PRECISE LIFTING METHOD AND LIFTING AND REINFORCING STRUCTURE FOR PLANT EQUIPMENT FOUNDATION
20220145576 · 2022-05-12
Inventors
Cpc classification
E02D19/18
FIXED CONSTRUCTIONS
E02D3/12
FIXED CONSTRUCTIONS
E02D35/00
FIXED CONSTRUCTIONS
International classification
Abstract
The present application relates to a precise lifting method and a lifting and reinforcing structure for a plant equipment foundation. The method includes the construction steps of: forming a curtain wall: drilling downwards at two sides of the plant equipment to form curtain holes and grouting the curtain holes, in which the grouting areas overlap each other to form two parallel curtain walls; forming a reinforcing body: drilling grouting holes inclining downwards, grouting the grouting holes to form the reinforcing body attached to a lower surface of a baseplate of the plant equipment foundation among a bottom of the baseplate and two curtain walls; and lifting: drilling lifting holes obliquely downwards to below the bottom of the reinforcing body and between two curtain walls; and conducting pressure grouting to the bottom of the lifting holes and then backward grouting upwards layer by layer.
Claims
1. A precise lifting method for a plant equipment foundation, comprising the following steps: Step S1, forming a curtain wall: drilling downwards in a vertical direction at two to-be-lifted sides of the plant equipment to form a plurality of curtain holes and grouting the curtain holes, wherein the grouting area overlap each other to form two parallel curtain walls for separation from non-lifting areas; Step S2, forming a reinforcing body: drilling grouting holes inclining downwards along the outer contour of the plant equipment in a length direction of the curtain wall, wherein the grouting holes are symmetrically provided at both sides of the plant equipment; grouting the grouting holes to form the reinforcing body attached to a lower surface of a baseplate of the plant equipment foundation among a bottom of the baseplate and two curtain walls, so as to form a substantially inverted U-shaped structure together with two curtain walls; and Step S3, lifting: drilling lifting holes obliquely downwards to below a bottom of the reinforcing body and between two curtain wall, wherein the lifting holes on both sides of the plant equipment are inclined toward each other; and conducting pressure grouting to the bottom of the lifting holes and then a backward grouting upwards layer by layer, whereby a soil body is pressed to generate an upward lifting force as a slurry in the curtain walls is continuously increased and solidified, so as to lift the plant equipment to a set lifting height equably.
2. The precise lifting method for a plant equipment foundation according to claim 1, wherein a plurality of rebars are provided between every two grouting holes in step S2, and the rebars are inserted obliquely into the reinforcing body and form a structure similar to reinforced concrete together with the reinforcing body, wherein the rebars at both sides of the plant equipment are inclined toward each other.
3. The precise lifting method for a plant equipment foundation according to claim 1, wherein the lifting height is monitored in real time by a precision leveling instrument based on the set lifting height in step S3.
4. The precise lifting method for a plant equipment foundation according to claim 1, wherein the depth of the curtain wall in step S1 is at least equivalent to a thickness of backfilling soil layer.
5. The precise lifting method for a plant equipment foundation according to claim 1, wherein a distance between adjacent curtain holes in step S1 is 2-3 m.
6. The precise lifting method for a plant equipment foundation according to claim 1, wherein a distance between the curtain hole and the plant equipment in step S1 is 1-2 m.
7. The precise lifting method for a plant equipment foundation according to claim 1, wherein a distance between adjacent grouting holes in step S2 is 2-3 m.
8. The precise lifting method for a plant equipment foundation according to claim 1, wherein the grouting is a drilling and grouting integrated backward grouting in step S1, comprising lifting and grouting for a depth and repeating the lifting and grouting.
9. The precise lifting method for a plant equipment foundation according to claim 1, wherein a plurality of curtain holes are drilled around the plant equipment in step S1 and grouted in such a way that the grouting areas overlap with each other to form a closed curtain wall.
10. The precise lifting method for a plant equipment foundation according to claim 1, wherein a slurry for grouting the grouting holes to form the reinforcing body is solidified in 30-60 s and a pressure slurry for lifting is solidified in 10-30 s.
11. A precise lifting and reinforcing structure for a plant equipment foundation, wherein the precise lifting and reinforcing structure is a lifting and reinforcing structure constructed by the precise lifting method for a plant equipment foundation according to claim 1.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0030]
[0031]
[0032]
[0033]
DETAILED DESCRIPTION
[0034] The application is further described in detail below in combination with Figures.
[0035] The present application provides a precise lifting method for plant equipment foundation. A strip shaped plant equipment is taken as an example in the following for explaining, and the plant equipment is hereinafter referred to as equipment. The precise lifting method includes following steps:
[0036] Step S1, forming a curtain wall 1: referring to
[0037] Grout is filled into the curtain holes 11, in which the grouting areas overlapped each other, so as to form two parallel curtain walls 1, the height of which may be equal to the thickness of the backfilling soil layer. The curtain wall 1 separates the lifting area of the equipment from the non-lifting area, which can prevent causing disturbance to surrounding backfilling soil layer during subsequent equipment lifting which otherwise would lifts the surrounding equipment. In addition, the curtain wall 1 separates the lifting area from the non-lifting area, which can bring no influence to the surrounding equipment and lift the subsiding equipment. Specifically, in the condition of causing no influence to the operation of the equipment, a row of curtain holes 11 are provided at 1 m distance from an outer edge of the equipment, in which the distance of the adjacent curtain holes 11 is 2 m. Holes are drilled downwards in the vertical direction and then grout is filled into the curtain holes 11 to form the curtain wall 1 with a height of 9 m. During construction, a drilling and grouting integrated backward grouting technology is adopted, that is, drilling the curtain holes 11 to the design deepness, lifting and then grouting for a length of 0.3-0.5 m, and repeating the lifting and grouting. In this way, the formed curtain wall 1 has a better integrity and it is easy to pull out the drilling stem after the grouting. The grouting pressure inside the curtain hole 11 is determined according to the design thickness and stratum.
[0038] Step S2, forming reinforcing body: referring to
[0039] Further, in order to prevent the bulging phenomenon at local area during grouting and lifting, a plurality of rebars 3 are provided between adjacent grouting holes 21, in which the tilt direction of the rebar 3 is in line with that of the grouting hole 21. The rebar 3 is obliquely inserted into the reinforcing body 2 and forms a reinforced concrete together with the reinforcing body 2. Specifically, the rebar 3 is provided in the middle of adjacent grouting holes 21, and is inserted into the reinforcing body 2 in an inclining angle of 45°, in which the inserted length in the reinforcing body 2 is 3 m. Then the grouting holes 21 is grouted to integrate the rebar 3 with reinforcing body 2 to increase the integrity of the reinforcing body 2, so that the equipment can be lifted equably and prevent the bulging phenomenon in local lifting area during lifting. In addition, inserting rebars 3 can reduce the thickness of the reinforcing body 2 and in turn reduce the height of the curtain wall 1 to save grouting material.
[0040] Step S3, lifting: referring to
[0041] During the lifting process, in order to ensure the lifting height in each position and monitor the lifting velocity in each position, testing points are arranged at equal distance along the outer contour of the equipment. The heights at each testing points are monitored in real time using precise leveling instrument based on on-site reference elevation, so as to, monitor the lifting height at each testing point accurately and timely for facilitating adjusting the corresponding grouting velocity and lifting velocity.
[0042] The above description is made using a strip shaped equipment as an example. When the equipment is not regular square or rectangle, a plurality of curtain holes 11 are drilled along the circumference of the equipment, and grouted in such a way that the grouting areas overlap with each other to form a closed curtain wall 1. A reinforcing body 2 in formed in the closed structure of the curtain wall 1, and grouting for lifting is performed therein. This can effectively prevent the diffusion of the grouting slurry, so as to control the lifting velocity more easily and further realize the precise lifting.
[0043] In order to avoid an accelerated subsidence of the equipment during the whole construction process due to softening of the soil body under and around the equipment. All the slurries used for grouting are of quickly solidified type. Preferably, the grouting slurry forming the reinforcing body 2 is solidified in 30-60 s after being ejected from the nozzle of the grouting pipe, and the pressure slurry for lifting is solidified in 10-30 s after being ejected from the nozzle of the grouting pipe. The slurry used for grouting can be single slurry or double slurries.
[0044] Preferably, the above-mentioned slurry used to form the reinforcing body 2 and the pressure slurry used for lifting are two-component composite slurry. For convenience of description, it is named as slurry A and slurry B. Two slurries reach the slurry outlet of the grouting pipe from different channels, and are injected into the soil body around the slurry outlet, by which chemical reaction occurs to cause initial solidification in a short time.
[0045] The slurries for grout can be any one of existing slurries, as long as they can meet the requirements for initial solidification time and has good permeability.
[0046] Following is a formula of a grouting slurry which can be used with the present application: slurry A includes the following raw materials by weight parts: 70-90 parts of metallic oxide and/or metal hydroxide, 0.5-1.2 parts of composite retarder, 0.5-0.7 part of water reducer, 0.7-1.5 parts of acid-base buffer, 3-5 parts of composite stabilizer and 0.5-1.5 parts of composite surfactant. In particular, the metal oxide can be a combination of any two of magnesium oxide, alumina and magnesium phosphate. The composite retarder is urea and sodium tripolyphosphate. The water reducing agent is polycarboxylic acid water reducer. The acid-base buffer is magnesium carbonate or potassium hydroxide. The composite stabilizer includes at least two of hydroxymethyl cellulose, N-alkyl cetyl alcohol, starch ether and cellulose ether. The composite surfactant is at least two of alkyl polyoxyethylene ether, benzylphenol polyoxyethylene ether and alkyl sulfonate. When two or more different materials are used in the above individual components, they can be added by equivalent amount. Providing two materials are mainly to prevent the failure of one of them, so as to make the effect of the whole composite slurry more stable.
[0047] Slurry B includes the following raw materials by weight parts: 30˜40 parts of phosphate and 0.2˜1 part of defoamer. In particular, the phosphate can be diammonium hydrogen phosphate or potassium dihydrogen phosphate; and the defoamer can be silicone defoamer or polyether defoamer.
[0048] Slurry A and slurry B are mixed with water by a weight ratio of 100:(40-50) to form slurries respectively, injected into grouting pipe through different pipelines, combined with each other at the slurry outlet and solidified in the soil body.
[0049] Different initial solidification times of the composite slurry are realized by adjusting proportion of the composite retarder. Preferably, during pressure grouting in lifting process, less water should be added, so as to increase the concentration of grouting slurry to press the surrounding soil body better (for example, the weight ratios of slurry A to water and slurry B to water are 100:40). For other slurries for grouting, more water should be added and the concentration of grouting slurry is small (for example, the weight ratios of slurry A to water and slurry B to water are 100:50).
[0050] The above are the preferred embodiments of the present application, which are not intend to limit the protection scope of the present application. Therefore, all equivalent changes made according to the structure, shape and principle of the present application should be covered within the protection scope of the present application.