Bridge construction system and method

11319679 · 2022-05-03

    Inventors

    Cpc classification

    International classification

    Abstract

    The bridge construction system and method according to the present invention provides a lightweight, efficient, economical, long-lasting, and easily implemented composite steel structure that can be filled with concrete in place for the construction of pedestrian and smaller road bridges, specifically those found in rural areas. The bridge construction system of the present invention is unique in that it is a steel-frame reinforced composite bridge with decking and rebar caging that provides a permanent, non-removable form for poured-in-place concrete. The composite nature of the bridge allows for installation of the bridge to take place in one day, while the entire process from site preparation such as grading and excavation to cleanup takes a week or less. The quick installation of the bridge is designed to have a minimally invasive impact on the surrounding environment.

    Claims

    1. A bridge construction system comprising: a plurality of abutment walls, wherein said abutment walls are hollow; a plurality of steel wing walls or head walls, wherein said wing walls or head walls are hollow; a plurality of lower steel beams; a plurality of steel scour edge beams; a plurality of lower rebar mats; a plurality of scour edge beam rebar cages; a plurality of upper steel tub girders; a plurality of upper decking panels; and a plurality of upper rebar mats.

    2. The bridge construction system of claim 1, wherein each of the steel abutment walls are each connected together with two of the steel wing walls or head walls so that two or more single walls exist prior to delivery to a jobsite.

    3. The bridge construction system of claim 1, wherein the steel abutment walls come in heights of 6 foot, 8 foot, or 10 foot.

    4. The bridge construction system of claim 1, wherein said bridge construction system is designed to be capable of spanning a waterway from a width of 15 feet up to 40 feet in increments of 5 feet.

    5. The bridge construction system of claim 1, wherein said bridge construction system is designed to be capable of being built to cover roadway widths from 20 feet up to 38 feet in 2 foot increments.

    6. The bridge construction method of claim 1, wherein said steel abutment and steel wing walls are covered in a corrosion resistant finish to provide maximum longevity of the steel and to protect against negative environmental and wildlife impacts.

    7. The bridge construction method of claim 6, wherein said corrosion resistant finish may be a zinc flame spray or zinc primer.

    8. The bridge construction system of claim 1, wherein various edge options are available for the traffic way sides of the bridge, including a standard curb design, a modified k-rail design, guardrail support, or even an ADA compliant guardrail for pedestrian bridges.

    9. The bridge construction system of claim 1, wherein said bridge construction system meets American Association of State Highway Transportation Officials loading standards (AASHTO HL-93).

    10. A method of constructing a bridge construction system, said method comprising the steps of: a. preparing a site where the bridge construction system is to be installed, which comprises demolition of previous infrastructure, if applicable, and excavation and bridge base preparation; b. installing a foundation of the bridge; c. installing hollow steel abutment walls and hollow steel wing walls or head walls and braces, wherein the steel abutment walls and steel wing walls have already been connected together, where said installing comprises the far abutment and wing wall being set on the foundation, braced and leveled and then the near abutment and wing wall being set on the precast concrete setting blocks, braced and leveled; d. installing or setting of a plurality of lower steel beams and a plurality of lower steel scour edge beams; e. installing a plurality of lower rebar mats and a plurality of scour edge beams rebar cages; f. installing a plurality of upper steel tub girders; g. installing of a plurality of upper decking panels; h. installing a plurality of upper rebar mats; and i. pouring of concrete over the lower rebar mats, two scour edge beams rebar cages, the plurality of upper rebar mats, and infilling the hollow portions of the hollow steel abutment walls and hollow steel wing walls.

    Description

    BRIEF DESCRIPTION OF THE DRAWINGS

    (1) FIG. 1 is an exploded perspective view of a bridge construction system of the present invention showing some of the various components;

    (2) FIG. 2 is an environmental perspective view of the present invention depicting step 2 of the method of the present invention and some components of the bridge construction system of the present invention;

    (3) FIG. 3 is an environmental perspective view of the present invention depicting step 3 of the method of the present invention and some components of the bridge construction system of the present invention;

    (4) FIG. 4 is an environmental perspective view of the present invention depicting step 4 of the method of the present invention and some components of the bridge construction system of the present invention;

    (5) FIG. 5 is an environmental perspective view of the present invention depicting step 5 of the method of the present invention and some components of the bridge construction system of the present invention;

    (6) FIG. 6 is an environmental perspective view of the present invention depicting step 6 of the method of the present invention and some components of the bridge construction system of the present invention;

    (7) FIG. 7 is an environmental perspective view of the present invention depicting step 7 of the method of the present invention and some components of the bridge construction system of the present invention;

    (8) FIG. 8 is an environmental perspective view of the present invention depicting step 8 of the method of the present invention and some components of the bridge construction system of the present invention;

    (9) FIG. 9 is an environmental perspective view of the present invention after step 7 depicting another embodiment of the present invention wherein a different tub girder design was used.

    DESCRIPTION

    (10) Referring now to the drawings, reference will be made to the preferred embodiment of the invention, an example of which is illustrated in the accompanying drawings and not meant for purposes of limiting the scope of the present invention. With reference to FIG. 1, it is generally shown a bridge construction system 1 of the present invention, depicting various components comprising said system. The bridge construction system of the present invention is comprised of at least eight precast concrete setting blocks 2 (not shown in FIG. 1; see FIGS. 2-9) that act as the foundation of the bridge, two hollow steel abutment walls 3, four hollow steel wing walls 4 (or flat head walls dependent on the specific design requirements of the customer), a plurality of lower steel beams 5, two steel scour edge beams 6, lower rebar mats 7 (not shown in FIG. 1; see FIG. 5), scour edge beam rebar cages (not shown), a plurality of upper steel tub girders 8, a plurality of upper decking panels 9, upper rebar mats 10, and any means for fastening the various components as needed.

    (11) The bridge construction system of the present invention is unique in that it is a steel-frame reinforced composite bridge with decking and rebar caging that provides a permanent, non-removable form for poured-in-place concrete. The composite nature of the bridge allows for installation of the bridge to take place in one day, while the entire process from site preparation such as grading and excavation to cleanup takes a week or less. The quick installation of the bridge is designed to have a minimally invasive impact on the surrounding environment. Further, all steel components that are exposed to earth and water are covered with a finish for corrosion resistance as well and environmental and wildlife concerns. Such a finish may be a zinc flame spray or a zinc primer, among other options.

    (12) The bridge construction system of the present invention is intended to provide various design options to customers dependent on their needs. For example, the steel abutment walls are intended to be available in heights of 6 feet, 8 feet, or 10 feet. Further, the bridge construction system is intended to cover roadway widths from 20 feet up to 38 feet in two foot increments. The bridge construction system is also designed to cover a span of a waterway from 15 feet to 40 feet in five foot increments. Also, dependent on the type of bridge and the needs of the customer, various options are available for the traffic way sides of the bridge, from standard curb design, to modified k-rail design, guardrail support, or even an ADA compliant guardrail for pedestrian bridges.

    (13) The method for constructing the bridge construction system of the present invention is depicted in FIG. 2 through FIG. 8. The method of construction is comprised of the following steps. The first step is preparing the site where the bridge construction system is to be installed, which comprises demolition of previous infrastructure, if applicable, and excavation and bridge base preparation. Bridge base preparation comprises the site being properly graded and backfilled. The second step is depicted in FIG. 2 and comprises installing the precast concrete setting blocks 2 or “wallpads” according to a specific design's specifications which act as the foundation of the bridge. A minimum of eight precast concrete setting blocks 2 are used. Only six can be seen in FIG. 2 because the other two are covered up due to the angle of the environmental drawing. FIG. 3 depicts the third step which comprises installing the steel abutment walls 3 and steel wing walls 4 or flat head walls (dependent on design) and braces. The abutment walls 3 and corresponding wing walls 4 or flat head walls come to the site already connected together as once single piece/wall. The far abutment and wing wall is set on the precast setting blocks, braced and leveled and then the near abutment and wing wall is set on the precast setting blocks, braced and leveled. The only difference between a wing wall and a flat head wall design is that a wing wall is connected to the abutment wall at an angle, thereby creating a “wing” and a flat head wall is connected along the same line as the abutment wall. In other words, there is no angle or set off between the abutment wall and a flat head wall.

    (14) FIG. 4 depicts the fourth step which comprises installing or setting of the plurality of lower steel beams 5 and the two lower steel scour edge beams 6.

    (15) FIG. 5 depicts the fifth step which comprises installing of the lower rebar mats 7 and the scour edge beams rebar cages (not shown).

    (16) FIG. 6 depicts the method's sixth step which comprises installing the plurality of upper steel tub girders 8.

    (17) FIG. 7 depicts the seventh step in the method which comprises the installing of the plurality of upper decking panels 9.

    (18) FIG. 8 depicts the eighth step which comprises installing the upper rebar mats 10.

    (19) The ninth step comprises the pouring of the concrete where necessary, including the infilling of the composite steel structure of the present invention, specifically the infilling of the abutment walls 3 and corresponding wing walls 4 or flat head walls. Concrete is also poured over the lower rebar mats and the upper rebar mats and decking. The final step comprises site cleanup.

    (20) FIG. 9 depicts another embodiment of the present invention wherein a different tub girder design was used.

    (21) Various changes, alternatives and modifications may become apparent to one of ordinary skill in the art following a reading of the foregoing specification. It is intended that any such changes, alternatives, and modifications within the scope of the appended claims be considered a part of the present invention. Further, it is within the ambit of the present invention to cover any obvious modifications of the preferred embodiment described herein.