Facility for processing steel
11429916 · 2022-08-30
Assignee
Inventors
Cpc classification
B65G1/16
PERFORMING OPERATIONS; TRANSPORTING
B66C13/005
PERFORMING OPERATIONS; TRANSPORTING
B66C17/20
PERFORMING OPERATIONS; TRANSPORTING
G06Q10/08
PHYSICS
B65G57/20
PERFORMING OPERATIONS; TRANSPORTING
International classification
G06Q10/08
PHYSICS
B66C13/00
PERFORMING OPERATIONS; TRANSPORTING
B65G57/20
PERFORMING OPERATIONS; TRANSPORTING
Abstract
Facilities for processing steel. One facility includes a line for producing packages; a plurality of stackable cassettes for receiving packages; a splitter subfacility; automated transfer apparatus; and an automated overhead crane. The line may be a slitting line with the packages being coils of steel, or a cut-to-length line with the packages being stacks of steel sheets. A premises of the facility comprises a loading area in which packages from the line are loaded into cassettes, a storage area in which cassettes are stored, and a transition zone including at least one transfer position. The automated transfer apparatus moves packages and/or cassettes between the transfer position and the splitter subfacility. The automated overhead crane moves cassettes between the storage area, the loading area, and the transition zone.
Claims
1. A facility comprising: a cut-to-length line for producing packages, the packages being stacks of steel sheets; a plurality of stackable cassettes, each cassette having a plurality of apertures in a base thereof and being adapted to receive at least one package; premises including a loading area in which packages from the line are loaded into cassettes, a storage area in which cassettes are stored and a transition zone including at least one transfer position; a splitter subfacility for: receiving a contents of a cassette, removing and packaging for shipment at least some of such contents and returning the remainder; or receiving a cassette, removing and packaging for shipment at least some of such contents and returning the cassette; automated transfer apparatus for moving the contents of a cassette disposed at the transfer position to the splitter subfacility and for moving a package from the splitter subfacility to a cassette in the transfer position, the automated transfer apparatus comprising: a conveyor having a plurality of rollers over which packages pass to and from the splitter subfacility, and a lifter having a plurality of rollers, the rollers having a lowered position whereat, when a cassette, loaded with a package, is at the transfer position, the rollers are beneath the package, and having a raised position, whereat the rollers protrude through the apertures of the cassette to form an extension of the conveyor adapted to deliver packages to the conveyor and to receive packages from the conveyor; and an automated overhead crane extending over the storage area, the loading area and the transition zone and adapted to move cassettes therebetween.
2. A facility according to claim 1, further comprising a manual overhead receiving crane for moving packages from the line to the loading area and wherein the facility is adapted to arrest movement of the automated overhead crane in the loading area, if a human is in the loading area.
3. A facility according to claim 2, further comprising a receiving area for receiving packages from the line and wherein the manual overhead crane is adapted to move packages from the receiving area to the loading area.
4. A facility according to claim 1, further comprising: a bay for receiving trucks; and a manual overhead shipping crane for moving packages from the splitting subfacility to the bay.
5. A facility according to claim 1, further comprising: a shipping area; and a manual overhead shipping crane for moving packages from the splitting subfacility to the shipping area.
6. A facility according to claim 1, wherein each cassette defines a hollow and defines, at each end of the hollow, an aperture, the aperture providing for communication between the rollers of the lifter when in the raised position and the rollers of the conveyor.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
DETAILED DESCRIPTION
(14) A facility 20 constructed according to an exemplary embodiment of the invention is shown in
(15) Premises
(16) The premises will be seen to include a package receiving area 22, a loading area 24, a cassette storage area 26, a shipping area 28, a transition zone 30 having at least one transfer position 32 and a truck bay 34.
(17) Equipment
(18) The equipment will be seen to comprise a line 36, a splitter subfacility 38, a manual overhead receiving crane 40, an automated storage crane 42, a manual overhead shipping crane 44 and an automated transfer apparatus 46.
(19) The line 36 is a cut-to-length line for producing packages in the form of stacks of steel sheets from coils of steel.
(20) The splitter subfacility 38 in this embodiment is defined by a pair of lifters 48 and a pair of conveyors 50.
(21) The lifter will be seen in isolation in
(22) The manual overhead receiving crane extends from the receiving area 22 to the loading area 24 as indicated by dotted line 40′.
(23) The automated overhead receiving crane 42 extends over the cassette storage 26 area, the transition zone 30 and the loading area 24 as indicated by dotted line 42′.
(24) The manual overhead shipping crane 44 extends over the conveyors 50,50 of the splitter subfacility 38, the shipping area 28 and the truck bay 34, as indicated by dotted line 44′.
(25) The automated transfer apparatus 46 includes a pair of lifters 48 as aforedescribed, a plurality of conveyors 50 as aforedescribed and a pair of turntables 52. The turntables (not shown in detail) will be understood to function generally similarly to the conveyors but the plurality of rollers are adapted for rotation about a vertical axis. The lifters are each positioned at one of the transfer positions. One of the turntables is provided for each lifter. One of the conveyors is provided for each lifter to couple said each lifter to the turntable provided therefor. A further one of the conveyors extends between the turntables and the final of the conveyors extends to the lifters of the splitter subfacility from one of the turntables.
(26) Cassette
(27) As seen in
(28) Receiving
(29) In operation, the cut-to-length line 36 delivers packages (stacks of sheets) to the receiving area 22. In this embodiment, packages are banded for transport in this area.
(30) Loading
(31) Banded packages are transported by overhead crane 44 to an empty cassette in the loading area 24. Banding is manually removed in this location.
(32) Storage
(33) The automated overhead crane 42 transfers empty cassettes to the loading area 24 and loaded cassettes to the storage area 26. Access control is provided around the perimeter of the loading area; humans cannot enter the loading area when the automated crane is overhead and the overhead crane cannot overly the loading area when humans are therewithin.
(34) Splitting
(35) The contents of a cassette are split by delivery, by the automated crane, of the cassette to one of the transfer areas 32 in the transition zone, as shown by
(36) In this embodiment, splitting is done manually, by moving sheets from the package to a pallet. To minimize effort, this is done through a pair of adjacent lifters, to minimize the elevation difference between the sheet being removed from the package and the pallet onto which the sheet is to be loaded. Once the pallet has been suitably loaded, the pallet is passed to the conveyors 50 within reach of the manual overhead crane, banded and removed by the overhead crane to a truck in the bay 34 or the shipping area 28, as appropriate. If only a portion of the cassette has been loaded onto a pallet, the remainder is returned to a cassette, using a reversal of the process indicated above, and then returned to storage. If the intent of the transfer was to fully empty the cassette, the cassette from which the material was removed is automatically stored by the overhead crane either within the transition zone or the storage area.
(37) It has been found, surprisingly, that if the line is operated with a view to maximum throughput, the production costs benefit outweigh the incremental costs of carrying the inventory and splitting the production, resultant from the relatively low amounts of floor space occupied by the inventory and the relatively low cost at which it can be accessed by virtue of the automated crane.
(38) Whereas a specific embodiment has been hereinbefore described, it will be evident that variations are possible.
(39) For example, only, whereas the exemplary embodiment handles stacks of steel, the invention can be embodied for use with a slitter by providing: cassettes that handle multiple coils, as shown by
(40) As an alternative to the cassettes above, split coils could also be stored in stacks 70, as shown in
(41) Other variations can also be provided, for example, secondary inspection could be provided by providing another access controlled area, similar to the loading area.
(42) Accordingly the invention should be understood to be limited only by the accompanying claims, purposively construed.