TWO-STAGE ENERGY DISSIPATION TYPE SHED TUNNEL SUPPORT STRUCTURE CONNECTED BY PRINCIPLE OF DOUGONG AND A DESIGN METHOD THEREOF
20220127804 · 2022-04-28
Assignee
Inventors
- Zhixiang Yu (Chengdu, CN)
- Liru Luo (Chengdu, CN)
- Linxu LIAO (Chengdu, CN)
- Yuntao Jin (Chengdu, CN)
- Lijun ZHANG (Chengdu, CN)
- Hu Xu (Chengdu, CN)
- Lei Zhao (Chengdu, CN)
- Hao ZHAO (Chengdu, CN)
- Shichun Zhao (Chengdu, CN)
Cpc classification
International classification
Abstract
A two-stage energy dissipation type shed tunnel support structure connected by a principle of Dougong and a design method thereof are provided. The two-stage energy dissipation type shed tunnel support structure includes a Dougong joint domain, crossbeams and columns. The Dougong joint domain includes section steel members, wavy-wall cylindrical elastoplastic buffers, U-shaped sliding connecting troughs and high-strength bolts. Multiple layers of the section steel members are orthogonally stacked to form a Dougong shape, the wavy-wall cylindrical elastoplastic buffers are arranged between adjacent layers of the section steel members, and the U-shaped sliding connecting troughs are arranged at upper and lower ends of the wavy-wall cylindrical elastoplastic buffers, which realizes a connection between the wavy-wall cylindrical elastoplastic buffers and a section steel in two orthogonal directions. Under an impact of small energy rockfalls, an elastic deformation of the Dougong joint domain is used to achieve a buffering.
Claims
1. A two-stage energy dissipation type shed tunnel support structure connected by a principle of Dougong, comprising: a Dougong joint domain, a crossbeam and columns, wherein lower ends of the Dougong joint domain are supported on the columns, and upper ends of the Dougong joint domain support the crossbeam; the Dougong joint domain comprises section steel members, buffers, and U-shaped sliding connecting troughs; the section steel members are arranged in a plurality of layers, upper and lower layers of the section steel members are connected by the buffers, and the plurality of layers of the section steel members are orthogonally stacked to form a “gong”; a “Dou”-shaped support structure comprises the buffers and the U-shaped sliding connecting troughs arranged at two ends of the buffers, and the U-shaped sliding connecting troughs at the two ends of the buffers are respectively connected to the upper and lower layers of the section steel members.
2. The two-stage energy dissipation type shed tunnel support structure according to claim 1, wherein the crossbeam is supported on top section steel members of the Dougong joint domain, a first side of an angle steel is fixed to the top section steel members, and a second side of the angle steel is fixed to the crossbeam.
3. The two-stage energy dissipation type shed tunnel support structure according to claim 1, wherein steel plates are fixed at bottoms of the buffers below bottom section steel members of the Dougong joint domain, and high-strength bolts penetrate through the steel plates to fix the steel plates to the columns.
4. The two-stage energy dissipation type shed tunnel support structure according to claim 1, wherein each the U-shaped sliding connecting troughs is provided with slotted holes, and high-strength bolts penetrate through the slotted holes and the high-strength bolts are fixed in corresponding reserved holes on a side wall of a corresponding section steel member.
5. The two-stage energy dissipation type shed tunnel support structure according to claim 2, wherein corresponding positions of connection surfaces of the angle steel and the crossbeam are preset with slotted holes, high-strength bolts penetrate through the angle steel and the crossbeam to pre-tighten the angle steel and the crossbeam, and when the two-stage energy dissipation type shed tunnel support structure is impacted, the crossbeam controllably slides along the slotted holes to form a friction energy dissipation surface.
6. The two-stage energy dissipation type shed tunnel support structure according to claim 2, wherein a flange is provided between the crossbeam and the top section steel members to ensure that the crossbeam accurately transmits an upper load to an expected position of the Dougong joint domain.
7. The two-stage energy dissipation type shed tunnel support structure according to claim 1, wherein the buffers are wavy-wall cylindrical elastoplastic buffers, wherein the wavy-wall cylindrical elastoplastic buffers are formed by pressing thin-walled short tubes of an elastoplastic material with wavy walls.
8. The two-stage energy dissipation type shed tunnel support structure according to claim 1, wherein each layer of the plurality of layers comprises more than two section steel members.
9. The two-stage energy dissipation type shed tunnel support structure according to claim 1, wherein a side wall of the U-shaped sliding connecting troughs is closely attached to a side wall of the section steel members, and the side wall of the U-shaped sliding connecting troughs is pre-polished by a shot blasting to form a friction energy dissipation surface.
10. A design method of the two-stage energy dissipation type shed tunnel support structure connected by the principle of Dougong according to claim 1, comprising the following steps: a. presetting a protection capability E.sub.impact of a shed tunnel; b. calculating an impact energy E.sub.structure received by the two-stage energy dissipation type shed tunnel support structure, wherein a calculation formula is expressed as:
11. The two-stage energy dissipation type shed tunnel support structure according to claim 2, wherein steel plates are fixed at bottoms of the buffers below bottom section steel members of the Dougong joint domain, and high-strength bolts penetrate through the steel plates to fix the steel plates to the columns.
12. The two-stage energy dissipation type shed tunnel support structure according to claim 2, wherein each of the U-shaped sliding connecting troughs is provided with slotted holes, and high-strength bolts penetrate through the slotted holes and the high-strength bolts are fixed in corresponding reserved holes on a side wall of a corresponding section steel member.
13. The two-stage energy dissipation type shed tunnel support structure according to claim 2, wherein the buffers are wavy-wall cylindrical elastoplastic buffers, wherein the wavy-wall cylindrical elastoplastic buffers are formed by pressing thin-walled short tubes of an elastoplastic material with wavy walls.
14. The two-stage energy dissipation type shed tunnel support structure according to claim 3, wherein the buffers are wavy-wall cylindrical elastoplastic buffers, wherein the wavy-wall cylindrical elastoplastic buffers are formed by pressing thin-walled short tubes of an elastoplastic material with wavy walls.
15. The two-stage energy dissipation type shed tunnel support structure according to claim 4, wherein the buffers are wavy-wall cylindrical elastoplastic buffers, wherein the wavy-wall cylindrical elastoplastic buffers are formed by pressing thin-walled short tubes of an elastoplastic material with wavy walls.
16. The two-stage energy dissipation type shed tunnel support structure according to claim 5, wherein the buffers are wavy-wall cylindrical elastoplastic buffers, wherein the wavy-wall cylindrical elastoplastic buffers are formed by pressing thin-walled short tubes of an elastoplastic material with wavy walls.
17. The two-stage energy dissipation type shed tunnel support structure according to claim 6, wherein the buffers are wavy-wall cylindrical elastoplastic buffers, wherein the wavy-wall cylindrical elastoplastic buffers are formed by pressing thin-walled short tubes of an elastoplastic material with wavy walls.
18. The two-stage energy dissipation type shed tunnel support structure according to claim 2, wherein each layer of the plurality of layers comprises more than two section steel members.
19. The two-stage energy dissipation type shed tunnel support structure according to claim 3, wherein each layer of the plurality of layers comprises more than two section steel members.
20. The two-stage energy dissipation type shed tunnel support structure according to claim 4, wherein each layer of the plurality of layers comprises more than two section steel members.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0037] In order to describe the technical solutions in the embodiments of the present application or in the prior art more clearly, the following briefly introduces the accompanying drawings required for describing the embodiments or the prior art. Apparently, the accompanying drawings in the following description show some embodiments of the present application, and a person of ordinary skill in the art may still derive other drawings from these accompanying drawings without creative efforts.
[0038]
[0039]
[0040]
[0041]
[0042]
[0043]
[0044]
[0045]
[0046] In the figures, the same reference signs are used to denote the same structures or parts, and the names of the structures or parts corresponding to the reference signs are as follows:
[0047] 1—Dougong joint domain; 11—section steel member; 12—wavy-wall cylindrical elastoplastic buffer; 13—U-shaped sliding connecting trough; 14—high-strength bolt A; 2—crossbeam; 3—column; 4—angle steel; 5—rectangular steel plate; 6—high-strength bolt B; 7—corbel; 8—flange; 9—buffer layer; 10—concrete slab.
DETAILED DESCRIPTION OF THE EMBODIMENTS
[0048] In order to make the objectives, technical solutions and advantages of the present application clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present application. Apparently, the described embodiments are only part of the embodiments of the present application, not all of them. All other embodiments obtained by those of ordinary skill in the art without creative efforts based on the embodiments of the present application shall fall within the protection scope of the present application.
[0049] In the present application, energy dissipation buffering beam-column connection joints are formed based on the principle of Chinese ancient architectural Dougong, to achieve the effects of elastoplastic deformation buffering, friction energy dissipation, outrigger supporting and the like similar to those of plate springs. Under the impact of small energy rockfalls, the elastic deformation of Dougong joint domain can be used to achieve buffering; under the impact of large energy rockfalls, the elastoplastic deformation of the Dougong joint domain and the friction between members can be used to achieve energy dissipation; therefore, two-stage energy dissipation buffering capacity is achieved, and a novel rockfall protection shed tunnel support structure is formed. The Dougong joint domain of the support structure can be completely prefabricated, serialized and conventionalized, is easy to assemble and can be replaced independently, which facilitates the assembly and maintenance of the shed tunnel structure.
[0050] As shown in
[0051] In the embodiment of the present application, as shown in
[0052] Each layer has not less than two section steel members 11, which are orthogonally overlapped in vertical and horizontal directions and stacked in multiple layers to form a “gong”. There is a certain height difference between the stacked adjacent layers of section steel members 11 for arranging the buffers.
[0053] As shown in
[0054] The wavy-wall cylindrical elastoplastic buffers 12 and the U-shaped sliding connecting troughs 13 constitute a “Dou”. The U-shaped sliding connecting trough 13 is provided with slotted holes that are aligned with preset slotted holes at corresponding positions of a section steel side wall, and the high-strength bolts A 14 penetrate the slotted holes of the two for pre-tightening. The side wall of the U-shaped sliding connecting trough 13 is closely attached to the section steel side wall, and is pre-polished by shot blasting to form a friction energy dissipation surface.
[0055] As shown in
[0056] The corresponding positions of connection surfaces of the angle steel 4 and the side wall of the crossbeam 2 are preset with slotted holes, aligned and pre-tightened by high-strength bolts B 6, so that when the structure is impacted, the crossbeam 2 can controllably slide along the slotted holes to form a friction energy dissipation surface.
[0057] A flange 8 is provided between the crossbeam 2 and the top section steel member 11 of a joint to ensure that the crossbeam accurately transmits the upper load to an expected position of the Dougong joint domain 1.
[0058] A layer of wavy-wall cylindrical elastoplastic buffers 12 is arranged below the bottom section steel members 11 of the Dougong joint domain 1, the wavy-wall cylindrical elastoplastic buffers 12 are still connected with the section steel members 11 by the U-shaped sliding connecting troughs 13, rectangular steel plates 5 are welded below the buffers, the steel plates 5 are punched, and the Dougong joint domain 1 are connected with the columns 3 of the support structure by high-strength bolts B 6.
[0059] As shown in
[0060] The protective shed tunnel of the two-stage energy dissipation type shed tunnel support structure connected by Dougong joint domain increases the energy dissipation path and improves the overall energy dissipation capacity of the rockfall protective shed tunnel. Under the impact of small energy rockfalls, the elastic deformation of the Dougong joint domain can be used to achieve buffering; under the impact of large energy rockfalls, the elastoplastic deformation of the Dougong joint domain can be used to achieve energy dissipation; therefore, the support structure has two-stage energy dissipation buffering capacity, and can meet the protection requirements for large energy impact. The crossbeams and columns are connected by the Dougong joint domain which are prone to elastoplastic deformation, the Dougong joints are prefabricated and easy to process and replace, and once the shed tunnel is impacted, the joints can complete energy dissipation buffering and be quickly replaced, so that the protective shed tunnel quickly restores to the normal working status to ensure the smoothness of traffic lifelines; meanwhile, the Dougong joint domain with buffering performance protect the ends of the crossbeams and columns, which prolongs the service life of the structure and has significant economic advantages.
Embodiment of Design Method
[0061] The following specifically describes, in combination with a rockfall disaster site, a design method of the two-stage energy dissipation type shed tunnel support structure connected by Dougong joint domain:
[0062] As shown in
[0063] The impact energy received by the two-sided support structure is E.sub.structure=αφE.sub.impact, where α is an energy dissipation distribution coefficient of the support structure, and is 0.4 here; φ is a safety factor, and is 2, then E.sub.structure=0.4*2*1000 =800 kJ;
[0064] A single Dougong joint domain dissipates energy E.sub.Dougong=βE.sub.structure, and the two-sided support structure has a total of four buffering joints, so the value of β is 0.25, E.sub.Dougong=200 kJ;
[0065] The preset number of layers of the Dougong joints is n=4;
[0066] The energy dissipation buffering capacity of a single wavy-wall cylindrical elastoplastic buffer is E.sub.S≥E.sub.Dougong/4n, namely E.sub.S≥12.5 kJ;
[0067] The wavy-wall cylindrical elastoplastic buffers of corresponding specifications are selected according to the required energy dissipation capacity, wherein the specification parameters are: material type, wall thickness, cylindrical diameter and height, and wave number. Details are not described herein again;
[0068] Section steel members of corresponding specifications are designed according to the flexural bearing capacity, wherein the principle of design is, under rated energy dissipation requirements, only the plastic deformation of the cross section is considered, and the following should be satisfied:
[0069] Where, M is a maximum bending moment that a member bears, the member almost only bears uniaxial bending moment, and the value of bending moment can be obtained by numerical calculation; W is a net section modulus of an axis corresponding to the bending moment; γ is a section plastic development coefficient, which is not more than 1.1; f is a design value of bending strength of steel;
[0070] The required bearing capacities of crossbeams and columns are obtained by numerical calculations, and the crossbeams and columns of the support structure are designed in accordance with Steel Structure Design Standard GB50017-2017 and Concrete Structure Design Code GB 50010-2010;
[0071] Whether the protection requirements are met is checked by numerical calculations or experiments.
[0072] Finally, it should be noted that the above embodiments are merely intended to describe the technical solutions of the present application, instead of limiting the present application. Although the present application is described in detail with reference to the aforementioned embodiments, a person of ordinary skill in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features therein may be equivalently substituted; and these modifications or substitutions do not cause the essence of the technical solutions to depart from the spirit and scope of the technical solutions of the embodiments of the present application.