METHOD FOR PURGE CLEAN OF LOW PRESSURE FURNACE
20230265557 ยท 2023-08-24
Assignee
Inventors
Cpc classification
B08B5/00
PERFORMING OPERATIONS; TRANSPORTING
F27B17/0025
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
B08B9/0804
PERFORMING OPERATIONS; TRANSPORTING
C23C16/4405
CHEMISTRY; METALLURGY
C23C16/4408
CHEMISTRY; METALLURGY
B08B2209/08
PERFORMING OPERATIONS; TRANSPORTING
International classification
F27B17/00
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F27D25/00
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
B08B9/08
PERFORMING OPERATIONS; TRANSPORTING
B08B7/00
PERFORMING OPERATIONS; TRANSPORTING
B08B5/00
PERFORMING OPERATIONS; TRANSPORTING
Abstract
The present application discloses a method for purge clean of a low pressure furnace, comprising: step 1, providing a process chamber of the low pressure furnace in a standby state, wherein an inner wall thin film formed by a furnace deposition process is accumulated on the surface of an inner wall of the process chamber; step 2, performing temperature ramp-up or temperature ramp-down treatment on the process chamber to generate first thermal stress in the inner wall thin film, wherein thin film particles with poor adhesion in the inner wall thin film peels off; step 3, introducing a cleaning gas in a pulse manner to perform cycle purge clean on the process chamber, so as to remove the peeling thin film particles from the process chamber; and step 4, switching a state of the process chamber to the standby state after the cycle purge clean ends.
Claims
1. A method for purge clean of a low pressure furnace, comprising the following steps: step 1, providing a process chamber of the low pressure furnace in a standby state, wherein an inner wall thin film formed by a furnace deposition process is accumulated on the surface of an inner wall of the process chamber; step 2, performing temperature ramp-up or temperature ramp-down treatment on the process chamber to generate first thermal stress in the inner wall thin film, wherein thin film particles with poor adhesion in the inner wall thin film peels off due to release of the first thermal stress, the thin film particles with poor adhesion refer to thin film particles that will peel off during the subsequent furnace deposition process thin film particles, and the first thermal stress is greater than second thermal stress formed in the inner wall thin film during the furnace deposition process; step 3, introducing a cleaning gas in a pulse manner to perform cycle purge clean on the process chamber, so as to remove the peeling thin film particles from the process chamber; and step 4, switching a state of the process chamber to the standby state after the cycle purge clean ends.
2. The method for purge clean of a low pressure furnace according to claim 1, wherein the process chamber in step 1 undergoes the furnace deposition process more than one time.
3. The method for purge clean of a low pressure furnace according to claim 1, wherein the material of the inner wall of the process chamber in step 1 is quartz.
4. The method for purge clean of a low pressure furnace according to claim 3, wherein the process chamber presents a vertical tubular structure.
5. The method for purge clean of a low pressure furnace according to claim 1, wherein step 2 comprises the following substeps: step 21, performing the first temperature ramp-up treatment on the process chamber, wherein the first temperature ramp-up treatment ramps up the temperature of the process chamber from a standby temperature to a first temperature at a first temperature ramp-up rate, and during the first temperature ramp-up treatment, the first thermal stress is temperature ramp-up thermal stress and the first thermal stress becomes larger when the first temperature ramp-up rate becomes larger; step 22, performing high-temperature thermostatic treatment on the process chamber at the first temperature; step 23, performing the temperature ramp-down treatment on the process chamber, wherein the temperature ramp-down treatment ramps down the temperature of the process chamber from the first temperature to a second temperature at a second temperature ramp-down rate, the second temperature is less than the standby temperature, and during the temperature ramp-down treatment, the first thermal stress is temperature ramp-down thermal stress and the first thermal stress becomes larger when the second temperature ramp-down rate becomes larger; step 24, performing low-temperature thermostatic treatment on the process chamber at the second temperature; and step 25, performing the second temperature ramp-up treatment on the process chamber, wherein the second temperature ramp-up treatment ramps up the temperature of the process chamber from the second temperature to the standby temperature at a second temperature ramp-up rate, and during the second temperature ramp-up treatment, the first thermal stress is temperature ramp-up thermal stress and the first thermal stress becomes larger when the second temperature ramp-up rate becomes larger.
6. The method for purge clean of a low pressure furnace according to claim 5, wherein the cycle purge clean in step 3 starts when step 22 starts and ends when step 25 ends.
7. The method for purge clean of a low pressure furnace according to claim 6, after step 25, further comprising: performing third thermostatic treatment on the process chamber at the standby temperature, wherein during the third thermostatic treatment, the cycle purge clean is maintained in step 3, and when step 3 ends, the third thermostatic treatment ends and step 4 starts.
8. The method for purge clean of a low pressure furnace according to claim 6, wherein the first temperature in step 21 is determined by a process temperature of the furnace deposition process.
9. The method for purge clean of a low pressure furnace according to claim 6, wherein a time of the high-temperature thermostatic treatment in step 22 is 10-40 minutes.
10. The method for purge clean of a low pressure furnace according to claim 6, wherein in step 3, the cleaning gas comprises nitrogen, the cleaning gas is introduced with a pulse time of 2-5 minutes and an interval time of 2-5 minutes, and the cleaning gas is introduced at a gas flow rate of 30-500 sccm.
11. The method for purge clean of a low pressure furnace according to claim 6, wherein a time of the low-temperature thermostatic treatment in step 24 is 10-40 minutes.
12. The method for purge clean of a low pressure furnace according to claim 4, wherein the process chamber simultaneously grows thin films on a plurality of wafers during the furnace deposition process.
13. The method for purge clean of a low pressure furnace according to claim 12, wherein each of the wafers is placed in a boat.
14. The method for purge clean of a low pressure furnace according to claim 12, wherein a thin film material deposited by the furnace deposition process comprises polysilicon, silicon dioxide, or silicon nitride.
15. The method for purge clean of a low pressure furnace according to claim 1, wherein after step 4, the process chamber is on standby for the furnace deposition process of a next batch of the wafers.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0037] The present application will be further described in detail below with reference to the drawings and specific implementations:
[0038]
[0039]
[0040]
[0041]
[0042]
[0043]
DETAILED DESCRIPTION OF THE DISCLOSURE
[0044]
[0045] Step 1. A process chamber of the low pressure furnace in a standby state is provided.
[0046] For a structure of the process chamber, reference may be made to
[0047] In this embodiment of the present application, the material of the inner wall 101 of the process chamber is quartz.
[0048] The process chamber presents a vertical tubular structure.
[0049] The process chamber simultaneously grows thin films on a plurality of wafers 103 during the furnace deposition process.
[0050] Each of the wafers 103 is placed in a boat 102.
[0051] A thin film material deposited by the furnace deposition process includes polysilicon, silicon dioxide, or silicon nitride.
[0052] The process chamber in step 1 undergoes the furnace deposition process more than one time, such that a relatively large number of the thin film particles prone to peeling-off are accumulated in the inner wall thin film 104.
[0053] Step 2. Temperature ramp-up or temperature ramp-down treatment is performed on the process chamber to generate first thermal stress in the inner wall thin film 104, wherein a thin film particles with poor adhesion in the inner wall thin film 104 peels off due to release of the first thermal stress, the thin film particles with poor adhesion refer to thin film particles that will peel off during the subsequent furnace deposition processthin film particles, and the first thermal stress is greater than second thermal stress formed in the inner wall thin film 104 during the furnace deposition process.
[0054] In this embodiment of the present application, referring to
[0055] Step 21. The first temperature ramp-up treatment is performed on the process chamber, wherein the first temperature ramp-up treatment ramps up the temperature of the process chamber from a standby temperature to a first temperature at a first temperature ramp-up rate, and during the first temperature ramp-up treatment, the first thermal stress is temperature ramp-up thermal stress and the first thermal stress becomes larger when the first temperature ramp-up rate becomes larger.
[0056] In
[0057] In some embodiments, the first temperature is determined by a process temperature of the furnace deposition process.
[0058] Step 22. High-temperature thermostatic treatment is performed on the process chamber at the first temperature.
[0059] In
[0060] In some embodiments, a time of the high-temperature thermostatic treatment in step 22 is 10-40 minutes.
[0061] Step 23. The temperature ramp-down treatment is performed on the process chamber, wherein the temperature ramp-down treatment ramps down the temperature of the process chamber from the first temperature to a second temperature at a second temperature ramp-down rate, the second temperature is less than the standby temperature, and during the temperature ramp-down treatment, the first thermal stress is temperature ramp-down thermal stress and the first thermal stress becomes larger when the second temperature ramp-down rate becomes larger.
[0062] In
[0063] Step 24. Low-temperature thermostatic treatment is performed on the process chamber at the second temperature.
[0064] In
[0065] In some embodiments, a time of the low-temperature thermostatic treatment is 10-40 minutes.
[0066] Step 25. The second temperature ramp-up treatment is performed on the process chamber, wherein the second temperature ramp-up treatment ramps up the temperature of the process chamber from the second temperature to the standby temperature at a second temperature ramp-up rate, and during the second temperature ramp-up treatment, the first thermal stress is temperature ramp-up thermal stress and the first thermal stress becomes larger when the second temperature ramp-up rate becomes larger.
[0067] In
[0068] Step 3. A cleaning gas is introduced in a pulse manner to perform cycle purge clean on the process chamber, so as to remove the peeling thin film particles from the process chamber.
[0069] In this embodiment of the present application, the cycle purge clean in step 3 starts when step 22 starts and ends when step 25 ends.
[0070] In step 3, the cleaning gas includes nitrogen, the cleaning gas is introduced with a pulse time of 2-5 minutes and an interval time of 2-5 minutes, and the cleaning gas is introduced at a gas flow rate of 30-500 sccm. In
[0071] In some embodiments, after step 25, the method further includes: performing third thermostatic treatment on the process chamber at the standby temperature, wherein during the third thermostatic treatment, the cycle purge clean is maintained in step 3, and when step 3 ends, the third thermostatic treatment ends and step 4 starts. In
[0072] Step 4. A state of the process chamber is switched to the standby state after the cycle purge clean ends.
[0073] In
[0074] After step 4, the process chamber is on standby for the furnace deposition process of a next batch of the wafers 103. Since no thin film particles with poor adhesion exists in the process chamber after step 4 of this embodiment of the present application, the number of peeling particle defects can be significantly reduced in the subsequent furnace deposition process.
[0075] Different from an existing process where purge clean is performed under a high-temperature thermostatic condition by using a cleaning gas with a constant flow rate, this embodiment of the present application performs violent temperature ramp-up treatment or temperature ramp-down treatment on the process chamber. When a temperature change during the temperature ramp-up treatment or temperature ramp-down treatment becomes more violent, i.e., when a temperature change rate becomes larger, the first thermal stress applied to the inner wall thin film 104 becomes larger. In view of the feature, by increasing the magnitude of the first thermal stress to be greater than that of the second thermal stress formed in the inner wall thin film 104 during the furnace deposition process, the first thermal stress can peel off all the thin film particles with poor adhesion that are prone to peeling-off during the furnace deposition process. Subsequently, under the impact effect of the cycle purge clean, all the peeling thin film particles can be removed from the process chamber. Therefore, this embodiment of the present application can peel off all the thin film particles with poor adhesion in the inner wall thin film 104 which are accumulated inside the process chamber, thereby avoiding the risk of peeling-off of the thin film particles with poor adhesion in the subsequent furnace deposition process, and ultimately improving the product yield.
[0076] This embodiment of the present application violently ramps up or ramps down the temperature of the furnace chamber by means of the thermal stress principle, releasing the thin film stress accumulated on the furnace wall in the chamber and causing peeling-off of the thin film particles with poor adhesion from the furnace wall, and introducing the cleaning gas at intervals to effectively clean the furnace chamber, reducing the peeling particles of the inner wall of the furnace during the process. Therefore, this embodiment of the present application can more effectively peel off particles with poor adhesion on the inner wall of the furnace. Thermal stress is stress generated because the thin film cannot fully expand and contract freely when temperature changes due to internal and external constraints.
[0077] This embodiment of the present application can effectively reduce the peeling particles on a product by means of violent temperature ramp-up or ramp-down and cycle purge clean using the cleaning gas. In the long run, the peeling particles on the product are reduced by 10 particles, accounting for 33% of the original peeling particles.
[0078] The present application is described in detail above via specific embodiments, but these embodiments are not intended to limit the present application. Without departing from the principle of the present application, those skilled in the art can still make many variations and improvements, which should also be construed as falling into the protection scope of the present application.