beams 19, support structures 10 and locating portions 11 are also lowered. The gripping parts 12a, 12b are lowered in a separate position, that is, open to each other in an open position. In an open position, the gripping parts are in a higher position than the lower edge of the walls 11a, so that the edges may be at the top of the bale without the gripping parts touching the bale in that moment.
(28) With the equipment lowered, the gripping parts 12a, 12b are driven by the hydraulic cylinders to close, so that they approach each other. As in the first embodiment the gripping parts are in the form of opposite hooks, during the approach the thinner parts of the hooks pass close to the bale and lift the tying means so that it slides over the inner parts of the opposite hooks, being “grabbed” by the gripping parts. At this point, the wire is brought up into the space of cutout 11b of the side wall. Once the corresponding tying means are “grabbed”, the equipment can be lifted.
(29) As shown in
(30)
(31)
(32) In the second embodiment, the equipment comprises a support structure 100 supporting a locating portion 110 with at least one gripping element 120 and at least one pneumatic cylinder 140.
(33) As best illustrated in
(34) The gripping element 120 is formed by two gripping parts 120a and 120b, each gripping part protruding from one of the locating parts, like a curved wall projecting downwardly toward the other locating part. Thus, when the locating part is moved by the cylinder, the corresponding gripping part is also moved, so that when the locating parts 110a and 110b are close, the two gripping parts 120a, 120b approach to pick up the wires that tie the bales.
(35) The locating portion 110 further comprises two pusher elements 130a and 130b (one of which is best illustrated in
(36) As best illustrated in
(37) Preferably, the pneumatic cylinder 140 is coupled to the first and second locating parts by means of forks 140a (see
(38) The equipment of the present invention may further comprise a sustaining structure 170, better illustrated in
(39) The sustaining structure may further comprise a beam 190 or other reinforcement element which enables the equipment to be integrated with other equipment or that may support an installation or hoisting structure.
(40)
(41)
(42) In the embodiment shown in
(43) In this embodiment, locating portions 1100 are formed by first and second locating parts 1100a and 1100b which are driven for opening and closing by means of a pneumatic system (see
(44) As best illustrated in
(45) As best seen in
(46) A receptacle 1300 for the locating parts 1100a and 1100b is connected to the housing part 1500. As best illustrated in
(47) The pneumatic cylinder 1400 is coupled to the housing by means of a bracket 1400a (see
(48) The load handling equipment of the present invention weighs up to about 6 tons and is capable of supporting a load of up to about 32 tons. In addition, the loading elements can be driven (closed or open) by the load handling crane operator or the ship overhead crane operator.
(49) Thus, having described examples of embodiments of the present invention, it should be understood that the scope of the present invention encompasses other possible variations and is limited only by the content of the appended claims, including the possible equivalents thereof.