Structures for Use in Erecting Multistory Buildings and Methods for Making Such Structures
20220162847 ยท 2022-05-26
Inventors
Cpc classification
B28B7/22
PERFORMING OPERATIONS; TRANSPORTING
E04B1/04
FIXED CONSTRUCTIONS
International classification
E04B1/348
FIXED CONSTRUCTIONS
B28B7/22
PERFORMING OPERATIONS; TRANSPORTING
Abstract
Disclosed are various construction techniques for erecting a multistory building with an elevator shaft. In accordance with the method, upper and lower shaft components are formed at an offsite facility. These shaft components are then joined together to form a segment of the larger elevator shaft. Once constructed, the segment is transported to a jobsite and erected. Once an individual segment is installed, a floor slab can be formed about the segment. Using pre-cast elevator segments simplifies and expedites the construction process. In one embodiment, each segment includes a serrated edge that facilitates a connection between the floor slab and the shaft segment. Rebar and reinforcing dowels can also be used to improve the connection. Associated shaft constructions are also disclosed.
Claims
1. (canceled)
2. A method of constructing an elevator shaft comprising the following steps: forming a lower shaft component at an offsite facility, the lower shaft component including walls, upper and lower edges, and a series of exposed surfaces and pockets; setting a series of rebar segments within the lower shaft component at the offsite facility, each rebar segment including a first end positioned within the lower shaft component and a second end extending from an exposed surface or a pocket; forming an upper shaft component at the offsite facility, the upper shaft component including walls, and upper and lower edges; joining the lower edge of the upper shaft component to the upper edge of the lower shat component at the offsite facility, the joined shaft components constituting a shaft segment; securing the shaft segment with a series of stitch plates at the offsite facility, with each stitch plate secured between a wall of the upper shaft component and one of the exposed surfaces of the lower shaft component; transporting the shaft segment to a jobsite and installing it as one of a series of segments of the elevator shaft; pouring a concrete slab about the shaft segment at the jobsite, with the poured concrete extending into and bonding with the series of pockets within the lower shaft component, the poured concrete further bonding to the second ends of the rebar segments.
3. A method of constructing an elevator shaft, with such construction taking place both a jobsite and an offsite facility, the offsite facility being remote from the jobsite, the method comprising the following steps: assembling a shaft segment at the offsite facility, the assembly comprising the following steps: forming a first component, the first component including walls, upper and lower edges, and a series of pockets and adjacent surfaces; forming a second component, the second component including walls, and upper and lower edges; joining the lower edge of the second shaft component to the upper edge of the first shaft component; and securing the first and second components with a series of plates, with each plate secured between a wall of the second shaft component and one of the adjacent surfaces of the first shaft component; and transporting the assembled shaft segment to a jobsite and installing it as one of a series of segments of the elevator shaft.
4. The method as described in claim 2 comprising the additional step of pouring a concrete floor slab about the assembled shaft segment at the jobsite, with the poured concrete extending into and bonding with the series of pockets within the first component.
5. The method as described in claim 2 comprising the additional set of setting a series of rebar segments within the first shaft component at the offsite facility, each rebar segment including a first end positioned within the first shaft component and a second end extending from a pocket or an adjacent surface.
6. The method as described in claim 5 wherein each of the rebar segments is bent.
7. The method as described in claim 5 wherein each of the rebar segments is bent at approximately a 90 degree angle.
8. An elevator shaft for use in constructing a multi-story building, the elevator shaft being formed from a series of elevator shaft segments, the elevator shaft comprising: a lower shaft component including walls, an upper edge, a lower edge, and a series of pockets formed along each of the walls, each pocket including a recessed surface and adjacent surfaces; an upper shaft component including walls, an upper edge, and a lower edge, the lower edge of the upper shaft component being joined to the upper edge of the lower shaft component to form one of the series of elevator shaft segments; a slab formed about the elevator shaft segment with the slab extending into the pockets of the lower shaft component.
9. The elevator shaft as described in claim 8 further comprising: a series of rebar segments, each rebar segment including first and second ends, with the first end formed within the lower shaft component and the second end extending from one of the series of pockets and into the slab floor.
10. The elevator shaft as described in claim 9 wherein the rebar segments are bent.
11. The elevator shaft as described in claim 9 wherein the rebar segments are bent at an angle of approximately 90 degrees.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0014] For a fuller understanding of the nature and objects of the invention, reference should be had to the following detailed description taken in connection with the accompanying drawings in which:
[0015]
[0016]
[0017]
[0018]
[0019]
[0020]
[0021]
[0022]
[0023] Similar reference characters refer to similar parts throughout the several views of the drawings.
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENT
[0024] The present disclosure relates to a construction method for erecting an elevator shaft for a multistory building. In accordance with the method, upper and lower shaft components are formed at an offsite facility. These shaft components are then joined together to form a segment of the larger elevator shaft. Once constructed, the segment is transported to a jobsite and erected. Once an individual segment is installed, a floor slab can be formed about the segment. Using pre-cast elevator segments simplifies and expedites the construction process. In one embodiment, each segment includes a serrated edge that facilitates a connection between the floor slab and the shaft segment. Rebar and reinforcing dowels can also be used to improve the connection. Associated shaft constructions are also disclosed. The various components of the present disclosure, and the manner in which they interrelate, are described in greater detail hereinafter.
[0025] With reference now to
[0026] Each segment 22 is formed from interconnected upper and lower components (24 and 26). In particular, and as better illustrated in
[0027] The lower shaft component 26, depicted in
[0028] With continuing reference to
[0029] Each upper shaft component 24 is formed to match the dimensions of the lower shaft component 26. As such, the depicted upper shaft component 24 includes four walls 62 and upper and lower edges (64 and 66). An opening 68 is also formed within one of the walls 62 and is designed to complement the corresponding opening 38 in the lower shaft component 26. Together, these openings (38 and 68) form a larger opening for doors of the elevator shaft. The upper, rectangular shaft component 24 is similarly pre-formed from a reinforced concrete with interior rebar 48 (
[0030] Each elevator shaft segment 22 is formed by joining the upper edge 34 of the lower shaft component 26 to the lower edge 66 of the upper shaft component 24. Reinforcing dowels 72 can extend between the upper and lower shaft components (24 and 26) to improve the bonding. The connection is further strengthened via a series of stitch plates 74. Each stitch plate 74 includes an upper extent that is connected to one of the walls 62 of the upper shaft component 24 and a lower extent connected to one of the exposed surfaces 46 of the lower shaft component 26.
[0031] Once an elevator shaft segment 22 is completed it is transported to a jobsite to be erected as part of the larger elevator shaft 20. Thereafter, a slab floor 28 is formed about the shaft segment 22. As the floor slab 28 is poured, the concrete extends into and bonds with the pockets 42 of the lower shaft component 26, with the second ends 56 of the hooked rebar segments 52 extending into the slab floor 28 (
[0032] The floor slab 28 can be constructed via any number of construction methods. For example, in order to provide proper reinforcement, slab 28 can be poured about rebar or rebar cages.
[0033] The anchorage assembly 96 used for tendon 92 is illustrated in
[0034] The associated method of the present disclosure is next described. In the first step, a lower shaft component is formed from reinforced concrete at an offsite facility. As noted, this lower shaft component includes walls, upper and lower edges, and a series of pockets. Each pocket includes recessed and exposed surfaces. An upper shaft component is likewise formed from reinforced concrete at the offsite facility. This upper shaft component is similarly defined by walls, and upper and lower edges. In the next step, the lower edge of the upper shaft component is joined to the upper edge of the lower shaft component. The joined shaft components together constitute a shaft segment. Next, the shaft segment is further secured with a series of stitch plates, with each stitch plate connecting the wall of the upper shaft component to one of the exposed surfaces of the lower shaft component. The assembled shaft segment is then transported to the jobsite and installed. This process is repeated as needed to complete the entire elevator shaft. Thereafter, the floors can be constructed by pouring concrete about each shaft segment. As each floor is poured, the concrete extends into and bonds with the series of pockets within the lower shaft component. The floors can be poured following the completion of the entire elevator shaft. Alternatively, each floor can be poured after each individual shaft segment is installed. Furthermore, the shaft segments can be transported to the jobsite individually or in larger quantities.
[0035] Although this disclosure has been described in terms of certain embodiments and generally associated methods, alterations and permutations of these embodiments and methods will be apparent to those skilled in the art. Accordingly, the above description of example embodiments does not define or constrain this disclosure. Other changes, substitutions, and alterations are also possible without departing from the spirit and scope of this disclosure.