Abstract
A method of ground anchoring a plurality of posts (11), especially to erect a fence or barrier. The method includes anchoring a first plurality of posts (11) into the ground, preferably simultaneously, using a plurality of post anchoring stations (50) located on at least one movable platform (10) that can be moved along a path, and then anchoring a second plurality of posts (11), again preferably simultaneously, into the ground using the plurality of post anchoring stations (50). In preferred forms there are a plurality of movable platforms which may be mechanically and/or wireless linked.
Claims
1. A method of ground anchoring a plurality of posts, the method comprising: anchoring a first plurality of posts into the ground using a plurality of post anchoring stations, the post anchoring stations being located on at least one movable platform; moving the at least one movable platform along a predetermined path; and anchoring a second plurality of posts into the ground using the plurality of post anchoring stations.
2. The method of claim 1, wherein the first plurality of posts are anchored substantially simultaneously, and the second plurality of posts are anchored substantially simultaneously.
3. The method of claim 1, wherein: there are at least two operatively connected movable platforms; there are at least two operatively connected movable platforms and the at least two movable platforms are aligned along the predetermined path; there are at least two operatively connected movable platforms and the at least two movable platforms are configured to follow along the predetermined path by being operatively connected to each other; there are at least two operatively connected movable platforms and the at least two movable platforms form a series of platforms operatively connected through mechanical interconnection; or there are at least two operatively connected movable platforms and an interconnected movable platform is articulated with respect to other movable platforms.
4.-7. (canceled)
8. The method of claim 1, wherein: there are at least two movable platforms and the at least two movable platforms form a series of mechanically independent movable platforms; there are at least two movable platforms and the at least two movable platforms are operatively connected through wireless communication; there are at least two movable platforms and each movable platform has a propulsion unit configured to move the movable platform along the predetermined path; or there are at least two movable platforms and a propulsion unit is configured to tow one or more of the movable platforms.
9.-10. (canceled)
11. The method of claim 1, wherein: a distance between respective post anchoring stations is independently varied; there are at least two movable platforms, and a distance between respective post anchoring stations is varied by moving the post anchoring station position on the movable platforms; or there are at least two movable platforms and a distance between respective post anchoring stations is varied by changing the spacing between each or any one or more of the movable platforms.
12.-13. (canceled)
14. The method of claim 1, wherein: each post anchoring station comprises a post anchoring mechanism that is independently capable of adjustment such that it can be configured to be operated on either side of the movable platform; or each post anchoring station comprises a post anchoring mechanism that is independently capable of adjustment such that it can extend or retract on a substantially horizontal plane perpendicularly from the movable platform.
15. The method of claim 1, wherein: a barrier material is located on, and dispensed from, the at least one movable platform; or a barrier material is located on, and dispensed from, the at least one movable platform, and the barrier material is connected to mid-strainer posts and/or end strainer posts.
16. A method of erecting a fence, the method comprising: anchoring a first plurality of posts into the ground using a plurality of post anchoring stations, the post anchoring stations being located on at least one movable platform; moving the at least one movable platform along a predetermined fence line; anchoring a second plurality of posts into the ground using the plurality of post anchoring stations; laying out at least one length of barrier material adjacent the first plurality of posts and adjacent the second plurality of posts, and straining the at least one length of barrier material; and attaching the at least one length of barrier material to the first plurality of posts and the second plurality of posts.
17. The method of claim 16, wherein: the at least one movable platform comprises a plurality of operatively connected movable platforms; the at least one movable platform comprises a plurality of operatively connected movable platforms, and the plurality of movable platforms are operatively connected through mechanical interconnection; the at least one movable platform comprises a plurality of operatively connected movable platforms, and the plurality of movable platforms are operatively connected through a wireless communication system; or the at least one movable platform comprises a plurality of operatively connected movable platforms, and the plurality of movable platforms are operatively connected through mechanical interconnection and through a wireless communication system.
18. (canceled)
19. The method of claim 16, wherein: the at least one movable platform comprises an aligned series of mechanically independent movable platforms; or the at least one movable platform comprises an aligned series of mechanically interconnected movable platforms.
20. The method of claim 16, wherein the first plurality of posts are anchored substantially simultaneously, and the second plurality of posts are anchored substantially simultaneously.
21. The method of claim 16, wherein: a barrier material is located on, and dispensed from, the at least one movable platform; or a barrier material is located on, and dispensed from, the at least one movable platform, and the barrier material is connected to mid-strainer posts and/or end strainer posts.
22. (canceled)
23. A multi vehicle train that is used to anchor posts, the multi vehicle train comprising: a plurality of operatively connected movable platforms; and a plurality of post anchoring stations, each post anchoring station comprising a post anchoring mechanism, wherein at least one post anchoring station of the plurality of post anchoring stations is located on at least two or more of the plurality of movable platforms.
24. The multi vehicle train of claim 23, wherein one of the movable platforms is used to mount at least one barrier material feeder.
25. The multi vehicle train of claim 23, configured to at least: anchor a first plurality of posts into the ground using a plurality of post anchoring stations, the post anchoring stations being located on at least one movable platform; move the at least one movable platform along a predetermined path; and anchor a second plurality of posts into the ground using the plurality of post anchoring stations.
26. The multi vehicle train of claim 23, configured to at least: anchor a first plurality of posts into the ground using a plurality of post anchoring stations, the post anchoring stations being located on at least one movable platform; move the at least one movable platform along a predetermined fence line; anchor a second plurality of posts into the ground using the plurality of post anchoring stations; lay out at least one length of barrier material adjacent the first plurality of posts and adjacent the second plurality of posts, and strain the at least one length of barrier material; and attach the at least one length of barrier material to the first plurality of posts and the second plurality of posts.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0046] An embodiment of the invention will be described, by way of example only, with reference to the accompanying figures in which:
[0047]
[0048]
[0049]
[0050]
[0051]
[0052]
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
[0053] Like numerals have been used to describe like components in the description below.
[0054]
[0055] The movable platform 10 includes a movable platform 20 formed by a chassis 30 on which is mounted a floor 40. The chassis 30 includes four rear wheels 31 mounted adjacent the end of the floor 40 and two front wheels 32 located forward of the floor 40. The distance between the front wheels 32 and the rear wheels 31 can be adjusted using a telescopic arm 33. A trailer hitch 34 is located at the adjacent the front wheels 32 and a tow ball 35 is located adjacent the rear wheels 31.
[0056] It would be appreciated that there are many ways to create a movable platform that would be known to a person skilled in the art. The representation of the wheels as a method providing movement as shown is purely for illustrative purposes only and is not meant to limit the scope of the movable platform. Other forms can include continuous rubber tracked or steel plate tracked mechanisms such as found on skid steer equipment and bulldozers.
[0057] An interconnected movable platform configuration has been illustrated, however the invention should not be limited to this configuration, as it is described in this specification and intended and claimed that each movable platform can be autonomous and independently capable of substantially following the path of the at least one other leading movable platform. Where there are more than two movable platforms it is claimed that each movable platform is capable of following substantially along the same path as the first leading movable platform and capable of operating substantially in unison with each of the other movable platforms even though they are not connected in a similar fashion as that of a train.
[0058] An anchoring station 50 is located on the floor 40 of the movable platform 10. The anchoring station 50 includes a post anchoring mechanism 51 located adjacent one end of the floor 40 and a safety railing 52 located adjacent the front of the floor 40. Posts 11 to be anchoring into the ground are located on the floor 40 adjacent the anchoring mechanism 51. It would be appreciated that there are many types of anchoring mechanisms 51 that would be known to a person skilled in the art. The representation shown is purely for illustrative purposes only and is not meant to limit the scope of anchoring mechanisms 51 than may be used.
[0059] The anchoring station 50 also includes a rotatable body 57 that is used to mount the post anchoring mechanism 51 via a series of movable arms 58. The rotatable body 57 is connected to the floor 40. A motor 56 is connected to the rotatable body to enable rotation of the rotatable body 57 and hence the post anchoring mechanism 51. Accordingly, the post anchoring mechanism 51 can be rotated, extended, and/or titled with respect to the movable platform 10 using the arms 58. This enables that a post 11 can be anchored into the ground at a desired angle (which is normally vertical).
[0060] To anchor a post 11 into the ground, an operator (not shown) who is located on the floor 40, picks up a post 11 located on the trailer 10. The post 11 is placed within the post anchoring mechanism 51. The post anchoring mechanism 51 is then activated, and then the post 11 is anchored into the ground at the desired orientation along a fence line.
[0061]
[0062] As the loader 53 and post anchoring mechanism 51 are both automated, a user is not required to be located on the floor 40 of the trailer 10. That is, a post 11 can be loaded and driven into the ground remotely. The circular dolly 54 can be rotated to allow a greater level of movement of the anchoring mechanism 51 if required.
[0063] In use, an operator stands on each trailer and loads a post 11 into their respective anchoring mechanism 51. The post anchoring mechanisms 51 are, therefore, ready to anchor the posts 11 into the ground, as shown in
[0064] The powered vehicle 1 leads the trailers 10 along a predetermined fence line. When the powered vehicle 1 is in a desired position, the vehicle stops, and the operators are told they are in the correct position. The operators then simultaneously anchor in the posts 11 into the ground using their respective anchoring mechanisms 51, as shown in
[0065] Once all of the posts 11 have been anchored to the ground, and the anchor mechanism 51 has been withdrawn from the anchored posts 11, the powered vehicle 1 moves to the next desired location. Simultaneously, the posts 11 are loaded, by the operators, into the empty post anchoring mechanisms 51 on each trailer as shown in
[0066] When the next location along the fence line is reached by the powered vehicle 1, this is again indicated to the operators, and posts are anchored into the ground by the operators using the anchoring mechanisms 51 as shown in
[0067] The distance that the powered vehicle 1 moves largely depends on the spacing between the posts 11 and the number of anchoring stations 50. For example, if the fence posts 11 are to be anchored at seven-metre centres, and there are seven anchoring stations, the powered vehicle will anchor forward 49 metres and stop. The seven operators on each of the trailers 10 would then each install one post per anchoring station using the associated anchoring mechanism.
[0068] This method enables seven posts 11 to be installed substantially at one time ‘covering 49 meters, with all posts being installed substantially in alignment with the desired fence line, with each post being substantially perpendicular. It would be appreciated that the spacing between the anchoring stations may be varied by the length of the telescopic arm.
[0069] It is envisaged that each trailer may have one, two or three anchoring stations 50 and therefore can anchor one, two or three posts substantially at the same time. The fence posts are be installed substantially “IN-LINE” along a predetermined fence line. It would also be appreciated that designated strainer posts or in-line mid strainer posts can be installed, when required, by any of the various anchoring stations.
[0070] It would also be appreciated that the trailer shown in
[0071]
[0072] The barrier material 61 is strained at appropriate locations using strainer posts (not shown) that would be evident to a person skilled in the art. The barrier material is then connected to posts 11 that have been anchored into the ground to complete installation of a fence.
[0073]
[0074]
[0075] This method of anchoring posts into the ground to erect a fence or the associated method of erecting a fence can be formed substantially quicker than current methods. This is due to a large number of posts being able to be anchored into the ground simultaneously at a desired spacing along a predetermined fence line.
[0076] In this specification, the terms “comprise”, “comprises”, “comprising” or similar terms are intended to mean a non-exclusive inclusion, such that a system, method or apparatus that comprises a list of elements does not include those elements solely, but may well include other elements not listed.
[0077] The reference to any prior art in this specification is not, and should not be taken as, an acknowledgement or any form of suggestion that the prior art forms part of the common general knowledge.
[0078] It should be appreciated that various other changes and modifications may be made to the embodiments described without departing from the spirit or scope of the invention.