Pre-pour slump maximization of delivered concrete
11331828 · 2022-05-17
Assignee
Inventors
- Gregory A. Goldstein (Somerville, MA, US)
- Mark F. Roberts (North Andover, MA, US)
- Nathan A. Tregger (Northborough, MA, US)
- Byong-wa Chun (Waban, MA)
- Kati Hazrati (Concord, MA, US)
Cpc classification
B28C7/026
PERFORMING OPERATIONS; TRANSPORTING
C04B40/0032
CHEMISTRY; METALLURGY
B28C5/422
PERFORMING OPERATIONS; TRANSPORTING
International classification
B28C5/42
PERFORMING OPERATIONS; TRANSPORTING
B28C7/02
PERFORMING OPERATIONS; TRANSPORTING
Abstract
A method and system for initiating a majority percentage of chemical admixture dosage into a delivered concrete load preferably just before arrival of the concrete delivery truck at the delivery pour site, such that a maximized slump (or slump flow, or other slump characteristic) increase occurs just before discharge/pour. The invention employs a concrete slump management system having a processor that is programed to consider time of pour (discharge) and stored data that includes dosage response (change of slump characteristic) of the concrete mix due to past additions in the same type of concrete mix, and thus maximizes pre-pour increase in slump characteristic while minimizing or avoiding the risk of overshooting the slump target as well as limiting the time required for adjusting concrete to attain the target slump value at the jobsite.
Claims
1. A method for dosing a cement plasticizer chemical admixture into a concrete load contained in a delivery mixer truck using a processor-controlled system and a delivery mixer truck mixer drum, comprising: (A) providing a concrete mix load into the rotatable drum of a delivery truck, the concrete mix load having a known volume; (B) providing a processor-accessible database having data sets obtained from at least four doses of a cement plasticizer chemical admixture, wherein the data sets comprise a slump characteristic of the concrete mix load before the addition of the cement plasticizer chemical admixture to the concrete mix load, a slump characteristic of the concrete mix load after the addition of the cement plasticizer chemical admixture, the volume of the cement plasticizer chemical admixture added to achieve the change in slump characteristic, and the volume of concrete mix load to which the cement plasticizer chemical admixture was added; (C) monitoring the concrete mix load in the truck drum during transit at least every five minutes from at least batching until dosing of the cement plasticizer chemical admixture using a processor unit to calculate the time-to-administer the cement plasticizer chemical admixture dose (which is designated by t.sub.a) for the concrete mix load based upon i. a scheduled pour time (which is designated by t.sub.p); ii. the slump characteristic increase (which is designated by ΔS) required to achieve the target slump characteristic at pouring wherein the slump characteristic increase is calculated using the relationship ΔS=S.sub.T−S.sub.c wherein S.sub.T represents target slump characteristic and S.sub.c represents current slump characteristic of the concrete mix load during transit; iii. the dosage of the cement plasticizer chemical admixture required to achieve the slump characteristic increase ΔS (which is designated by D.sub.ΔS) which is based on the current slump characteristic (which is designated by S.sub.C), and the data described above in Step (B); wherein the time-to-administer the cement plasticizer chemical admixture dose (which is designated by t.sub.a) is calculated by the relationship t.sub.a=t.sub.p−t.sub.h, where t.sub.h is based on at least the time required to add the cement plasticizer chemical admixture; and (D) administer the cement plasticizer chemical admixture dose when the current time (t.sub.c) equals or exceeds the time-to-administer (t.sub.c≥t.sub.a) such that the following relationship is satisfied:
D.sub.Δs>D.sub.c/(t.sub.c−t.sub.b)×(t.sub.p−t.sub.a) wherein t.sub.c represents the current time, t.sub.a represents the time-to-administer the cement plasticizer chemical admixture dose, D.sub.ΔS represents the dosage required to achieve a target slump characteristic from a current slump characteristic, D.sub.c represents the total cumulative cement plasticizer chemical admixture dosages since time of batching (t.sub.b) up to current time (t.sub.c), and t.sub.p represents the time at which the concrete load is scheduled to be poured.
2. The method of claim 1 wherein, in Step (B), the slump characteristic is slump or slump flow.
3. The method of claim 1 wherein, in Step (B), the processor-accessible database having data sets is obtained from at least ten doses of the cement plasticizer chemical admixture.
4. The method of claim 1 wherein, in Step (B), the processor-accessible database having data sets is obtained from at least fifty doses of the cement plasticizer chemical admixture.
5. The method of claim 1 wherein, in Step (B), the processor-accessible database having data sets further includes information about the mix design of the concrete to which the addition of cement plasticizer chemical admixture was made, information about the mixer drum to which the addition of cement plasticizer chemical admixture was made, information about the mixer drive system which was used to rotate the mixer drum to which the addition of cement plasticizer chemical admixture was made, information about the concrete to which the addition of cement plasticizer chemical admixture was made, or combinations thereof.
6. The method of claim 1 wherein, in Step (C), the concrete mix load in the truck drum is monitored at least every 1 minute.
7. The method of claim 1 wherein, in Step (C), the concrete mix load in the truck drum is monitored from at least batching to discharging of the concrete.
8. The method of claim 1 wherein, in Part (i) of Step (C), the scheduled pour time (which is represented by t.sub.p) is the time the concrete truck arrives at a job site.
9. The method of claim 1 wherein, in Part (i) of Step (C), the processor unit calculates the scheduled pour time (which is represented by t.sub.p) based on location information provided by a global positioning system (GPS) and traffic information, historical deliveries to the same job site, information received from contractors placing concrete at the job site, or a combination thereof.
10. The method of claim 9 wherein the processor unit calculates the scheduled pour time (which is represented by t.sub.p) based on information provided by contractors through a mobile device.
11. The method of claim 1 wherein, in Part (ii) of Step (C), the processor unit calculates the current slump characteristic (which is designated by S.sub.C) based on signals provided by at least one hydraulic sensor, at least one force sensor, or combination thereof.
12. The method of claim 1 wherein, in Part (iii) of Step (C), the processor unit calculates the dosage required to achieve the slump characteristic increase ΔS (which is designated by DAs) based on the current rate of slump characteristic loss.
13. The method of claim 1 wherein, in Part (iii) of Step (C), the processor unit calculates the dosage required to achieve the slump characteristic increase ΔS (which is designated by D.sub.ΔS) based on the variability of the data within the datasets provided in Step (B).
14. The method of claim 1 wherein, in Step (C), the processor unit calculates the time required to add the cement plasticizer chemical admixture based on the time required to pump the cement plasticizer chemical admixture, the time required to mix the cement plasticizer chemical admixture throughout the volume of concrete, other code requirements in accordance with ASTM C94-16a, or combinations thereof.
Description
BRIEF DESCRIPTION OF DRAWINGS
(1) An appreciation of the benefits and features of the invention may be more readily comprehended when the following written description of preferred embodiments is considered in conjunction with the drawings, wherein
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
DETAILED DESCRIPTION OF EXEMPLARY EMBODIMENTS
(11) As used herein, the phrase “chemical cement plasticizer admixture” (or variations such as “cement dispersant chemical admixture” or “chemical admixture”) refers to a polymeric dispersant admixture which reduces the amount of water required for achieving a certain slump or workability in a given concrete mix. Such water-reducing admixtures, otherwise termed water reducers, have been used in the concrete industry for decades. Terms such as “chemical admixture” as used herein will be understood to include so-called cement plasticizers and/or superplasticizers (the latter of which refers to replacement of larger water portions within the concrete mix).
(12) The term “slump” as used herein will refer to the property of concrete workability, such as determined using the conventional vertical drop measurement of concrete using standard inverted cone; but this could also include “slump flow” whereby workability is determined using horizontal spread measurement of concrete when released from cone. The term “slump characteristic” may be used also to refer to either or both of these rheological properties and to emphasize that the present invention is not limited necessarily to either slump or slump flow measurements or monitoring, but can comprehend related rheology values such as yield stress as well. The term “slump” is used for sake of convenience herein in referring to concrete rheology and concrete management/monitoring systems.
(13) Automated concrete slump management (monitoring) systems for managing slump or other rheological properties are commercially available, for example, from Verifi LLC, 62 Whittemore Avenue, Cambridge, Mass., USA, which has disclosed various automated concrete monitoring methods and systems in the patent literature, such as U.S. Pat. Nos. 8,020,431; 8,118,473; 8,311,678; 8,491,717; 8,727,604; 8,764,273; 8,989,905; as well as U.S. Ser. No. 11/834,002 (Publ. No. US 2009/0037026 A1); U.S. Ser. No. 258,103 (Publ. No. 2012/0016523 A1); U.S. Ser. No. 14/052,289 (Publ. No. 2014/0104066 A1); U.S. Ser. No. 14/052,310 (Publ. No. 2014/0104972); PCT/US2015/025054 (Publ. No. WO 2015/160610 A1); and PCT/US2014/065709 (Publ. No. WO2015073825 A1).
(14) Alternatively, the slump monitoring system may be based on use of a force sensor which is mounted within the drum, as taught for example in U.S. Pat. No. 8,848,061 and US Publication No. 2015/0051737 A1 of Berman (Sensocrete Inc./GCP Applied Technologies), U.S. Pat. No. 9,199,391 of Denis Beaupre et al. (I.B.B. Rheologie Inc.), or US Publication No. 2009/0171595 and WO 2007/060272 of Benegas.
(15) An exemplary automated concrete slump management (monitoring) system of the present invention is illustrated in
(16) To date, the vast majority of concrete manufacturers do not employ automated concrete slump management/monitoring systems on their ready-mix concrete delivery trucks. The following sections will compare prior art water and/or chemical admixture dosing processes with and without the use of such automated slump monitoring systems.
(17) The following terms will be used to describe the present invention and are listed for convenient reference and defined as follows:
(18) Slump characteristic—a rheology measurement such as slump, slump flow, yield stress, viscosity, etc.
(19) Current time (t.sub.c)—the time at which the system processor is currently implementing the exemplary methods of the present invention (during transit delivery operation).
(20) Time of batching (t.sub.b)—the time at which the concrete in the current concrete mixer drum delivery truck was initially batched (components assembled and mixed in drum).
(21) Time-to-administer (t.sub.a)—the time at which a majority of cement plasticizer chemical admixture (percentage of total dosage) is to be administered (added into the concrete).
(22) Pour time (t.sub.p)—the time at which the concrete is poured or discharged from the concrete mixer drum of the delivery truck.
(23) Time required to add the chemical admixture (t.sub.h)—the time required to make the addition (dosing) of the cement plasticizer chemical admixture into the concrete. This may include the time it takes to pump and administer the chemical admixture into the drum, the time required to mix the chemical admixture throughout the concrete volume (to attain state of homogeneity within the concrete mix load), other time period due to meeting ASTM C94-16a (e.g., required numbers of rotation to mix in the admixture), or combinations thereof.
(24) Target slump characteristic (S.sub.T)—the desired slump characteristic of the concrete at the pour time when the concrete is to be discharged.
(25) Current slump characteristic (S.sub.C)—the current slump characteristic of the concrete at current time.
(26) Slump characteristic increase (ΔS)—the increase in slump characteristic required to bring the current slump characteristic to the target slump characteristic.
(27) Total cumulative admixture dosages (D.sub.C)—the total cumulative cement plasticizer chemical admixture dosage amount administered since batching time to current time.
(28) Dosage required to achieve target slump (D.sub.ΔS)—the dosage amount of cement plasticizer chemical admixture estimated to change the slump characteristic from the current slump characteristic value to the target slump characteristic value.
(29) As illustrated in
(30) On the other hand, an exemplary late stage addition according to the present invention is represented by the lower curve (Case 2) in
(31) As further detailed in
(32)
(33) In contrast to the PRIOR ART process illustrated in
(34) As illustrated in
(35) As seen in
(36)
(37)
(38)
(39)
(40) Preferably, the sensor is a hydraulic pressure sensor (designated at 9), and, more preferably, one hydraulic pressure sensor is mounted on the charge pressure port and a second hydraulic pressure sensor is mounted on the discharge pressure port of the hydraulic motor 3 used for rotating the mixer drum 2 (See e.g., US Publication No. 2014/0104972 owned by the assignee hereof, disclosing use of charge and discharge hydraulic pressure sensors). A second sensor for sensing rotational states of the mixer drum is designated at 5 and is preferably based on the use of an accelerometer as taught in U.S. Pat. No. 8,727,604 and/or gyroscope unit as taught in WO 2014/073825 A1.
(41) Alternatively, the slump monitoring system may be based on use of a force sensor which is mounted within the drum, as taught for example in U.S. Pat. No. 8,848,061 and US Publication No. 2015/0051737 A1 of Berman (Sensocrete Inc./GCP Applied Technologies), U.S. Pat. No. 9,199,391 of Denis Beaupre et al. (I.B.B. Rheologie Inc.), or US Publication No. 2009/0171595 and WO 2007/060272 of Benegas.
(42) Thus, an exemplary method of the present invention for dosing a cement plasticizer chemical admixture into a concrete load contained in a delivery mixer truck using a processor-controlled system and a delivery mixer truck mixer drum, comprises: (A) providing a concrete mix load into the rotatable drum of a delivery truck, the concrete mix load having a known volume; (B) providing a processor-accessible database having data sets obtained from at least four doses, wherein a data set comprises a slump characteristic (e.g., slump, slump flow, yield stress) before the addition of a chemical admixture, a slump characteristic after the addition of a chemical admixture, the volume of chemical admixture added to achieve the change in slump characteristic, and the volume of concrete to which the chemical admixture was added, or combinations thereof; (C) monitoring the concrete mix load in the truck drum during transit at least every five minutes from at least batching until dosing of the chemical admixture using a processor unit to calculate the time-to-administer admixture dose (which is designated by t.sub.a) for the concrete mix load based upon (i) a scheduled pour time (which is designated by t.sub.p); (ii) the slump characteristic increase (which is designated by ΔS) required to achieve the target slump characteristic at pouring wherein the slump characteristic is calculated using the relationship ΔS=S.sub.T−S.sub.c wherein S.sub.T represents target slump characteristic and S.sub.c represents current slump characteristic of the concrete mix load during transit; (iii) the dosage required to achieve the slump characteristic increase ΔS (which is designated by D.sub.ΔS) which is based on the current slump characteristic (which is designated by S.sub.C), and the data described above in Step (B); wherein the time-to-administer admixture dose (which is designated by t.sub.a) is calculated by the relationship t.sub.a=t.sub.p−t.sub.h, where t.sub.h is based on at least the time required to add the chemical admixture; and (D) administer the admixture dose when the current time (t.sub.c) equals or exceeds the time-to administer (t.sub.c≥t.sub.a) such that the following relationship is satisfied: D.sub.ΔS>D.sub.s/t.sub.c−t.sub.b)×(t.sub.p−t.sub.a) wherein t.sub.c represents the current time, t.sub.a represents the time-to-administer admixture dose, D.sub.ΔS represents the dosage required to achieve a target slump characteristic from a current slump characteristic, D.sub.c represents the total cumulative admixture dosages since time of batching (t.sub.b) up to current time (t.sub.c), and t.sub.p represents the time at which the concrete load is scheduled to be poured.
(43) Further exemplary methods of the invention include, in providing a processor-accessible database in Step (B), the processor-accessible database having data sets obtained from at least ten doses instead of four doses. While the invention may be carried out using data from four prior admixture doses, the present inventors prefer that more data be employed for increased accuracy. For example, the data of historic chemical admixture dosing and corresponding effect on slump characteristic can be obtained from truck-based slump monitoring system or systems during earlier deliveries on the same day, same week, or from within preceding weeks (according to preference of the slump system operator, central control manager, or programmer), preferably involving the same concrete mix, delivery truck designs and plastic properties (e.g. same air content). For example, a large construction operation may require 10, 20, 50, or 70 truckloads of concrete to be poured, such that the first ten deliveries (which could involve up to 10 different trucks which each use an automated slump monitoring system) could provide slump data, whereby a large percentage of the admixture is dosed according to the late stage addition process of the invention, but the actual amount administered is a percentage of the total calculated (85% as done at present), so that the actual slump increase is measured and the difference between predicted slump increase and actual slump increase is taken account by the slump monitoring processor for subsequent doses (within the same trucks as well as within the entire fleet of delivery trucks whose slump monitoring systems are in wireless communication with a central monitoring office or station), such that for deliveries subsequent to the tenth dosage, a larger percentage of the maximized dose (e.g., 95%) can be administered just before discharge/pour.
(44) Other exemplary methods of the invention include, in providing a processor-accessible database in Step (B), the processor-accessible database having data sets obtained from at least fifty doses.
(45) Instill other exemplary embodiments of the invention, the data sets used by the slump monitoring system processor can be filtered according to the preference of the system manager, operator, or supervisor. For example, factors that may be considered by the supervisor or manager, who is reviewing the slump monitoring system data which may be streamed into a central supervising or management office, and/or who may in turn alter the filters on the data used by the truck system processors, may include but not be limited to: (a) whether the truck/mixer combination or design has a large effect on the variation of data across the delivery fleet and concrete slump data; (b) whether the aggregate used in the concrete has wide variations in clay content that such that dosage efficiency of chemical admixture dispersant (e.g., particularly of the polycarboxylate polymer type) is adversely affected; (c) whether the concrete mix designs vary so widely (e.g., between residential mix having low cement content and special commercial mix having high cement content); and (d) other conditions or factors which would suggest that certain data should be filtered out from others when deciding what historical data to use for determining when and how much chemical admixture to administer during the late stages, in accordance with the present invention.
(46) In further exemplary methods, in providing a processor-accessible database in Step (B), the processor-accessible database having data sets further includes information about the mix design of the concrete to which the chemical addition was made, information about the mixer drum to which the chemical addition was made, information about the mixer drive system which was used to rotate the mixer drum to which the chemical addition was made, information about the plastic concrete to which the chemical addition was made or combinations thereof.
(47) In other exemplary methods, in monitoring the concrete in Step (C), the concrete mix load in the truck drum is monitored by the slump monitoring system processer at least every minute.
(48) In still further exemplary methods, in monitoring the concrete in Step (C), the concrete mix load in the truck drum is monitored from at least batching to discharging of the concrete.
(49) Further exemplary methods include in monitoring the concrete in Step (C), Part (i), the scheduled pour time (which is represented by t.sub.p) is the time the concrete truck arrives at the site.
(50) In further exemplary methods, in monitoring the concrete in Step (C), Part (i), the system processor calculates the scheduled pour time (which is represented by t.sub.p) based on location information provided by a global positioning system (GPS) and traffic information, historical deliveries to the same job site, information received from contractors placing concrete at the jobsite or a combination thereof.
(51) In still further exemplary methods, in monitoring the concrete in Step (C), Part (i), the system processor calculates the scheduled pour time (which is represented by t.sub.p) based on information provided by contractors through a mobile device.
(52) The monitoring systems used in the invention may be based on the use of hydraulic pressure, strain gauges, or mixture of both, for predicting the slump or other rheology measurement of the concrete. Hence in further exemplary methods of the invention, the system processor calculates the current slump characteristic (which is designated by S.sub.C) based on signals provided by at least one hydraulic sensor, at least one force sensor, or combination thereof.
(53) In still further exemplary methods, in monitoring the concrete in Step (C), Part (iii), the system processor calculates the dosage required to achieve the slump characteristic increase ΔS (which is designated by D.sub.ΔS) based on the current rate of slump characteristic loss.
(54) In further exemplary methods, in monitoring the concrete in Step (C), Part (iii), the system processor calculates the dosage required to achieve the slump increase ΔS (which is designated by DΔS) based on the variability of the data within the datasets provided in Step (B).
(55) In other exemplary methods, in monitoring the concrete in Step (C), the system processor calculates the time required to add the chemical admixture based on the time required to pump the admixture, the time required to mix chemical throughout the volume of concrete, other code requirements in accordance with ASTM C94-16a or combinations thereof.
(56) The present invention also provides a system for dosing a liquid plasticizer chemical admixture into a concrete load contained in a delivery mixer truck. An exemplary system comprises: a processor unit, at least two sensors in communication with the processor unit to enable monitoring of the slump of concrete load contained in a delivery mixer truck mixer drum and to enable monitoring of at least one rotational property of the mixer drum, and a liquid dispenser control in communication with the processor unit for introducing a liquid plasticizer chemical admixture into a concrete load contained in a delivery mixer truck, the processor unit being programmed to perform the above exemplary methods described above.
(57) While the invention is described herein using a limited number of embodiments, these specific embodiments are not intended to limit the scope of the invention as otherwise described and claimed herein. Modifications and variations from the described embodiments exist. More specifically, the following examples are given as a specific illustration of embodiments of the claimed invention. It should be understood that the invention is not limited to the specific details set forth in the examples. All parts and percentages in the examples, as well as in the remainder of the specification, are by percentage dry weight unless otherwise specified.
Example 1
(58) What follows is an example that illustrates the unexpected advantages and of delaying the majority percentage addition of chemical admixture during transit delivery. Sixteen loads of concrete, based on the same concrete mix design, were batched and delivered in the same concrete mixer truck outfitted with an automated slump management system (Verifi LLC of Cambridge, Mass. USA). All concrete loads were initially adjusted to a slump of 2 inches (±1) without the use of a cement dispersant chemical admixture. At this point, a first sample was taken to determine strength before addition of admixture and ensure a consistent water content was achieved. The mixing speed of the mixer drum was set at three (3) revolutions per minute (rpm) for sixty (60) minutes.
(59) Protocol 1 was used on ten loads wherein the concrete was dosed with chemical admixture to achieve eight inch slump immediately after the initial slump was confirmed with the automated slump management system. The slump was maintained at eight inches, and if the slump fell by half an inch, then admixture was added automatically by the slump management system in the amount necessary to return slump to eight inches. After sixty minutes from the time the concrete achieved the initial slump, the concrete was mixed at 18 rpm for one minute and then discharged for testing. Testing included duplicate slump measurements, air content, unit weight and strength. The total dosage of chemical admixture added into the concrete was recorded.
(60) Six loads were dosed according to a Protocol 2. In this protocol the loads were dosed to achieve slump of four inches immediately after the initial slump was confirmed. The slump was maintained at 4 inches with the same half-inch (½″) tolerance. After fifty minutes, some admixture amount was added so that the total dose administered by both protocols were equal. If Protocol 2 was more efficient in terms of dosage, at equal dose, the slump for Protocol 2 should be higher than Protocol 1. The concrete was mixed at 18 rpm for one minute then discharged and tested in the same manner as occurred for protocol 1.
(61) Because of the inherent variability in the materials and test methods (i.e. each load of concrete will have a variable amount of different materials due to the tolerances of the batching equipment, and each physical testing method has its own associated errors), the data was normalized as a dose response (dose required per unit slump increase) was compared between each protocol. This was calculated as the total dose divided by the measured slump after sixty minutes. A typical Analysis of Variance which is sometimes referred to as ANOVA (See e.g. Statistical Methods for Research Workers (ISBN 0-05-002170-2)) was used on the two sets to determine that the means of the sets were statistically different with a significance of 1%. For Protocol 1, the mean dose response was 6.3±0.2 ounces/inch (i.e., the weight amount of admixture necessary to achieve slump gain of one inch), while in Protocol 2 the mean dose response was 5.4±0.1 ounces/inch, thus reflecting a reduction of fourteen percent (14%) in the amount of admixture required to achieve the same level of slump performance. The plus/minus values represent the variance around the mean value.
(62) For each of the ten loads using Protocol 1 and the six loads using Protocol 2, the following calculations were made: (a) cumulative dose (D.sub.C) before the last addition; (b) the time of the last addition—the time of batching (t.sub.c−t.sub.b); (c) the dose of the last addition (D.sub.ΔS); (d) the time of discharge—the time of the last addition (t.sub.p−t.sub.c); (e) D.sub.C/(t.sub.c−t.sub.b); and (f) D.sub.ΔS/(t.sub.d−t.sub.c). For all loads using Protocol 1, the ratio in e) was greater than the ratio in f). Conversely, for all the loads using Protocol 2, the ratio in e) was less than the ratio in f). The ratios for all the loads are shown below in Table 1.
(63) TABLE-US-00001 TABLE 1 Protocol Ratio in e) Ratio in f) 1 3.13 0.11 1 0.51 0.13 1 0.48 0.33 1 0.53 0.17 1 2.05 0.05 1 2.21 0.08 1 10.27 −0.58 1 15.40 −0.56 1 2.58 0.06 1 9.00 −1.13 2 0.08 3.18 2 0.20 1.69 2 0.41 1.21 2 0.37 1.10 2 0.44 1.05 2 0.28 4.06
Example 2
(64) In addition to the dose response, a comparison between the strengths before admixture addition and at the end of each protocol was analyzed. Any changes in strength would be due to the different mixing protocol as water and air contents were nominally equal. The increase in strength as a percentage of the initial strength of the concrete (before addition of the chemical admixture) was calculated as follows: (Final strength−initial strength)/initial strength.
(65) For Protocol 1, an average increase of 0.6±0.1% was observed, while, for Protocol 2, an average increase of 5.2±0.1% was observed. An ANOVA shows that the means of the sets were statistically different at a significance of 5%. The plus/minus values represent the variance around the mean value.
Example 3
(66) A further test was done regarding 28 strength properties of the concretes, as tested on the concrete mix before addition of the chemical admixture, to obtain additional confirmation that the water contents were similar for all mixes. The results from ANOVA showed no statistically significant different between the means of the two datasets.
Example 4
(67) The present inventors surmise that a hypothetical example could be used to validate the surprising advantages and benefits of the present invention. Consider a concrete delivery truck is leaving the batch plant on its way to a jobsite with a fresh load. The previous ten deliveries using the same mixer truck type and concrete mix design have yielded data, as obtained through the automated slump monitoring system, of an average ounce/inch slump response of four inches slump increase for each ounce of polymer cement dispersant chemical admixture (within a margin of +/−one half inch). The time required to administer and mix in has been ten minutes, plus or minus one minute. Using GPS (global positioning system) data, the time to jobsite arrival is predicted to be 44 minutes. Past deliveries have taken an average of 46 minutes±5 minutes. The current slump for the current delivery is at three inches (3″). Based on this information, the slump monitoring system will continue to maintain the slump at 3″ until the concrete mixer is 30 minutes from the jobsite (at which time, it will take 10 minutes to administer and mix in the chemical admixture, with five minutes to spare). This can be updated every minute, for example, to include further recent historical deliveries and changes in traffic or jobsite delays.
(68) The present invention is described herein using a limited number of illustrative embodiments not intended to limit the scope of the invention as otherwise described and claimed herein.