The present invention discloses a method for constructing inner dump type strip mine pit bottom reservoirs section by section, specifically including the following steps: S1: processing end slopes: discarding clay at a lowest step of an inner waste dump of a strip mine; S2: discharging concrete to slope faces of lowest steps of the end slopes on two sides of a pit bottom; S3: sealing the bottom; S4: discarding gravel into a pit of the strip mine; S5: laying geotextile; S6: re-adopting clay on the lowest steps of the end slopes of the inner waste dump, so as to form a reservoir sealing isolation layer; S7: constructing a plurality of reservoirs step by step in an advancing direction of the strip mine; S8: storing water resources: completing installation of water storage wells; S9: completing installation of water fetching wells; S10: storing water resources.
Claims
1. A method for constructing inner dump type strip mine pit bottom reservoirs section by section, comprising the procedures of single reservoir construction, multi-reservoir section-by-section construction and water resource storage, and specifically comprising the following steps: S1: processing side slopes: discarding 5-10-meter-thick clay at a lowest step of an inner waste dump (1) of a strip mine when the width of a constructed pit bottom (4) of the strip mine reaches about 150-300 m, so as to form an inner waste dump isolation layer (2), and stopping advancing of the inner waste dump (1) of the strip mine after the inner waste dump isolation layer (2) is formed; S2: after processing the side slopes, discharging concrete to slope faces of lowest steps (3) of the end slopes on two sides of the pit bottom (4) of the strip mine by adopting a guniting mode, so as to form an end slope isolation layer (6), thus completing end slope processing; S3: carrying out concrete guniting on the pit bottom (4) of the strip mine, and filling the pit bottom with the concrete and performing compaction to seal the bottom, so as to form a pit bottom isolation layer (7), wherein the laying thickness is 2-5 m, a slope is formed from the surface of the pit bottom isolation layer (7) to the end slopes on the two sides, and the pit bottom (4) is relatively high in the middle, and relatively low near the end slopes on the two sides; S4: after sealing the bottom, starting discarding gravel (8) into a pit of the strip mine, wherein the discarded gravel is massive gravel having larger pores that is stripped from the strip mine and does not disintegrate while touching water, and the height of the discarded gravel (8) is the height of the lowest steps (3) of the end slopes of the strip mine; S5: during gravel (8) discarding, laying geotextile when the gravel reaches the height of the lowest steps (3) of the end slopes, so as to form a roof isolation layer (9), and completing capping work after the roof isolation layer (9) is formed, wherein waste is normally dumped in the upper inner waste dump (1) at the same time; S6: with gradual forward advancement of the pit of the strip mine, re-adopting clay on the lowest steps (3) of the end slopes of the inner waste dump (1) while it reaches 150-300 m, so as to form a reservoir sealing isolation layer (10), wherein the construction of a single pit bottom (4) reservoir is completed, namely, reservoir sealing is realized, and a plurality of sets of moisture sensors are arranged symmetrically on two sides of each isolation layer to monitor soil moisture in the location in real time; S7: after the completion of construction of the single reservoir, repeating the above steps: constructing a plurality of reservoirs step by step along with advancement of the strip mine in an advancing direction of the strip mine, so as to form section-by-section reservoirs; S8: then storing water resources: firstly completing installation of water storage wells (11): during the construction of the single reservoir, directionally drilling holes in the end slopes on the two sides of the strip mine obliquely downward from the surface, and burying water pipes, wherein one end of each of the drill holes is located on the surface, and the other end of the drill hole is located in the lower part of the roof isolation layer (9) of the reservoir; S9: then continuing to complete installation of water fetching wells (12): during the construction of the single reservoir, directionally drilling holes in the end slopes on the two sides of the strip mine obliquely downward from the surface to form the water fetching wells (12), and installing pumping units, wherein one end of each of the water fetching wells (12) is located on the surface of the strip mine, and the other end of the water fetching well is located in the upper part of the pit bottom isolation layer (7) of the pit bottom (4) reservoir and near the end slopes; and S10: finally storing the water resources: after the completion of construction of the single reservoir, injecting the water resources into the pit bottom (4) reservoir via the water storage wells (11), wherein the water resources are stored in the pores of the gravel, and when water is needed, the water resources are pumped to the surface via the water fetching wells (12).
2. The method for constructing inner dump type strip mine pit bottom reservoirs section by section according to claim 1, wherein the pit bottom isolation layer (7) in step S3 is capable of being replaced with compacted clay.
3. The method for constructing inner dump type strip mine pit bottom reservoirs section by section according to claim 1, wherein the slope in step S3 is set as a gradient of 0.3%.
4. The method for constructing inner dump type strip mine pit bottom reservoirs section by section according to claim 1, wherein the guniting thickness of the end slope isolation layer (6) in step S2 is 20-50 cm.
5. The method for constructing inner dump type strip mine pit bottom reservoirs section by section according to claim 1, wherein during gravel (8) discarding in step S5, the laying height of the gravel is capable of being adjusted to a height higher than the lowest steps (3) of the end slopes, and at this time, the height of the corresponding isolation layer is also increased accordingly, so that the sealing property of the reservoir is ensured.
6. The method for constructing inner dump type strip mine pit bottom reservoirs section by section according to claim 2, wherein during gravel (8) discarding in step S5, the laying height of the gravel is capable of being adjusted to a height higher than the lowest steps (3) of the end slopes, and at this time, the height of the corresponding isolation layer is also increased accordingly, so that the sealing property of the reservoir is ensured.
7. The method for constructing inner dump type strip mine pit bottom reservoirs section by section according to claim 2, wherein the slope in step S3 is set as a gradient of 0.3%.
8. The method for constructing inner dump type strip mine pit bottom reservoirs section by section according to claim 2 wherein the guniting thickness of the end slope isolation layer (6) in step S2 is 20-50 cm.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0023]
[0024]
[0025]
[0026]
[0027] In the figures, 1 denotes an inner waste dump, 2 denotes an inner waste dump isolation layer, 3 denotes a lowest step of an end slope, 4 denotes a pit bottom, 5 denotes a stope, 6 denotes an end slope isolation layer, 7 denotes a pit bottom isolation layer, 8 denotes gravel, 9 denotes a roof isolation layer, 10 denotes a reservoir sealing isolation layer, 11 denotes a water storage well, and 12 denotes a water fetching well.
DETAILED DESCRIPTION OF THE INVENTION
[0028] The present invention will be further described in detail below with reference to the accompanying drawings.
[0029] As shown in
[0030] S1: Side slopes are processed. 5-10-meter-thick clay is discarded at a lowest step of an inner waste dump 1 of a strip mine when the width of a constructed pit bottom 4 of the strip mine reaches about 150-300 m, so as to form an inner waste dump isolation layer 2. Advancing of the inner waste dump 1 of the strip mine is stopped after the inner waste dump isolation layer 2 is formed.
[0031] S2: After processing the side slopes, concrete is discharged to slope faces of lowest steps 3 of the end slopes on two sides of the pit bottom 4 of the strip mine by adopting a guniting mode, so as to form an end slope isolation layer 6, thus completing end slope processing. Preferably, the guniting thickness of the end slope isolation layer 6 is 20-50 cm. Within this range, not only can isolation of water resources be ensured, but also the usage amount of the concrete can be reduced, and thus the production cost is reduced.
[0032] S3: As shown in
[0033] S4: After sealing the bottom, discarding gravel 8 into a pit of the strip mine is started. The discarded gravel is massive gravel having larger holes that is stripped from the strip mine and does not disintegrate while touching water. The height of the discarded gravel 8 is the height of the lowest steps 3 of the end slopes of the strip mine.
[0034] S5: During gravel 8 discarding, geotextile is laid when the gravel reaches the height of the lowest steps 3 of the end slopes, so as to form a roof isolation layer 9. Capping work is completed after the roof isolation layer 9 is formed. Waste is normally dumped in the upper inner waste dump 1 at the same time. If a larger storage capacity of water resources is needed, the discarded gravel 8 may be laid to a height higher than the lowest steps 3 of the end slopes so as to increase the water storage capacity. At this time, the height of the corresponding isolation layer is also increased accordingly, so that the sealing property of the reservoir is ensured.
[0035] S6: As shown in
[0036] S7: After the completion of construction of the single reservoir, the above steps are repeated. A plurality of reservoirs are constructed step by step along with advancement of the strip mine in an advancing direction of the strip mine, i.e. a direction from the inner waste dump 1 to a stope 5, so as to form section-by-section reservoirs.
[0037] S8: Then the water resources are stored. Firstly installation of water storage wells 11 is completed. During the construction of the single reservoir, holes are directionally drilled in the end slopes on the two sides of the strip mine obliquely downward from the surface. Water pipes are buried. One end of each of the drill holes is located on the surface, and the other end of the drill hole is located in the lower part of the roof isolation layer 9 of the reservoir.
[0038] S9: Then installation of water fetching wells 12 is continued to be completed. During the construction of the single reservoir, holes are directionally drilled in the end slopes on the two sides of the strip mine obliquely downward from the surface to form the water fetching wells 12. Pumping units are installed. One end of each of the water fetching wells 12 is located on the surface of the strip mine, and the other end of the water fetching well is located in the upper part of the pit bottom isolation layer 7 of the pit bottom 4 reservoir and near the end slopes.
[0039] S10: Finally the water resources are stored. After the completion of construction of the single reservoir, the water resources are injected into the pit bottom 4 reservoir via the water storage wells 11. The water resources are stored in the pores of the gravel. When water is needed, the water resources are pumped to the surface via the water fetching wells 12. The slope of the pit bottom isolation layer 7 ensures that the water resources can be gathered to the vicinity of the end slopes as much as possible, thereby ensuring an effect of storing and fetching water, as shown in
[0040] The construction principle of the method for constructing the reservoir section by section according to the present invention is as follows: according to the above steps, starting from the pit of strip mine, after excavation, the inner waste dump isolation layer 2, the end slope isolation layer 6, and the pit bottom isolation layer 7 are gradually formed through concrete guniting or clay discarding; then the geotextile is adopted for capping; then the reservoir sealing isolation layer 10 is constructed to complete the construction of the single reservoir; and the plurality of reservoirs are constructed step by step in the advancing direction of the inner waste dump 1, i.e. the direction towards the stope 5. The water resources are introduced via the water storage wells 11, temporarily stored in the reservoir, and pumped out via the water fetching wells 12 when needed. There is less water loss throughout the process, which effectively reduces the waste of the water resources in coal mine areas in northern China.