LNG delivery system with saturated fuel reserve
11248747 · 2022-02-15
Assignee
Inventors
Cpc classification
F17C3/00
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2225/0123
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2223/033
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C7/04
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2227/04
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2205/0332
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2227/0121
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2201/054
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2203/0629
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2225/036
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2270/0168
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2227/0107
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2265/066
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
Y02T10/30
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
F17C2203/0391
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2250/01
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2223/0161
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2223/047
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2225/035
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2201/056
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F17C2201/035
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
International classification
Abstract
A cryogenic fluid delivery system includes a main tank system with a main tank adapted to contain a first supply of cryogenic liquid, and reserve tank system with reserve tank adapted to contain a second supply of cryogenic liquid. A pressure building circuit is adapted to delivery vapor to the head space of the main tank to build pressure in the main tank and a fuel delivery line supplies cryogenic fuel from either the main tank or the reserve tank to a use device. The reserve tank stores saturated cryogenic fuel that is delivered to the use device via the fuel delivery line while the cryogenic liquid in the main tank is being saturated. The fluid delivery system automatically switches to delivering cryogenic fuel from the main tank to the use device via the fuel delivery line upon saturation of the cryogenic liquid in the main tank.
Claims
1. A cryogenic fluid delivery system comprising: a main tank system, the main tank system including a main tank adapted to contain a first supply of cryogenic liquid, the main tank including a head space adapted to contain a vapor, the main tank system further including a main liquid withdrawal line and a main economizer circuit in communication with the main liquid withdrawal line and the head space of the main tank, the main economizer circuit including a main regulator configured to open to direct the vapor from the head space of the main tank to the main liquid withdrawal line when a pressure in the main tank rises above a predetermined main tank maximum pressure; a reserve tank system, the reserve tank system including a reserve tank adapted to contain a second supply of cryogenic liquid, the reserve tank including a head space adapted to contain a vapor, the reserve tank system further comprising a reserve liquid withdrawal line and a reserve economizer circuit in communication with the reserve liquid withdrawal line and the head space of the reserve tank, the reserve economizer circuit including a reserve regulator configured to open to direct the vapor from the head space of the reserve tank to the reserve liquid withdrawal line when a pressure in the reserve tank rises above a predetermined reserve tank maximum pressure, wherein the predetermined reserve tank maximum pressure is less than the main tank maximum pressure; a pressure building circuit adapted to deliver vapor to the head space of the main tank to build pressure in the main tank; a fuel delivery line; at least one fuel selection valve in communication with the fuel delivery line, wherein the main tank is in fluid communication with a use device through the main liquid withdrawal line and the fuel delivery line and the reserve tank is not in fluid communication with the use device through the fuel delivery line when the at least one fuel selection valve is in a first state and the reserve tank is in fluid communication with the use device through the main liquid withdrawal line and the fuel delivery line and the main tank is not in fluid communication with the use device when the at least one fuel selection valve is in a second state; a reserve fill line in fluid communication with the reserve tank and the main liquid withdrawal line of the main tank; wherein said reserve fill line, said reserve liquid withdrawal line, and said fuel delivery line are configured to deliver a liquid portion of the first supply of the cryogenic liquid from the main tank to the reserve tank via the reserve fill line as the cryogenic liquid flows from the reserve tank to the use device via the reserve liquid withdrawal line and the fuel delivery line when the at least one fuel selection valve is in the second state.
2. The system as in claim 1, further comprising: a main vaporizer positioned within the main liquid withdrawal line; and wherein the pressure building circuit comprises a flow inducer and a gas return pathway in fluid communication with an outlet of the main vaporizer and the head space of the main tank, wherein the flow inducer causes gas to flow from the main vaporizer to the head space of the main tank.
3. The system as in claim 1, further comprising a controller, a main tank pressure sensor, a reserve tank pressure sensor, a main tank liquid level sensor and a reserve tank liquid level sensor configured to sense fill levels and pressure levels of each of the main tank and the reserve tank and automatically switch the at least one fuel selection valve between the first state and the second state based on the sensed fill levels and pressure levels.
4. The system as in claim 3, wherein the controller is configured to automatically switch the at least one fuel selection valve from the second state to the first state when the main tank reaches a predetermined pressure as determined by the main tank pressure sensor and to automatically switch the at least one fuel selection valve from the first state to the second state when a liquid level in the main tank drops to a predetermined main tank liquid level as determined by the main tank liquid level sensor.
5. The system as in claim 1, wherein at least one of the main tank and the reserve tank is formed or an outer tank and an inner tank inside the outer tank with a vacuum space between the outer tank an inner tank.
6. The system as in claim 1, wherein a main biasing relief valve is included in the main liquid withdrawal line to cause the main economizer circuit to be a path of least resistance out of the main tank when the main regulator is open.
7. The system as in claim 6, wherein a main small orifice is located in parallel with the main biasing relief valve to allow back flow to the main tank during transient periods of high to low use.
8. The system as in claim 1 wherein a reserve biasing relief valve is included in the reserve liquid withdrawal line to cause the reserve economizer circuit to be a path of least resistance out of the reserve tank when the reserve regulator is open.
9. The system as in claim 8, wherein a reserve small orifice is located in parallel with the reserve biasing relief valve in the reserve liquid withdrawal line to allow back flow to the reserve tank during transient periods of high to low use.
10. The system of claim 3 wherein the controller is configured to automatically switch the at least one fuel selection valve from the second state to the first state when the main tank reaches a predetermined pressure as determined by the main tank pressure sensor and a liquid level within the reserve tank drops to a predetermined reserve tank liquid level as determined by the reserve tank liquid level sensor.
11. The system of claim 2 wherein the reserve fill line is in liquid communication with the main liquid withdrawal line between the main tank and an inlet of the main vaporizer.
12. The system of claim 1 further comprising a check valve positioned within the reserve fill line, said check valve configured to prevent flow from the reserve tank towards the main.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1)
(2)
(3)
DETAILED DESCRIPTION
(4) Before the present subject matter is further described, it is to be understood that this subject matter described herein is not limited to particular embodiments described, as such may of course vary. It is also to be understood that the terminology used herein is for the purpose of describing a particular embodiment or embodiments only, and is not intended to be limiting. Unless defined otherwise, all technical terms used herein have the same meaning as commonly understood by one skilled in the art to which this subject matter belongs.
(5)
(6) With reference still to
(7) As shown in
(8)
(9) In the embodiment of
(10) The reserve tank 62 includes an economizer circuit 44 a vapor line or tube 80, which communicates with the vapor space 76. The vapor tube 80 includes an economizer regulator 78, which is set at a predetermined pressure threshold. A liquid line 64 communicates with liquid 66 in the tank 62. When the pressure in tank 62 exceeds the set point of regulator 78, the vapor 76 may be withdrawn through the vapor line 70 and to the use device through the fuel line 75. This results in a lowering of the pressure in the tank 62. A biasing relief valve 82 is included in the liquid line 64 to cause the economizer circuit 74 to automatically be the path of least resistance out of the tank 62 when the regulator 78 is open. A small orifice 84 is located in parallel with the relief valve 72 to allow back flow to the tank during transient periods of high to low use
(11) With reference still to
(12)
(13) In use, the reserve tank(s) retain a supply of previously saturated liquid. When the use device is filled, only the main tank(s) is filled with cold liquid. The reserve tank contains enough fuel to drive the use vehicle until the main tank becomes saturated. Pursuant to one method, the reserve tank is maintained in a normally empty state such that the reserve tank is empty upon arrival to the fuel station. Upon arrival at a fuel station, the liquid in the main tank is manually emptied into the reserve tank. The main tank is then filled with cold liquid at the fuel station. The use device uses fuel from the reserve tank while the main tank is saturated. When the reserve tank is nearly empty, the system switches to using fuel from the main tank for the use device. The use device can then operate until the main tank is nearly empty.
(14) In an alternate process, the reserve tank is maintained in a normally full state such that the reserve tank is full of liquid upon arrival to a fuel station. The main tank is then filled with cold liquid fuel station. The main tank is saturated while the use device uses fuel from the reserve tank. When the reserve tank is nearly empty, the use device switches to using fuel from the main tank. As the main tank becomes fully saturated, the reserve tank refills with liquid from the main tank. When the reserve tank is full, the feeling of the reserve tank is stopped and the use device continues while only using fuel from main tank. This device can then drive until the main tank is nearly empty.
(15) An example setup and operation of the described system for fueling an engine is now described using numerical values as non-limiting examples. In an example embodiment, the system for fueling an engine needs 10 barg inlet pressure. The economizer 38 has a set pressure of 12 barg and the economizer 78 has a set pressure of 11 barg. When the truck arrives at the fuel station, the reserve tank is −90% full of liquid saturated at 11 barg and the main tanks are nearly empty, but the liquid that remains is saturated at 11 barg. The main tanks are filled with cold liquid saturated at, for example, 4 barg. After the fill, all tanks are full; the main tank is full of liquid saturated at just above 4 barg, and the reserve tank is full of liquid saturated at 11 barg. The valve 10 is in a closed state and the valve 50 is in an open state.
(16) Continuing the example, the truck can operate using the liquid in the reserve tank 62 for the first 30 minutes or 1 hour of driving. During this time, the pressure building system 55 or 27 is acting on the main tank alone to build pressure and saturate the liquid in the main tank to 11 barg. By the time the reserve tank 62 is nearly empty, the main tank has sufficient pressure to be able to provide a constant source of high pressure to the engine. The control valve 10 will then open and the valve 50 will close. Then the pressure building system will build pressure up to 12 barg. When the liquid level in the main tank 22 falls to a predetermined threshold (such as, for example 60-70%), then the valve 50 will open and the valve 10 will close. This causes the reserve tank 62 to refill from the main tank 22 while providing high pressure gas to the engine. When the reserve tank 62 is full, the valve 50 will close and the valve 10 will open and the pressure building system will only maintain 11 barg. Then the vehicle will drive for the remainder of the fuel in the main tanks.
(17) In an embodiment, further control can be provided to keep the reserve tank pressure down while driving by strategically switching to use the reserve tank and also keep it filled to a desired level. In this embodiment, the system includes a control system, including a controller indicated at 90, main tank and reserve tank pressure sensors indicated at 92a and 92b and main tank and reserve tank liquid level sensors indicated at 94a and 94b in
(18) In any of the embodiments, multiple main tanks can be connected in parallel, sharing a fill connection, sharing return gas line 53, and sharing withdrawal line 28.
(19) Although embodiments of various methods and devices are described herein in detail with reference to certain versions, it should be appreciated that other versions, embodiments, methods of use, and combinations thereof are also possible. Therefore the spirit and scope of the appended claims should not be limited to the description of the embodiments contained herein.