SERVER, VEHICLE, AND VEHICLE DIAGNOSIS METHOD
20220194256 · 2022-06-23
Assignee
Inventors
Cpc classification
B60L2240/72
PERFORMING OPERATIONS; TRANSPORTING
B60L58/12
PERFORMING OPERATIONS; TRANSPORTING
B60L53/66
PERFORMING OPERATIONS; TRANSPORTING
B60L53/68
PERFORMING OPERATIONS; TRANSPORTING
International classification
Abstract
A vehicle diagnosis method includes a) determining, when a subject vehicle including a power storage enters a chargeable state in which it can receive power feed from EVSE, whether or not charging of the power storage is started in the subject vehicle, b) determining whether or not timer-programmed charging has been set in the subject vehicle that has entered the chargeable state, and c) determining whether or not charging and discharging control of the power storage is being carried out in the subject vehicle under remote control based on a determination result in at least one of a) determining and b) determining.
Claims
1. A server comprising: a first determination unit that determines, when a subject vehicle including a power storage enters a chargeable state in which power feed from a power feed facility outside the subject vehicle can be received, whether charging of the power storage is started in the subject vehicle; a second determination unit that determines whether timer-programmed charging has been set in the subject vehicle that has entered the chargeable state; and a third determination unit that determines whether charging and discharging control of the power storage is being carried out under remote control in the subject vehicle based on at least one of a result of determination by the first determination unit and a result of determination by the second determination unit.
2. The server according to claim 1, wherein when the first determination unit determines that the charging is started at time when the subject vehicle enters the chargeable state, the third determination unit determines that charging and discharging control of the power storage is not being carried out under remote control in the subject vehicle.
3. The server according to claim 1, wherein when the second determination unit determines that timer-programmed charging has been set in the subject vehicle that has entered the chargeable state and charging of the power storage is started at time which is not time to start set timer-programmed charging, the third determination unit determines that charging and discharging control of the power storage is being carried out under remote control in the subject vehicle.
4. The server according to claim 1, wherein when the second determination unit determines that timer-programmed charging has been set in the subject vehicle that has entered the chargeable state and charging of the power storage ends without a condition for quitting set timer-programmed charging being satisfied, the third determination unit determines that charging and discharging control of the power storage is being carried out under remote control in the subject vehicle.
5. The server according to claim 1, further comprising an error determination unit that determines whether a charging error that impedes charging of the power storage occurs in the subject vehicle, wherein when a prescribed condition is satisfied, the third determination unit determines that charging and discharging control of the power storage is being carried out under remote control in the subject vehicle, and the prescribed condition includes a condition that the first determination unit determines that the charging is not started at time when the subject vehicle enters the chargeable state, a condition that the second determination unit determines that timer-programmed charging has not been set in the subject vehicle that has entered the chargeable state, and a condition that the error determination unit determines that no charging error occurs in the subject vehicle.
6. The server according to claim 5, further comprising an error processing unit that performs, when the error determination unit determines that the charging error occurs, at least one of issuance of a notification and making of a record regarding occurrence of the charging error.
7. The server according to claim 1, further comprising a charging and discharging control unit, wherein a wireless communication device is mounted on the subject vehicle, the server wirelessly communicates with the subject vehicle through the wireless communication device, when the third determination unit determines that charging and discharging control of the power storage is not being carried out under remote control in the subject vehicle, the charging and discharging control unit carries out charging and discharging control of the power storage under remote control through wireless communication with the wireless communication device, and when the third determination unit determines that charging and discharging control of the power storage is being carried out under remote control in the subject vehicle, the charging and discharging control unit does not carry out the charging and discharging control of the power storage under the remote control.
8. The server according to claim 5, further comprising: a selector; and a charging and discharging control unit, wherein the server wirelessly communicates with a plurality of vehicles, each of the plurality of vehicles includes a power storage and a wireless communication device, the selector selects one or more vehicles from among the plurality of vehicles, the charging and discharging control unit carries out charging and discharging control of the power storage of each vehicle selected by the selector, under remote control through wireless communication with the wireless communication device, the selector preferentially selects a vehicle for which determination that charging and discharging control of the power storage is not being carried out under remote control is made by the third determination unit, over a vehicle for which determination that charging and discharging control of the power storage is being carried out under remote control is made by the third determination unit, and the selector does not select a vehicle for which determination that the charging error occurs is made by the error determination unit.
9. The server according to claim 8, wherein when there are a plurality of vehicles for which determination that charging and discharging control of the power storage is not being carried out under remote control is made by the third determination unit, the selector places higher priority in selection on a vehicle shorter in time elapsed since determination that charging and discharging control of the power storage is not being carried out under remote control was made.
10. The server according to claim 8, wherein when there are a plurality of vehicles for which determination that charging and discharging control of the power storage is not being carried out under remote control is made by the third determination unit, the selector sets priority in selection for the plurality of vehicles based on a charging location for each of the plurality of vehicles.
11. A server that carries out, on a vehicle including a power storage and a wireless communication device, charging and discharging control of the power storage for energy management, under remote control through wireless communication with the wireless communication device, the server excluding the vehicle from objects to be under the charging and discharging control when charging of the power storage is not started even when the vehicle enters a chargeable state in which power feed from a power feed facility outside the vehicle can be received while timer-programmed charging has not been set in the vehicle.
12. A vehicle comprising: a power storage; and a controller that controls a terminal of a user of the vehicle, the controller including a charging control unit that starts charging of the power storage when the vehicle enters a chargeable state in which power feed from a power feed facility outside the vehicle can be received while timer-programmed charging has not been set in the vehicle, and starts charging of the power storage when time to start set timer-programmed charging comes while timer-programmed charging has been set in the vehicle, a first determination unit that determines, when the vehicle enters the chargeable state, whether charging of the power storage is started in the vehicle, a second determination unit that determines whether timer-programmed charging has been set in the vehicle that has entered the chargeable state, and a third determination unit that determines whether charging and discharging control of the power storage is being carried out under remote control in the vehicle based on at least one of a result of determination by the first determination unit and a result of determination by the second determination unit.
13. The vehicle according to claim 12, wherein when the third determination unit determines that charging and discharging control of the power storage is being carried out under remote control in the vehicle, the controller controls the terminal of the user of the vehicle to be notified that the vehicle is remotely controlled.
14. The vehicle according to claim 12, further comprising an inlet, wherein the vehicle enters the chargeable state when a connector of a power cable connected to the power feed facility is connected to the inlet.
15. A vehicle diagnosis method comprising: a) determining, when a subject vehicle including a power storage enters a chargeable state in which power feed from a power feed facility outside the subject vehicle can be received, whether charging of the power storage is started in the subject vehicle; b) determining whether timer-programmed charging has been set in the subject vehicle that has entered the chargeable state; and c) determining whether charging and discharging control of the power storage is being carried out under remote control in the subject vehicle based on at least one of a result in a) determining and a result in b) determining.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0045]
[0046]
[0047]
[0048]
[0049]
[0050]
[0051]
[0052]
[0053]
[0054]
[0055]
[0056]
[0057]
[0058]
[0059]
[0060]
[0061]
DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0062] An embodiment of the present disclosure will be described in detail below with reference to the drawings. The same or corresponding elements in the drawings have the same reference characters allotted and description thereof will not be repeated.
First Embodiment
[0063]
[0064] Battery 130 includes a secondary battery such as a lithium ion battery or a nickel metal hydride battery. In this embodiment, a battery assembly including a plurality of lithium ion batteries is adopted as the secondary battery. The battery assembly is composed of a plurality of secondary batteries (which are generally also referred to as “cells”) electrically connected to one another. Instead of the secondary battery, another power storage such as an electric double layer capacitor may be adopted. Battery 130 according to this embodiment corresponds to an exemplary “power storage” according to the present disclosure.
[0065] Vehicle 50 includes an electronic control unit (which is referred to as an “ECU” below) 150. ECU 150 carries out charging control and discharging control of battery 130. ECU 150 controls communication with the outside of vehicle 50.
[0066] Vehicle 50 further includes a monitoring module 131 that monitors a state of battery 130. Monitoring module 131 includes various sensors that detect a state (for example, a voltage, a current, and a temperature) of battery 130 and outputs a result of detection to ECU 150. Monitoring module 131 may be a battery management system (BMS) that further performs, in addition to the sensor function, a state of charge (SOC) estimation function, a state of health (SOH) estimation function, a function to equalize a cell voltage, a diagnosis function, and a communication function. ECU 150 can obtain a state (for example, a temperature, a current, a voltage, an SOC, and an internal resistance) of battery 130 based on an output from monitoring module 131.
[0067] Electric vehicle supply equipment (EVSE) 40 corresponds to a power feed facility outside the vehicle. EVSE 40 includes a power supply circuit 41. A charging cable 42 is connected to EVSE 40. Charging cable 42 may always be connected to EVSE 40 or may be attachable to and removable from EVSE 40. Charging cable 42 includes a connector 43 at its tip end and contains a power line. Charging cable 42 according to this embodiment corresponds to an exemplary “power cable” according to the present disclosure.
[0068] Vehicle 50 includes an inlet 110 and a charger-discharger 120 for contact charging. Inlet 110 receives electric power supplied from the outside of vehicle 50. Inlet 110 is configured such that connector 43 of charging cable 42 can be connected thereto. As connector 43 of charging cable 42 connected to EVSE 40 is connected to (plugged into) inlet 110 of vehicle 50, vehicle 50 enters a chargeable state (that is, a state in which the vehicle can receive power feed from EVSE 40). Though
[0069] Charger-discharger 120 is located between inlet 110 and battery 130. Charger-discharger 120 includes a relay that switches between connection and disconnection of an electric power path from inlet 110 to battery 130 and a power conversion circuit (neither of which is shown). For example, a bidirectional converter can be adopted as the power conversion circuit. Each of the relay and the power conversion circuit included in charger-discharger 120 is controlled by ECU 150. Vehicle 50 further includes a monitoring module 121 that monitors a state of charger-discharger 120. Monitoring module 121 includes various sensors that detect a state of charger-discharger 120 and outputs a result of detection to ECU 150. In this embodiment, monitoring module 121 detects a voltage and a current input to and output from the power conversion circuit. Monitoring module 121 detects charging power for battery 130.
[0070] Vehicle 50 in the chargeable state is capable of external charging (that is, charging of battery 130 with electric power supplied from EVSE 40) and external power feed (that is, power feed from vehicle 50 to EVSE 40). Electric power for external charging is supplied, for example, from EVSE 40 through charging cable 42 to inlet 110. Charger-discharger 120 converts electric power received at inlet 110 into electric power suitable for charging of battery 130 and outputs resultant electric power to battery 130. Electric power for external power feed is supplied from battery 130 to charger-discharger 120. Charger-discharger 120 converts electric power supplied from battery 130 into electric power suitable for external power feed and outputs resultant electric power to inlet 110. When any of external charging and external power feed is performed, the relay of charger-discharger 120 is closed (connected), and when neither of external charging and external power feed is performed, the relay of charger-discharger 120 is opened (disconnected).
[0071] ECU 150 includes a processor 151, a random access memory (RAM) 152, a storage 153, and a timer 154. A computer may be adopted as ECU 150. A central processing unit (CPU) may be adopted as processor 151. RAM 152 functions as a work memory that temporarily stores data to be processed by processor 151. Storage 153 can store information that is put thereinto. Storage 153 includes, for example, a read only memory (ROM) and a rewritable non-volatile memory. Storage 153 stores not only a program but also information (for example, a map, a mathematical expression, and various parameters) to be used by a program. As a program stored in storage 153 is executed by processor 151, various types of control by ECU 150 are carried out in this embodiment. Various types of control by ECU 150 are not limited to control carried out by software but can also be carried out by dedicated hardware (electronic circuitry). Any number of processors may be provided in ECU 150 and a processor may be prepared for each prescribed type of control.
[0072] Timer 154 notifies processor 151 that the set time has come. As the time set in timer 154 comes, timer 154 transmits a signal to that effect to processor 151. In this embodiment, a timer circuit is adopted as timer 154. Timer 154 may be implemented by software instead of hardware (timer circuitry). ECU 150 can obtain current time from a real time clock (RTC) circuit (not shown) contained in ECU 150.
[0073] Vehicle 50 further includes a travel driving unit 140, an input apparatus 161, a meter panel 162, a navigation system (which is referred to as a “NAVI” below) 170, communication equipment 180, and a drive wheel W. Vehicle 50 is not limited to a front-wheel-drive vehicle shown in
[0074] Travel driving unit 140 includes a power control unit (PCU) and a motor generator (MG) which are not shown, and allows vehicle 50 to travel with electric power stored in battery 130. The PCU includes, for example, an inverter, a converter, and a relay (none of which is shown). The relay included in the PCU is referred to as a “system main relay (SMR)” below. The PCU is controlled by ECU 150. The MG is implemented, for example, by a three-phase AC motor generator. The MG is driven by the PCU and rotates drive wheel W. The PCU drives the MG with electric power supplied from battery 130. The MG performs regeneration and supplies regenerated electric power to battery 130. The SMR switches between connection and disconnection of an electric power path from battery 130 to the MG. The SMR is closed (connected) when vehicle 50 travels.
[0075] Input apparatus 161 accepts an input from a user. Input apparatus 161 is operated by a user and outputs a signal corresponding to the operation by the user to ECU 150. Examples of input apparatus 161 include various switches, various pointing devices, a keyboard, and a touch panel. Input apparatus 161 may include a smart speaker that accepts audio input.
[0076] Meter panel 162 shows information on vehicle 50. Meter panel 162 shows, for example, various types of information on vehicle 50 measured by various sensors mounted on vehicle 50. Information shown on meter panel 162 may include at least one of an outdoor temperature, a traveling speed of vehicle 50, an SOC of battery 130, average electric power consumption, and a travel distance of vehicle 50. Meter panel 162 is controlled by ECU 150. ECU 150 may have meter panel 162 show a message for a user or a warning indicator when a prescribed condition is satisfied.
[0077] NAVI 170 includes a processor, a storage, a touch panel display, and a global positioning system (GPS) module (none of which is shown). The storage stores map information. The touch panel display accepts an input from a user or shows a map and other types of information. The GPS module receives a signal (which is referred to as a “GPS signal” below) from a GPS satellite. NAVI 170 can identify a position of vehicle 50 based on a GPS signal. NAVI 170 conducts a path search for finding a travel route (for example, a shortest route) from the current position of vehicle 50 to a destination based on an input from the user, and shows the travel route found by the path search on a map.
[0078] Communication equipment 180 includes various communication interfaces (I/F). Communication equipment 180 includes a wireless communication device that wirelessly communicates with a server 30A (
[0079]
[0080] Portable terminal 80 corresponds to a terminal carried by a user of vehicle 50. In this embodiment, a smartphone equipped with a touch panel display is adopted as portable terminal 80. Without being limited thereto, any portable terminal can be adopted as portable terminal 80, and a tablet terminal, a wearable device (for example, a smart watch), an electronic key, or a service tool can also be adopted.
[0081] Power grid PG is a power network provided by an electric utility (for example, an electric power company). Power grid PG is electrically connected to a plurality of pieces of EVSE (including EVSE 40) and supplies AC power to each piece of EVSE. Power supply circuit 41 contained in EVSE 40 converts electric power supplied from power grid PG into electric power suitable for external charging. Power supply circuit 41 may include a sensor for detecting charging power.
[0082] As the relay of charger-discharger 120 is closed in vehicle 50 in the chargeable state, battery 130 is electrically connected to power grid PG. As electric power is supplied from power grid PG through power supply circuit 41, charging cable 42, and charger-discharger 120 to battery 130, battery 130 is externally charged.
[0083] Communication equipment 180 mounted on vehicle 50 communicates with EVSE 40 through charging cable 42. Communication between EVSE 40 and vehicle 50 may be of any type, and for example, controller area network (CAN) or power line communication (PLC) may be adopted. Standards of communication between EVSE 40 and vehicle 50 may be ISO/IEC15118 or IEC61851.
[0084] Communication equipment 180 mounted on vehicle 50 wirelessly communicates with server 30A, for example, through a mobile communication network (telematics). A protocol of communication between server 30A and vehicle 50 may be OpenADR. A signal exchanged between communication equipment 180 and server 30A may be encrypted. In this embodiment, communication equipment 180 and portable terminal 80 wirelessly communicate with each other. Communication equipment 180 and portable terminal 80 may communicate with each other through short-range communication such as Bluetooth® (for example, direct communication in a vehicle or within an area around the vehicle).
[0085] Prescribed application software (which is simply referred to as an “application” below) is installed in portable terminal 80. Portable terminal 80 is carried by a user of vehicle 50 and can exchange information with server 30A through the application. The user can operate the application, for example, through the touch panel display of portable terminal 80.
[0086] Server 30A includes a controller 31, a storage 32, a communication apparatus 33, and an input apparatus 34. A computer may be adopted as controller 31. Controller 31 includes a processor and a storage, performs prescribed information processing, and controls communication apparatus 33. Various types of information can be stored in storage 32. Communication apparatus 33 includes various communication I/Fs. Controller 31 communicates with the outside through communication apparatus 33. Input apparatus 34 accepts an input from a user. Input apparatus 34 provides the input from the user to controller 31.
[0087] Server 30A can communicate with each of vehicle 50 and portable terminal 80. Server 30A may communicate with EVSE 40. EVSE 40 may communicate with an EVSE management cloud. A protocol of communication between EVSE 40 and the EVSE management cloud may be open charge point protocol (OCPP).
[0088] In this embodiment, electric power system 1 functions as a virtual power plant (VPP). The VPP refers to a scheme in which a large number of distributed energy resources (which are also referred to as “DERs” below) are put together according to a sophisticated energy management technology that makes use of the Internet of Things (IoT) and the DERs are remotely controlled as being integrated as if the DER functioned as a single power plant. Exemplary DERs include energy resources possessed by each demand side (which are also referred to as demand side resources (DSR) below). In electric power system 1, the VPP is implemented by energy management using xEV (for example, vehicle 50 shown in
[0089] Server 30A carries out charging and discharging control of battery 130 under remote control through wireless communication with communication equipment 180 (wireless communication device). Server 30A can manage energy (for example, adjustment of demand and supply in power grid PG) by such charging and discharging control.
[0090]
[0091] Referring to
[0092] Electric power company E1 serves as a power generation utility and a power transmission and distribution utility. Electric power company E1 constructs a power network (that is, power grid PG shown in
[0093] An electric utility that puts the DER together to provide an energy management service is referred to as an “aggregator.” Electric power company E1, for example, in coordination with an aggregator, can adjust electric power of power grid PG. Parent aggregator E2 includes a plurality of servers (for example, servers 20A and 20B). Servers included in parent aggregator E2 belong to different utilities. Resource aggregator E3 includes a plurality of servers (for example, servers 30A and 30B). Servers included in resource aggregator E3 belong to different utilities. Servers included in parent aggregator E2 will be referred to as a “server 20” below and servers included in resource aggregator E3 will be referred to as a “server 30” below unless they are described as being distinguished from each other. Any independent number of servers 20 and servers 30 may be provided, and the number may be set to five or more or thirty or more.
[0094] In this embodiment, a single server 10 issues a request for energy management to a plurality of servers 20 and each server 20 that has received the request from server 10 issues a request for energy management to a plurality of servers 30. Furthermore, each server 30 that has received the request from server 20 issues a request for energy management to a plurality of vehicle users. Electric power company E1 can issue a request for energy management to a large number of demand sides (for example, vehicle users) using such a hierarchical structure (tree structure). The request may be issued by demand response (DR).
[0095] When server 30 receives a request for energy management from server 20, server 30 selects VPP cooperative vehicles in number necessary for meeting the request. The VPP cooperative vehicle is an xEV that cooperates in energy management. The VPP cooperative vehicle is selected from among xEVs belonging to users who have signed a contract with an aggregator in advance. A user who has signed the contract can be rewarded with a prescribed incentive by carrying out charging and discharging in accordance with a request from the aggregator. A prescribed penalty is imposed based on the contract, on a user who did not meet the request in spite of his/her approval to meet the request.
[0096] In this embodiment, when selection of the VPP cooperative vehicle ends, server 30 transmits a charging and discharging command (more specifically, a command to have the VPP cooperative vehicle carry out charging and discharging control) to each VPP cooperative vehicle. In response to this charging and discharging command, energy management in accordance with the request from server 20 (for example, adjustment of demand and supply in power grid PG) is carried out.
[0097] Server 30 measures an amount of power adjustment (for example, an amount of charging power and/or an amount of discharging power for a prescribed period) for each VPP cooperative vehicle with a prescribed wattmeter. The prescribed wattmeter may be smart meter 13 or a wattmeter (for example, monitoring module 121 shown in
[0098] In electric power system 1 shown in
[0099] Server 30A carries out charging and discharging control of battery 130 by remotely controlling vehicle 50 through wireless communication when it receives the request for energy management from server 20 (see
[0100] In electric power system 1 as above, a single vehicle 50 may simultaneously remotely be controlled by two or more servers (for example, servers 30A and 30B). When a single vehicle is simultaneously remotely controlled by two or more servers, commands from the servers may interfere with each other and energy management may not appropriately be carried out. Then, with a configuration which will be described below, server 30A according to this embodiment suppresses two or more simultaneous external control (remote control) operations onto vehicle 50.
[0101]
[0102] Information manager 301 manages information on each registered user (which is also referred to as “user information” below) and information on each registered vehicle (which is also referred to as “vehicle information” below). The user information and the vehicle information are stored in storage 32. Identification information (which is also referred to as a “user ID” below) for identifying a user is provided for each user and information manager 301 manages the user information as being distinguished based on the user ID. The user ID functions also as information (terminal ID) for identifying a portable terminal carried by a user. Identification information (vehicle ID) for identifying a vehicle is provided for each vehicle and information manager 301 manages vehicle information as being distinguished based on the vehicle ID. The vehicle ID may be a vehicle identification number (VIN).
[0103] The user information includes a communication address of a portable terminal carried by a user and information (vehicle ID) for identifying a vehicle belonging to the user. The vehicle information includes a communication address of a wireless communication device mounted on the vehicle and information received from the vehicle (for example, information representing a position and a state of the vehicle). The vehicle information includes also a result in each of third determination and error determination which will be described later. Controller 31 may be configured to allow the user to update the user information and the vehicle information in storage 32 through input apparatus 34.
[0104] First determination unit 311 is configured to determine whether or not charging (immediate charging) of battery 130 is started in vehicle 50 when vehicle 50 enters the chargeable state. Second determination unit 312 is configured to determine whether or not timer-programmed charging has been set in vehicle 50 that has entered the chargeable state. Determination by first determination unit 311 and determination by second determination unit 312 are also referred to as “first determination” and “second determination” below, respectively. Charging control (including immediate charging and timer-programmed charging) in vehicle 50 will be described later.
[0105] Error determination unit 314 is configured to determine whether or not a charging error that impedes charging of battery 130 in vehicle 50 occurs. Examples of the charging error include abnormality of charger-discharger 120 or battery 130. Abnormality of battery 130 includes restriction on charging of battery 130 due to a temperature of battery 130 being out of an appropriate range. When at least one of charger-discharger 120 and battery 130 is abnormal, charging of battery 130 is not carried out in vehicle 50. Determination by error determination unit 314 is also referred to as “error determination” below.
[0106] Third determination unit 313 is configured to determine whether or not vehicle 50 is under external control based on at least one determination result in first determination, second determination, and error determination. Being under external control and not being under external control mean a state that vehicle 50 is under external control and a state that vehicle 50 is not under external control, respectively. External control is charging and discharging control of battery 130 carried out under remote control from the outside of vehicle 50. Determination by third determination 313 is also referred to as “third determination” below. In this embodiment, third determination unit 313 makes third determination as shown below.
[0107] When determination as YES is made (that is, vehicle 50 is determined as having carried out immediate charging) in first determination, third determination unit 313 makes determination as “not under external control.” When determination as YES (that is, timer-programmed charging having been set in vehicle 50) is made in second determination and when charging of battery 130 is started at time which is not time to start set timer-programmed charging, third determination unit 313 makes determination as “under external control.” When determination as NO (that is, immediate charging not being carried out in vehicle 50) is made in first determination, when determination as NO (that is, timer-programmed charging not having been set in vehicle 50) is made in second determination, and when determination as “absence of error” (that is, occurrence of no charging error in vehicle 50) is made in error determination, third determination unit 313 makes determination as “under external control.” Third determination unit 313 has a result in third determination stored in storage 32.
[0108] Error processing unit 304 is configured to perform prescribed error processing when determination as “presence of error” (that is, occurrence of a charging error in vehicle 50) is made in error determination. Prescribed error processing refers, for example, to a notification and a record to the effect that the charging error occurs. Error processing unit 304 may carry out only one of issuance of a notification and making of a record.
[0109] Selector 303 is configured to select one or more vehicles from among a plurality of vehicles. More specifically, when selector 303 receives a request for energy management, it selects a VPP cooperative vehicle for meeting the request from a prescribed vehicle group (which is denoted as a “group G” below). Group G includes a plurality of xEVs configured similarly to vehicle 50 (see
[0110] Charging and discharging control unit 302 is configured to carry out charging and discharging control of the power storage of each VPP cooperative vehicle, under remote control through wireless communication with the wireless communication device. For example, when the VPP cooperative vehicle is vehicle 50, charging and discharging control unit 302 carries out charging and discharging control of battery 130, under remote control through wireless communication with communication equipment 180.
[0111] ECU 150 mounted on vehicle 50 includes an information manager 501 and a charging and discharging control unit 502. In ECU 150 according to this embodiment, each unit is implemented by processor 151 shown in
[0112] Information manager 501 obtains a state of vehicle 50 based on outputs from various sensors mounted on vehicle 50. Information manager 501 obtains a position of vehicle 50 from NAVI 170. Information manager 501 has a state of vehicle 50 recorded in storage 153 in association with the position of vehicle 50. Information manager 501 transmits the current position and state of vehicle 50 to server 30A at prescribed timing or in response to a request from server 30A. The state of vehicle 50 transmitted from vehicle 50 to server 30A includes a state of connection (connection/disconnection) of inlet 110, a state of setting of timer-programmed charging (not set/set), and the SOC of battery 130. Information manager 501 may transmit the current position and state of vehicle 50 to server 30A at timing when the state of connection of inlet 110 makes transition from disconnection to connection (that is, timing of plugging into inlet 110).
[0113] Charging and discharging control unit 502 is configured to carry out charging and discharging control of battery 130 by controlling charger-discharger 120. When vehicle 50 enters the chargeable state while timer-programmed charging has not been set, charging and discharging control unit 502 starts external charging (immediate charging). Charging and discharging control unit 502 does not carry out immediate charging while timer-programmed charging has been set in vehicle 50. The user of vehicle 50 can set timer-programmed charging in vehicle 50 (more specifically, ECU 150) by operating a user terminal (for example, input apparatus 161 or portable terminal 80). As the user programs charging by designating start time, timer-programmed charging is set in vehicle 50. Setting of timer-programmed charging (including start time) is stored in storage 153. When time to start set timer-programmed charging comes in vehicle 50 in the chargeable state, charging and discharging control unit 502 starts external charging (timer-programmed charging). Charging and discharging control unit 502 is configured to quit charging when a prescribed quitting condition is satisfied during charging.
[0114]
[0115] Referring to
[0116]
[0117] In S22, charging and discharging control unit 502 controls charger-discharger 120 to carry out charging of battery 130. In S23, charging and discharging control unit 502 determines whether or not a prescribed quitting condition (which is also referred to as a “charging quitting condition” below) is satisfied. In this embodiment, the charging quitting condition is satisfied when a state of charge (SOC) of battery 130 is equal to or higher than a prescribed SOC value (for example, an SOC value indicating full charge). Without being limited as such, the charging quitting condition can be modified as appropriate. For example, the charging quitting condition may be satisfied when prescribed time to end comes. Alternatively, the charging quitting condition may be satisfied when a user performs a prescribed operation to quit onto EVSE 40, input apparatus 161, or portable terminal 80.
[0118] While determination as NO (not satisfied) is made in S23, S21 to S23 are repeated. When the charging quitting condition is satisfied (YES in S23), the series of processing shown in
[0119] Referring again to
[0120]
[0121] Referring to
[0122]
[0123] Referring to
[0124] Referring to
[0125] When determination as YES (that is, vehicle 50 carrying out immediate charging) is made in S51, in S61, third determination unit 313 makes determination as “not under external control.”
[0126] When determination as YES (that is, timer-programmed charging having been set in vehicle 50) is made in S52, in S54, third determination unit 313 determines whether or not charging has been started in vehicle 50. Third determination unit 313 repeats determination in S54 until charging is started in vehicle 50. When charging is started in vehicle 50 (YES in S54), in S55, third determination unit 313 determines whether or not the current time (that is, time when charging has been started) and time to start set timer-programmed charging are the same. When determination as YES (the same) is made in S55, in S62, third determination unit 313 makes determination as “not under external control.” When determination as NO (not the same) is made in S55, in S63, third determination unit 313 makes determination as “under external control.”
[0127] When determination as YES (presence of error) is made in S53, in S64, error processing unit 304 performs prescribed error processing. For example, error processing unit 304 has contents of the charging error recorded in storage 32 in association with the ID of vehicle 50 (vehicle ID) and notifies portable terminal 80 carried by the user of vehicle 50 of occurrence of the charging error. When determination as NO (absence of error) is made in S53, in S65, third determination unit 313 makes determination as “under external control.” A result of determination (not under external control/under external control) in each of S61 to S63 and S65 is stored in storage 32 in association with the ID of vehicle 50 (vehicle ID).
[0128] When processing in any of S61 to S65 is performed, the process proceeds to S42 in
[0129]
[0130]
[0131] In this embodiment, priority is set as low/intermediate/high, with the charging location being categorized into home/workplace/public. How to determine the priority based on the charging location, however, is not limited as above. Server 30A may obtain charging history data (for example, data representing a frequency of external control for each charging location) from each xEV included in group G. Then, server 30A may evaluate probability of external control for each charging location based on the charging history data. The charging location where probability of external control is high is different for each xEV. Therefore, server 30A may evaluate the charging location for each xEV. Server 30A may set the priority of the xEV located at the charging location where probability of external control is high to be lower than the priority of the xEV located at the charging location where probability of external control is low.
[0132] Referring again to
[0133]
[0134] Referring to
[0135] In S72, selector 303 narrows down candidates for the VPP cooperative vehicle (which are also referred to as “selection candidates” below). More specifically, selector 303 excludes an xEV not suitable for energy management from the selection candidates among xEVs included in group G (initial selection candidates). For example, in energy management in which a request for charging of the power storage (demand creation) is issued to the xEV, an xEV the power storage of which is fully charged is excluded from the selection candidates. Selector 303 may give an advance notice to a vehicle user before selection of the VPP cooperative vehicle. When the vehicle user indicates his/her intention not to participate in energy management, selector 303 may exclude the xEV belonging to that vehicle user from the selection candidates.
[0136] In S73, selector 303 selects the VPP cooperative vehicle from among the selection candidates narrowed down in S72. Selector 303 selects a prescribed target number of VPP cooperative vehicles in accordance with priority indicated in the priority information (see
[0137] In S74, charging and discharging control unit 302 transmits a charging and discharging command to each VPP cooperative vehicle selected in S73. The charging and discharging command is transmitted from server 30A to each VPP cooperative vehicle through wireless communication. Charging and discharging control unit 302 remotely controls each VPP cooperative vehicle in accordance with this charging and discharging command. When charging and discharging control unit 302 transmits the charging and discharging command to each VPP cooperative vehicle, each VPP cooperative vehicle carries out charging and discharging control of the power storage in accordance with the charging and discharging command through the processing shown in
[0138] In S75, charging and discharging control unit 302 determines whether or not requested energy management has been completed. Charging and discharging control unit 302 may determine that energy management has been completed when a period for requested power adjustment expires. Transmission (S74) of the charging and discharging command is continued until energy management is completed. When energy management is completed (YES in S75), a series of processing shown in
[0139] As described above, the vehicle diagnosis method according to the first embodiment includes first determination. second determination, error determination, and third determination. In first determination, when the subject vehicle including the power storage enters the chargeable state in which it can receive power feed from EVSE (a power feed facility outside the vehicle), whether or not charging of the power storage is started in the subject vehicle is determined (S51 in
[0140] Server 30A may perform vehicle diagnosis processing when charging ends in the subject vehicle in which timer-programmed charging has been set.
[0141] When the number of xEVs for energy management is insufficient in the first embodiment, server 30A may wait for an xEV included in group G entering the chargeable state. Then, server 30A may perform vehicle diagnosis processing on the xEV that has entered the chargeable state, and carry out energy management with that xEV by externally controlling (remotely controlling) the xEV determined as “not under external control.” Server 30A may perform processing shown in
[0142]
[0143] Referring to
[0144] When determination as YES is made in any of S91 and S92, in S94, charging and discharging control unit 302 transmits the charging and discharging command to the subject vehicle. In S95, charging and discharging control unit 302 determines whether or not energy management has been completed. Processing in S94 and S95 is in conformity with S74 and S75 in
[0145] Server 30A according to the modification is configured to exclude a vehicle in which charging of the power storage mounted thereon is not started even when it enters the chargeable state while timer-programmed charging has not been set (that is, the subject vehicle for which determination as NO is made in both of S91 and S92) from an object to be under charging and discharging control under remote control. According to such a configuration, interference between two or more remote control operations and a malfunction in external control due to a charging error are suppressed.
[0146] In the modification, third determination unit 313 may determine whether or not charging and discharging control of the power storage is carried out under remote control in the subject vehicle based on a determination result in each of S91 and S92. More specifically, when determination as NO is made in S92, third determination unit 313 may determine the subject vehicle as being “under external control,” and when determination as YES is made in any of S91 and S92, it may determine the subject vehicle as being “not under external control.” In such a configuration, when determination as “not under external control” is made in third determination, charging and discharging control unit 302 carries out charging and discharging control of the power storage of the subject vehicle under remote control through wireless communication with the wireless communication device of the subject vehicle (S94). When determination as “under external control” is made in third determination, charging and discharging control unit 302 does not carry out charging and discharging control of the power storage under remote control (S93). Server 30A configured as such can carry out charging and discharging control of the power storage under remote control in the subject vehicle while interference with another remote control operation is avoided.
[0147] The first embodiment and various modifications may be carried out as being combined in any manner. For example, controller 31 may accept an input from a user so as to allow the user to adopt any control mode. Controller 31 may be configured to allow the user to select any of control shown in
[0148] The function in vehicle diagnosis processing described above may be implemented in server 30B (
Second Embodiment
[0149] A vehicle according to a second embodiment of the present disclosure will be described. Since the second embodiment is mostly identical to the first embodiment, differences will mainly be described and description of components in common is not provided.
[0150] The function involved with vehicle diagnosis processing implemented in the server in the first embodiment may be implemented in the vehicle.
[0151] Referring to
[0152] ECU 150A includes an information manager 501A instead of information manager 501 (
[0153] Charging and discharging control unit 502 is configured to carry out charging control shown in
[0154]
[0155] Referring to
[0156] In S112, information manager 501A determines whether or not vehicle 50A is under external control based on the result in third determination (
[0157] In vehicle 50A according to the second embodiment, when determination as “under external control” is made in third determination, the terminal of the user of vehicle 50A is notified of the fact that vehicle 50A is under remote control (S113). The user thus readily knows whether or not vehicle 50A is remotely controlled.
[0158] ECU 150A may perform vehicle diagnosis processing when charging ends in vehicle 50A in which timer-programmed charging has been set.
[0159] At least some of functions involved with vehicle diagnosis processing implemented in vehicle 50A in the second embodiment may be implemented in portable terminal 80A.
Another Embodiment
[0160] The electric power company may be divided for each business sector. A power generation utility and a power transmission and distribution utility may belong to companies different from each other. One aggregator may serve as both of the parent aggregator and the resource aggregator. The server may receive a request for energy management from a power market. The server that performs vehicle diagnosis processing is not limited to an aggregator server and any server that can communicate with a vehicle is applicable.
[0161] A configuration of the vehicle is not limited to the configuration shown in
[0162] Though embodiments of the present disclosure have been described, it should be understood that the embodiments disclosed herein are illustrative and non-restrictive in every respect. The scope of the present disclosure is defined by the terms of the claims and is intended to include any modifications within the scope and meaning equivalent to the terms of the claims.