Method for inspecting service performance of tunnel lining based on defect characteristics thereof
11193374 · 2021-12-07
Assignee
Inventors
Cpc classification
G05B23/0283
PHYSICS
G05B23/0254
PHYSICS
E21F17/18
FIXED CONSTRUCTIONS
E21D11/10
FIXED CONSTRUCTIONS
G01V9/00
PHYSICS
International classification
E21F17/18
FIXED CONSTRUCTIONS
G01N21/954
PHYSICS
G01V9/00
PHYSICS
Abstract
The invention discloses a method for detecting service performance of a tunnel lining based on defect characteristics of the tunnel lining. A tunnel, an external load and stratum conditions are simulated by establishing a model using a model test method. A structural stress failure test for the model is carried out, and test results of the defect characteristics of a simulation lining of the model are recorded. A corresponding relationship between the defect characteristics of the simulation lining and the remaining bearing capacity interval is established according to the recorded test results. Detection results of defect characteristics of the tunnel lining are recorded using an in-situ detection method, and a remaining bearing capacity interval of the tunnel lining is determined based on the detection results according to the corresponding relationship between the defect characteristics of the simulation lining and the remaining bearing capacity interval of the model.
Claims
1. A method for detecting service performance of a tunnel lining based on defect characteristics of the tunnel lining, comprising: (1) simulating a tunnel, an external load and stratum conditions by establishing a model using a model test method, carrying out a structural stress failure test on the model, and recording test results of the defect characteristics of a simulation lining of the model; (2) establishing a corresponding relationship between the defect characteristics of the simulation lining and a remaining bearing capacity interval of the model according to the test results of the defect characteristics of the simulation lining recorded in step (1); (3) recording detection results of the defect characteristics of the tunnel lining using an in-situ detection method; (4) determining a remaining bearing capacity interval of the tunnel lining in step (3) based on the detection results of the defect characteristics of the tunnel lining in step (3) according to the corresponding relationship between the defect characteristics of the simulation lining and the remaining bearing capacity interval of the model in step (2).
2. The method of claim 1, wherein step (1) comprises: (101) determining a size, structural mechanical parameters, stratum mechanical parameters of the tunnel lining, and the external load of the tunnel, wherein the structural mechanical parameters comprise parameters of cracks and reinforcing bars; detecting and recording the defect characteristics of the tunnel lining, and carrying out a similar model test on defective and intact tunnel linings; (102) determining a geometric similarity ratio C.sub.L, a stress similarity ratio C.sub.σ and an elastic modulus similarity ratio C.sub.E of the model to the tunnel, and determining a displacement similarity ratio C.sub.d, a strain similarity ratio C.sub.ε, a load similarity ratio C.sub.p, a bending moment similarity ratio C.sub.M and a stratum resistance similarity ratio C.sub.k of the model to the tunnel according to a similarity theory; (103) selecting sand, cement, gypsum and the reinforcing bars for a proportioning cube test to prepare a tunnel simulation material that satisfies the stress similarity ratio C.sub.σ and the elastic modulus similarity ratio C.sub.E according to the geometric similarity ratio C.sub.L, the stress similarity ratio C.sub.σ and the elastic modulus similarity ratio C.sub.E of the model to the tunnel in step (102), and pouring the tunnel simulation material into the model and curing the model through vibrations; (104) manufacturing a test device according to the geometric similarity ratio C.sub.L and the load similarity ratio C.sub.p of the model to the tunnel in step (102); wherein the test device comprises a load control system and a data acquisition system; the load control system comprises a reaction frame, a jack, a loading plate, and a spring for simulating stratum resistance; a number and a stiffness of the spring meet requirements of the stratum resistance; the load control system controls and simulates a top loose load, a bias load and a plastic ground load on both sides of tunnel side walls; the data acquisition system comprises a pressure sensor, a data acquisition device, a displacement indicator and a strain gauge; a number of the pressure sensor corresponds to the number of the spring and a number of curved plates, respectively; the displacement indicator is arranged in a middle of each of the curved plates which are arranged at an outer side of the model; the pressure sensor, the displacement indicator and the strain gauge are connected to the data acquisition device, respectively; and step (105) simulating the top loose load, the bias load and the plastic ground load on both sides of the tunnel side walls by the load control system in a static classification mode; wherein each level of load is stabilized for 60 minutes after being applied, and then a next level of load is applied until the simulation lining is damaged.
3. The method of claim 2, wherein defects of the tunnel lining comprise back cavities, insufficient thickness, weak strength, cracks and insufficient reinforcing bars; the back cavities are simulated by arranging no spring and load; the cracks are prefabricated according to the parameters of cracks obtained in step (101); a portion with the insufficient thickness is simulated according to the structural mechanics parameters; a portion with insufficient reinforcement bars is simulated according to the parameters of the reinforcing bars obtained in step (101).
4. The method of claim 3, wherein the tunnel lining is damaged when a main tensile reinforcing bar is broken, concrete in a compression zone is crushed, deformation increases continuously under the same load, or a maximum vertical width of the cracks reaches 1.5 mm.
5. The method of claim 2, wherein the defect characteristics of the tunnel lining comprise vault subsidence, side wall convergence, crack density and crack depth.
6. The method of claim 5, wherein the corresponding relationship between the defect characteristics of the tunnel lining and the remaining bearing capacity interval comprises a corresponding relationship between the vault subsidence and the remaining bearing capacity interval, a corresponding relationship between the side wall convergence and the remaining bearing capacity interval, a corresponding relationship between the crack density and the remaining bearing capacity interval and a corresponding relationship between the crack depth and the remaining bearing capacity interval, respectively.
7. The method of claim 5, wherein step (3) comprises: (301) measuring the crack depth of the tunnel lining by a crack depth sounder; (302) measuring a crack width of the tunnel lining by a vernier caliper, a crack width gauge or an image recognition method; (303) measuring a crack length of the tunnel lining by a tape measure or an image recognition method; (304) detecting a thickness, distribution of the reinforcing bars, and back cavity conditions of the tunnel lining by a geological radar, wherein the back cavity condition of the tunnel lining comprises a circumferential range and a longitudinal length of the back cavity; and (305) measuring the vault subsidence and the side wall convergence of the tunnel lining by a total station or a laser profiler.
8. The method of claim 7, wherein step (4) comprises: (401) determining a corresponding relationship between the defect characteristics of the tunnel lining and the remaining bearing capacity interval according to model similarity ratios and the corresponding relationship between the defect characteristics of the tunnel lining and the remaining bearing capacity interval determined by the model; and (402) determining the remaining bearing capacity interval of the tunnel according to the most unfavorable principle when several defect characteristics exist based on the test results of the defect characteristics of the tunnel lining measured in steps (301)-(305) according to the corresponding relationship between the defect characteristics of the tunnel lining and the remaining bearing capacity interval obtained in step (401).
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9) In the drawings, 1—model of secondary tunnel lining, 2—reaction frame, 3—jack, 4—pressure sensor, 5—spring, 6—loading plate, 7—data acquisition device, 8—displacement indicator, W—cavity range, d—actual thickness, D—designed thickness.
DETAILED DESCRIPTION OF EMBODIMENTS
(10) The invention will be described in detail with reference to the accompanying drawings and specific embodiments as follows. The embodiments are only intended to illustrate but not to limit the scope of the invention.
(11) As shown in
(12) (1) A tunnel, an external load and stratum conditions are simulated by establishing a model using a model test method; a structural stress failure test for the model is carried out, and test results of the defect characteristics of a simulation lining of the model are recorded.
(13) Taking a two-lane highway tunnel as an example, the tunnel has a cross section with a width of 1186 cm, a height of 962.8 cm and an axial length of 300 cm. The model is C30 reinforced concrete with a thickness of 50 cm. A main tensile reinforcing bar is HRB335, and a protective layer has a thickness of 5 cm and a reinforcement percentage of 0.62%. Considering the test site size and loading conditions, a geometric similarity ratio C.sub.L is set to 10, and the simulation lining has a thickness of 5 cm, a width of 118.6 cm, a height of 96.28 cm and an axial length of 30 cm. According to several comparing tests, the concrete material is simulated by M30 mixed mortar made by cement, yellow sand, lime plaster and water with a mass ratio of 187:1450:113:330. A cube test block of 7 cm×7 cm×7 cm is measured to have a compressive strength of 31 Mpa by an uniaxial compression test, and a stress similarity ratio C.sub.σ is set to be approximately 10:1. A prism test block of 10 cm×10 cm×30 cm is measured to have an elastic modulus of 1.57 Gpa by an uniaxial compression test, and an elastic modulus similarity ratio C.sub.E is set to be approximately 20:1. As shown in Table 1, Similarity constants of respective physical quantities in the model can be obtained according to the similarity theory.
(14) TABLE-US-00001 TABLE 1 Similarity constants of physical quantities in the test model Physical quantity Unit Similarity constant Length L m 10 Displacement δ m 5 Stress σ N/m.sup.2 10 Elastic modulus E N/m.sup.2 20 Surface force s N/m.sup.2 10 Strain ε “1” 0.5 Poisson's ratio μ “1” 1 Physical force ρ N/m.sup.3 1 Force N N 1,000 Bending moment M N .Math. m 10,000 Stratum resistance N/m.sup.3 2 coefficient k
(15) Step (1) includes the following steps.
(16) (101) a size, structural mechanical parameters, stratum mechanical parameters of the tunnel lining, and the external load of the tunnel are determined, where the structural mechanical parameters include parameters of cracks and reinforcing bars; the defect characteristics of the tunnel lining are detected and recorded; a similar model test on defective and intact tunnel linings is carried out according to the test results.
(17) Defects of the tunnel lining comprise back cavities, insufficient thickness, weak strength, cracks and insufficient reinforcing bars; the back cavities are simulated by arranging no spring and load as shown in
(18) (102) a geometric similarity ratio C.sub.L, a stress similarity ratio C.sub.σ and an elastic modulus similarity ratio C.sub.E of the model to the tunnel are determined; a displacement similarity ratio C.sub.d, a strain similarity ratio C.sub.ε, a load similarity ratio C.sub.P, a bending moment similarity ratio C.sub.M and a stratum resistance similarity ratio C.sub.k of the model to the tunnel according to a similarity theory are determined.
(19) (103) sand, cement, gypsum and reinforcing bars are selected for a proportioning cube test to prepare a tunnel simulation material that satisfies the stress similarity ratio C.sub.σ and the elastic modulus similarity ratio C.sub.E according to the geometric similarity ratio C.sub.L, the stress similarity ratio C.sub.σ and the elastic modulus similarity ratio C.sub.E of the model to the tunnel in step (102), and the tunnel simulation material is poured into the model and the model is cured through vibrations.
(20) (104) a test device is manufactured according to the geometric similarity ratio C.sub.L and the load similarity ratio C.sub.P of the model to the tunnel in step (102), where the test device includes a load control system and a data acquisition system. As shown in
(21) To simulate Grade VI surrounding rock having an elasticity resisting coefficient of 3.16 MPa/m, a stiffness coefficient of the spring 5 is calculated to be 100 kN/m according to Equation 1:
(22)
(23) where K is the stiffness coefficient of the spring; k is a stratum resistance coefficient; s is an area of the loading plate; C.sub.k is a stratum resistance coefficient similarity ratio; C.sub.E is the elastic modulus similarity ratio; and C.sub.L is the geometric similarity ratio.
(24) The stiffness coefficient of the spring for simulating elasticity resisting coefficient of Grade IV-V surrounding rocks is calculated according to Equation 1, respectively.
(25) As shown in
(26) (105) the load control system simulates the top loose load, the bias load and the plastic ground load on both sides of the tunnel side walls in a static classification mode; each level of load is stabilized for 60 minutes after being applied, and then a next level of load is applied until the simulation lining is damaged.
(27) The tunnel lining is damaged when a main tensile reinforcing bar is broken, concrete in a compression zone is crushed, deformation increases continuously under the same load, or a maximum vertical width of the cracks reaches 1.5 mm. If the tunnel lining is damaged after a continuous load ends, a load at that time should be a measured failure load; if the tunnel lining is damaged during a loading process, a previous load is taken as the measured failure load; if the tunnel lining is damaged during the continuous load, an average value of a current load and a previous load is taken as the measured failure load.
(28) (2) a corresponding relationship between the defect characteristics of the simulation lining and the remaining bearing capacity interval is established according to the test results of the defect characteristics of the simulation lining recorded in step (1). Step (2) is specifically described as follows.
(29) The test results of the defect characteristics of the simulation lining are analyzed to obtain a deformation rule of the defect characteristics of the tunnel lining of intact and defective tunnel linings by increasing the external load. A curve showing the relationship between the vault subsidence and the structural bearing capacity is established as shown in
(30) The corresponding relationships between the defect characteristics of the tunnel lining and the remaining bearing capacity interval are shown in Table 2.
(31) TABLE-US-00002 TABLE 2 Corresponding relationships between the defect characteristics of the tunnel lining and the remaining bearing capacity interval Remaining bearing Vault Side wall capacity subsidence/ convergence/ Crack density Crack depth/ interval cm cm cm/m.sup.2 cm 100%~85% 0~0.06 0~0.04 0 0 85%~60% 0.06~0.25 0.04~0.15 0~60 0~1 60%~35% 0.25~0.7 0.15~0.5 60~310 1~2 35%~15% 0.7~1.15 0.5~0.9 310~700 2~3.5 15%~0% 1.15~1.5 0.9~1.3 ≥700 ≥3.5
(32) (3) detection results of defect characteristics of the tunnel lining are recorded using an in-situ detection method. Step (3) is specifically described as follows.
(33) (301) the crack depth of the tunnel lining is measured by a crack depth sounder.
(34) (302) a crack width of the tunnel lining is measured by a vernier caliper, a crack width gauge or an image recognition method.
(35) (303) a crack length of the tunnel lining is measured by a tape measure or an image recognition method.
(36) (304) a thickness, distribution of the reinforcing bars, and back cavity conditions of the tunnel lining are detected by geological radar, where the back cavity condition of the tunnel lining includes a circumferential range and a longitudinal length of the back cavity.
(37) (305) the vault subsidence and the side wall convergence of the tunnel lining are measured by a total station or a laser profiler.
(38) Taking a cross section of Baiyangshan Tunnel in Zhejiang as an example, the detection results of the defect characteristics of the tunnel lining are shown in Table 3.
(39) TABLE-US-00003 TABLE 3 Defect characteristics of a cross section of Baiyangshan Tunnel in Zhejiang Defect characteristics Vault Side wall subsidence/ convergence/ Crack density Crack depth/ cm cm cm/m.sup.2 cm Detection 3 1.2 85 12 value
(40) (4) a remaining bearing capacity interval of the tunnel lining in step (3) is determined based on the detection results of the defect characteristics of the tunnel lining in step (3) according to the corresponding relationship between the defect characteristics of the simulation lining and the remaining bearing capacity interval of the model in step (2). Step (4) is specifically described as follows.
(41) (401) a corresponding relationship between the defect characteristics of the tunnel lining and the remaining bearing capacity interval is determined according to model similarity ratios and the corresponding relationship between the defect characteristics of the tunnel lining and the remaining bearing capacity interval determined by the model.
(42) The deformation δ.sub.p, load P.sub.p, and crack density ρ.sub.m of the tunnel lining are back calculated according to deformation δ.sub.m, load P.sub.m, and crack density ρ.sub.m of the model measured in the test and Equations (2), (3) and (4), respectively:
δ.sub.p=δ.sub.m*C.sub.δ (2)
P.sub.p=P.sub.m*C.sub.P (3)
ρ.sub.p=ρ.sub.m*C.sub.ρ (4)
(43) where C.sub.δ is the deformation similarity ratio, C.sub.P is the load similarity ratio, C.sub.ρ is the crack density similarity ratio.
(44) As shown in Table 4, the corresponding relationship between the defect characteristics of the tunnel lining and the remaining bearing capacity interval is determined according to the similarity ratios of the tunnel to the model.
(45) TABLE-US-00004 TABLE 4 Corresponding relationship between the defect characteristics of the tunnel lining and the remaining bearing capacity interval Remaining bearing Vault Side wall capacity subsidence/ convergence/ Crack density Crack depth/ interval cm cm cm/m.sup.2 cm 100%~85% 0~0.3 .sup. 0~0.2 0 0 85%~60% 0.3~1.25 0.2~0.75 0~12 0~5 60%~35% 1.25~3.5 0.75~2.5 12~62 5~10 35%~15% 3.5~6 2.5~4.5 62~140 10~17.5 15%~0% 6~7.5 4.5~6.5 ≥140 ≥17.5
(46) (402) the remaining bearing capacity interval of the tunnel is determined according to the most unfavorable principle when several defect characteristics exist based on the test results of the defect characteristics of the tunnel lining measured in steps (301)-(305) according to the corresponding relationship between the defect characteristics of the tunnel lining and the remaining bearing capacity interval obtained in step (401).
(47) According to the defect characteristics of a cross section of Baiyangshan Tunnel in Zhejiang in Table 3 and the corresponding relationship between the defect characteristics of the tunnel lining and the remaining bearing capacity interval in Table 4, the remaining bearing capacity interval corresponding to the vault subsidence is determined as 60%˜35%; the remaining bearing capacity interval corresponding to the side wall convergence is determined as 60%˜35%; the remaining bearing capacity interval corresponding to the crack density is determined as 35%˜15%, the remaining bearing capacity interval corresponding to the crack depth is determined as 35%˜15%. Based on these defect characteristics, the remaining bearing capacity interval of the lining structure of Baiyangshan Tunnel in Zhejiang is determined as 35˜15% according to the most unfavorable principle.