FOUNDATION FOR THE SUPPORT OF A STRUCTURE AND METHOD OF INSTALLATION
20170321388 · 2017-11-09
Inventors
Cpc classification
E04H12/20
FIXED CONSTRUCTIONS
International classification
E04H12/20
FIXED CONSTRUCTIONS
E04H12/34
FIXED CONSTRUCTIONS
Abstract
A method for installing a foundation in a ground for supporting a structure thereon, the method comprising the drilling of a main column borehole in the ground along an axis parallel to an axis of a force exerted by a load of the structure, inserting a main column into the main column borehole, drilling at least one anchor borehole at an angle away from the main column, inserting an anchor into each of the at least one anchor borehole, injecting a sealant into each of the at least one anchor borehole, after the sealant is dry securing a base to a top of the main column, securing to the base and placing under tension each anchor inserted into each of the at least one anchor borehole, the tension being such as to counteract radial forces to be induced by the structure to a longitudinal axis of the main column.
Claims
1. A method for installing a foundation in a ground for supporting a structure thereon, the method comprising: a) drilling of a main column borehole in the ground along an axis parallel to an axis of a force exerted by a load of the structure; b) inserting a main column into the main column borehole; c) drilling at least one anchor borehole at an angle away from the main column; d) inserting an anchor into each of the at least one anchor borehole; e) injecting a sealant into each of the at least one anchor borehole; f) letting the sealant dry; g) securing a base to a top of the main column; h) securing to the base and placing under tension each anchor inserted into each of the at least one anchor borehole, the tension being such as to counteract radial forces to be induced by the structure to a longitudinal axis of the main column.
2. A method in accordance with claim 1, wherein the placing under tension of each anchor inserted into each of the at least one anchor borehole is performed using a tension application mechanism that allows for power to be simultaneously applied on each anchor.
3. A method in accordance with claim 1, wherein the sealant is a slurry of 30 MPA concrete with expander.
4. A method in accordance with claim 1, wherein the main column borehole is drilled into a bedrock under the ground to a depth such as to support the load.
5. A method in accordance with claim 1, wherein the main column borehole is drilled to a depth such that a soil composing the ground is sufficiently dense so as to support the load.
6. A method in accordance with claim 1, wherein the main column is selected from a group consisting of a hollow tube, a solid cylinder and an H-beam.
7. A method in accordance with claim 1, wherein the main column is hollow and further comprising filling the main column with a dense and incompressible material, thereby increasing the compressive strength of the main column.
8. A method in accordance with claim 7, wherein the dense and incompressible material is a slurry of 30 MPA concrete with expander.
9. A method in accordance with claim 1, further comprising the step of filling a clearance between the main column and a wall of the main column borehole with a sealant.
10. A method in accordance with claim 9, wherein the sealant is a slurry of 30 MPA concrete with expander.
11. A method in accordance with claim 1, wherein the at least one anchor borehole is drilled into a bedrock under the ground to a depth so as to support the tension for counteracting the radial forces induced by the structure.
12. A method in accordance with claim 1, wherein the at least one anchor borehole is drilled to a depth such that a soil composing the ground is sufficiently dense so as to support the tension for counteracting the radial forces induced by the structure.
13. A method in accordance with claim 1, wherein the anchor borehole angle is between 15° and 60°.
14. A method in accordance with claim 1, wherein the anchor borehole angle is determined by radial forces induced by the structure to be supported by foundation.
15. A method in accordance with claim 1, wherein a plurality of anchor boreholes are drilled, each of the plurality of anchor boreholes being drilled at an angle away from an adjacent one of the plurality of anchor boreholes.
16. A method in accordance with claim 15, wherein the angles between adjacent anchors of the plurality of anchor boreholes are such that the anchors are equidistant.
17. A method in accordance with claim 15, wherein the angles between adjacent anchors are such as to accommodate the radial forces induced by the structure to be supported by foundation.
18. A kit for installing a foundation in a ground for supporting a structure thereon, the kit comprising: a main column; a base configures to be secured to a top end of the main column and to support the structure; a securing element associated with each of the at least one anchor; each securing element being configured to place under tension and secure the associated anchor to the base.
19. A kit in accordance with claim 18, further comprising a tension application mechanism allowing for power to be simultaneously applied on each of the at least one anchor when secured to the base.
20. A kit in accordance with claim 18, wherein the main column is selected from a group consisting of a hollow tube, a solid cylinder and an H-beam.
Description
BRIEF DESCRIPTION OF THE FIGURES
[0026] Embodiments of the disclosure will be described by way of examples only with reference to the accompanying drawing, in which:
[0027]
[0028]
[0029]
[0030]
[0031]
[0032]
[0033] Similar references used in different Figures denote similar components.
DETAILED DESCRIPTION
[0034] Generally stated, the non-limitative illustrative embodiments of the present disclosure provide a foundation for the support of a structure and method of installation. The foundation is used to support load support structures such as electrical transmission towers.
[0035] Referring to
[0036] Referring to
[0037] Referring back to
[0038] Then, with reference to
[0039] With reference to
[0040] Once the sealant 20 is dry, the base 16 is secured at the top of the main column 12. The design of the base 16 varies according to the structure to be supported, the type of main column 12 used and the number of anchors 14. After securing the base 16 at the top of the main column 12 (for example by soldering or bolting), each of the anchors 14 is secured using a respective securing element 18 and placed under tension T using a tension application mechanism that allows for power to be simultaneously applied on each anchor 14 along axis 2a. The tension T to be applied depends on the radial forces to the axis 1a (i.e. longitudinal axis) of the main column 12 to be counteracted according to the structure installed to ensure the stability of the main column 12.
[0041] Referring now to
[0042] The procedure 100 starts at block 102 with the drilling of a borehole in the ground 1 along an axis parallel to the axis of the force exerted by the load F for the insertion of the main column 12. The borehole is drilled to a depth c1 determined by the depth c2 of the bedrock 3 and the drilling depth c3 into the bedrock 3 or, alternatively, until the soil 1 is sufficiently dense, so as to support the load F. The diameter of the borehole is such as to be large enough to allow insertion of the main column 12.
[0043] At block 104, the main column 12 is inserted into the borehole and, optionally at block 106 in the case where the main column 12 is hollow, its center is filled with a dense and virtually incompressible material 20, such as a slurry of 30 MPA concrete, to increase the compressive strength of the main column 12.
[0044] Optionally still, at block 108, the clearance between the main column 12 and the wall of the borehole is filled with a sealant 22 such as a slurry of 30 MPA concrete with expander.
[0045] Then, at block 110, boreholes are drilled, at an angle β and spaced apart at an angle α, for the insertion of each anchor 14. The drilling depth a1 for the anchors 14, composed of the depth a2 to the bedrock 3 and the drilling depth a3 into the bedrock 3, is determined by the depth c2 of the bedrock 3, angle β and the drilling depth into the bedrock a2 necessary in relation to the tension T required. Alternatively, the drilling depth a1 for the anchors 14 may be determined by the depth for which the soil 1 is sufficiently dense so as to support the required tension T.
[0046] The angle β is determined by the radial forces induced by the structure to be supported by the base 16. In the illustrative embodiment angle β is between 15° and 60°. It is to be understood that in alternative embodiments this angle may vary depending on conditions of the soil, specific type of structure to be supported, etc. In the illustrative embodiment, angle β is identical for each anchor 14, however, in alternative embodiments angle β may vary for one or more anchor 14 in order to provide proper tensioning T of the main column 12.
[0047] The angle α between each adjacent anchor 14 is generally set so that adjacent anchors 14 are all equidistant. However, in an alternative embodiment, the angle between adjacent anchors 14 may vary such that anchors 14 are not all equidistant in order to accommodate specific radial forces and/or terrain configurations.
[0048] At block 112, the anchors 14 are inserted into their respective borehole following which, at block 114, a sealant 22 is injected, for example as a slurry of 30 MPA concrete with expander.
[0049] Once the sealant 20 has dried, the base 16 is secured, at block 116, at the top of the main column 12. The design of the base 16 varies according to the structure to be supported, the type of main column 12 used and the number of anchors 14.
[0050] Finally, at block 118, after securing the base 16 at the head of the main column 12, each of the anchors 14 is secured using a respective securing element 18 and placed under tension T using a tension application mechanism that allows for power to be simultaneously applied on each anchor 14 along axis 2a. The tension T to be applied depends on the radial forces to the axis 1a of the main column 12 to be counteracted according to the structure installed to ensure the stability of the main column 12.
[0051] The present foundation for the support of a structure and method of installation is applicable when the overburden layer 2 is more than 10 feet before reaching the bedrock 3. If the bedrock 3 is reached before 10 feet, the same technique applies with a main column 12 but without the anchors 14 as described hereinabove.
[0052] Although the present disclosure has been described with a certain degree of particularity and by way of illustrative embodiments and examples thereof, it is to be understood that the present disclosure is not limited to the features of the embodiments described and illustrated herein, but includes all variations and modifications within the scope of the disclosure as hereinafter claimed.