Encapsulated Duct Cable with Identification Tags and Manufacturing Method Thereof
20210355633 · 2021-11-18
Assignee
Inventors
Cpc classification
D07B1/141
TEXTILES; PAPER
International classification
Abstract
The present invention discloses an encapsulated duct cable with identification tags and a manufacturing method thereof. The logging encapsulated duct cable comprises an encapsulation layer. The cross section of the encapsulation layer is polygonal or arc-shaped. At least one cable protective tube and at least one oil-liquid tube are arranged in the encapsulation layer. A cable is arranged in the cable protective tube. Identification tags with different color identifiers are respectively arranged on one side of the cable protective tube and one side of the oil-liquid tube in one to one correspondence. The manufacturing method of the logging encapsulated duct cable mainly comprises three steps of machining the cable protective tube and paving the cable pavement, machining the oil-liquid tube, and machining the encapsulation layer. The present invention has double functions of conveying the oil and the liquid and transmitting the data.
Claims
1. An encapsulated duct cable with identification tags, comprising an encapsulation layer (1), wherein the cross section of the encapsulation layer (1) is polygonal or arc-shaped; at least one cable protective tube (2) and at least one oil-liquid tube (3) are arranged in the encapsulation layer (1); a cable (4) is arranged in the cable protective tube (2); identification tags (5) with different color identifiers are respectively arranged on one side of the cable protective tube (2) and one side of the oil-liquid tube (3) in one to one correspondence.
2. The encapsulated duct cable with identification tags according to claim 1, wherein the identification tag (5) is a rope or a narrow band.
3. The encapsulated duct cable with identification tags according to claim 1, wherein the encapsulation layer (1) is made from a thermoplastic material; the cable protective tube (2) is made of an 825 steel tube; the oil-liquid tube (3) is made of a 2507 steel tube.
4. The encapsulated duct cable with identification tags according to claim 1, wherein the cable (4) comprises a jacket (401), an insulation layer (402) and a core (403) which are sequentially arranged from exterior to interior.
5. The encapsulated duct cable with identification tags according to claim 4, wherein the jacket (401) is made from the polypropylene (PP); the insulation layer (402) is made from the fluorinated ethylene propylene (FEP) copolymer.
6. A manufacturing method of the encapsulated duct cable with identification tags according to claim 1, comprising the following steps: step 1: machining the cable protective tube and paving the cable: placing a steel coil raw material for producing the cable protective tube (2) on a steel band winding device; placing a wound cable (4) on a cable winding device; guiding the start end of the steel coil raw material to sequentially pass through a steel tube initial forming device, the cable winding device, a steel tube laser welding device, a nondestructive testing device, a steel tube drawing device and a traction device to produce the cable protective tube (2) sleeving the cable (4); winding the cable protective tube (2) by a cable protective tube winding device for later use; step 2: machining the oil-liquid tube: placing a steel coil raw material for producing the oil-liquid tube (3) on the steel band winding device; guiding the start end of the steel coil raw material to sequentially pass through a steel tube forming device, the steel tube laser welding device, an outer bur removing device, the steel tube drawing device, an annealing furnace and the nondestructive testing device to produce the oil-liquid tube (3); winding the oil-liquid tube (3) by an oil-liquid tube winding device for later use; step 3: machining the encapsulation layer: placing the cable protective tube (2) and the oil-liquid tube (3), which need to be encapsulated, on a relative winding device; guiding the start ends of the cable protective tube (2) and the oil-liquid tube (3) to sequentially pass through a steel tube straightening device, a steel tube preheating device, an identification tag winding device, an encapsulation and extrusion device, a cooling device and a traction device to form the encapsulation layer (1); winding the encapsulated duct cable by the winding device.
7. The manufacturing method of the encapsulated duct cable with identification tags according to claim 6, wherein the steel coil raw materials for producing the cable protective tube (2) and the oil-liquid tube (3) are degreased by utilizing alkaline hot water.
8. The manufacturing method of the encapsulated duct cable with identification tags according to claim 6, wherein the steel tube preheating device comprises a hot air blower (6) and a preheating tube (7), which are communicated through a tube; two ends of the preheating tube (7) are connected with plugs (8) in a sealing manner; multiple tube through holes (9) are formed in the center of the plug (8).
9. The manufacturing method of the encapsulated duct cable with identification tags according to claim 6, wherein the encapsulation and extrusion device comprises a die case (10) and a die core (11), which match with each other in use; the die case (10) is provided with a polygonal encapsulation and extrusion opening (1001); multiple reserved guide holes (1101) are formed in the die core (11); the circumferential inner wall of each reserved guide hole (1101) is provided with a groove (1102) for guiding the identification tag (5).
10. The manufacturing method of the encapsulated duct cable with identification tags according to claim 6, wherein a tension device (12) is arranged between the identification tag winding device and the encapsulation and extrusion device; the tension device (12) comprises a base (1201); two guide pulleys (1202) and a support (1203) are arranged on the base (1201); a lift arm (1204) is articulated with the support (1203); one end of the lift arm (1204) is connected with the support (1203) through a tension spring (1206), and the other end of the lift arm (1204) is provided with a tension pulley (1205); the tension pulley (1205) is located between the two guide pulleys (1202).
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0026] The present invention is further described below with reference to the accompanying drawings.
[0027]
[0028]
[0029]
[0030]
[0031]
[0032]
[0033]
[0034]
[0035]
[0036]
DESCRIPTION OF REFERENCE SIGNS
[0037] 1—encapsulation layer, 2—protective tube, 3—oil-liquid tube, 4—cable, 401—jacket, 402—insulation layer, 403—core, 5—identification tag, 6—hot air blower, 7—preheating tube, 8—plug, 9—tube through hole, 10—die case, 1001—encapsulation and extrusion opening, 11—die core, 1101—reserved guide hole, 1102—groove, 12—tension device, 1201—base, 1202—guide pulley, 1203—support, 1204—lift arm and 1205—tension pulley.
DESCRIPTION OF THE EMBODIMENTS
[0038] To make persons skilled in the art better understand the technical solutions of the present invention, the following further describes the present invention in detail with reference to the accompanying drawings and specific embodiments.
Embodiment 1
[0039] As shown in
[0040] To conveniently identify each cable protective tube 2 and each oil-liquid tube 3, multiple identification tags 5 are arranged on one side of the cable protective tube 2 and one side of the oil-liquid tube 3. Each identification tag 5 is in one-to-one correspondence with each cable protective tube 2 or each oil-liquid tube 3. Each identification tag 5 has its unique color identifier. The identification tag 5 is a rope or a narrow band. In the embodiment, the identification tag 5 is the narrow band.
[0041] The identification tag 5 can also be made from polyaromatic aramid synthetic fibers, Kevlar or a metal wire. By pulling the identification tag 5 outwards, the identification tag 5 cuts off the encapsulation layer 1 covering the cable protective tube 2 or the oil-liquid tube 3 to expose the cable protective tube 2 or the oil-liquid tube 3; then, the encapsulation layer or the oil-liquid tube can be connected with the device in the mine or on the ground.
[0042] In the embodiment, the encapsulation layer 1 may be made from thermoplastic materials such as thermoplastic vulcanizate (TPV), polypropylene (PP), fluorinated ethylene propylene (FEP) and polyvinylidene fluoride (PVDF). The cable protective tube 2 is made of an 825 steel tube. The oil-liquid tube 3 is made of a 2507 steel tube.
[0043] The cable 4 is used for transmitting signals after connected with an underground instrument. The cable 4 comprises a jacket 401, an insulation layer 402 and a core 403 which are sequentially arranged from exterior to interior. In the embodiment, the jacket 401 is made from the polypropylene (PP). Further, the jacket 402 is made from the fluorinated ethylene propylene (FEP) copolymer. The jacket 401 can protect its coated object and has the functions of insulation, flame retardation, corrosion resistance, fixation and the like. The cable 4 is manufactured by a cable plastic extruder and belongs to the conventional manner, which can be implemented by those skilled in the art.
[0044] As shown in
[0045] Step 1: Machining the cable protective tube and paving the cable: placing a steel coil raw material for producing the cable protective tube 2 on a steel band winding device; placing a wound cable 4 on a cable winding device; guiding the start end of the steel coil raw material to sequentially pass through a steel tube initial forming device, the cable winding device, a steel tube laser welding device, a nondestructive testing device, a steel tube drawing device and a traction device to produce the cable protective tube 2 sleeving the cable 4; winding the cable protective tube 2 by a cable protective tube winding device for later use.
[0046] The steel band is made in a U shape by the steel tube initial forming device. The cable 4 is placed into the cable protective tube 2 through an U-shaped opening. In the placing process, the cable needs to pass through a guide pulley. The guide pulley presses the cable 4 to approach the bottom surface of the cable protective tube 2 so as to prevent the cable 4 from being damaged by high temperature of laser welding. It should be noted that the steel band winding device, the cable winding device and the duct cable winding device are used for placing the raw materials, the semi-finished products and the finished products, and also used for paying off or taking up the materials. The laser welding device is used for welding an abutting slot of the cable protective tube 2. The nondestructive testing device conducts the nondestructive test on the welded cable protective tube 2 by using eddies. The drawing device draws the cable protective tube 2 to the desired size by using a preset specification of die. The drawing force is provided by a drawing gear device. The traction device provides the traction force for movement of the cable protective tube 2.
[0047] After the cable protective tube 2 is initially formed, its start end passes through the steel tube drawing device such that its tube diameter is changed. At this time, the steel tube drawing device stops, the start end of the cable 4 is placed in the initially formed cable protective tube 2. Then, the cable 4 is manually conveyed forwards till the start end of the cable 4 props against a shrunk position of the cable protective tube 2. The shrunk position of the cable protective tube 2 clamps the cable 4. At this time, the steel tube drawing device starts. The cable 4 follows the cable protective tube 2 to be drawn to move forwards.
[0048] Step 2: Machining the oil-liquid tube: placing a steel coil raw material for producing the oil-liquid tube on the steel band winding device; guiding the start end of the steel coil raw material to sequentially pass through a steel tube forming device, the steel tube laser welding device, an outer bur removing device, the steel tube drawing device, an annealing furnace and the nondestructive testing device to produce the oil-liquid tube 3;
[0049] winding the oil-liquid tube 3 by an oil-liquid tube winding device for later use.
[0050] Step 3: Machining the encapsulation layer: placing the cable protective tube 2 and the oil-liquid tube 3, which need to be encapsulated, on a relative winding device; guiding the start ends of the cable protective tube 2 and the oil-liquid tube 3 to sequentially pass through a steel tube straightening device, a steel tube preheating device, an identification tag winding device, an encapsulation and extrusion device, a cooling device and a traction device to form the encapsulation layer 1; winding the encapsulated duct cable by the winding device.
[0051] The cable protective tube 2 and the oil-liquid tube 3 only needs to pass through one steel tube preheating device. As shown in
[0052] As shown in
[0053] As shown in
[0054] To further supplement and optimize the above manufacturing method, the steel coil raw materials for producing the cable protective tube 2 and the oil-liquid tube 3 are degreased by utilizing alkaline hot water to remove impurities on the surface of the steel band.
[0055] It should be noted that the identification tag winding device is used for releasing the identification tag 5 along with the production line. The steel tube straightening device machines the wound duct cable to be a horizontal straight line through upper and lower pulleys. The encapsulation and extrusion device heats the PVDF grains at a corresponding temperature till the raw material is molten to be sol so as to have high plasticity. The cable protective tube 2 and the oil-liquid tube 3 pass through the extrusion device to form the encapsulation layer 1. After the cable protective tube 2 and the oil-liquid tube 3 are encapsulated and extruded, they enter a cold rinse bank to be cooled, solidified and molded. In the embodiment, the cold rinse bank is a cooling device.
Embodiment 2
[0056] As shown in
[0057] In its manufacturing method, the die case 10 is provided with a circular arc-shaped encapsulation and extrusion opening 1001. Multiple reserved guide holes 1101 on the die core 11 are also arranged in the shape of the circular arc. The other structures and manufacturing steps are totally the same as these in Embodiment 1, which are not described herein.
[0058] The above embodiments merely describe the preferred embodiments of the present invention and are not intended to limit the scope of the present invention. Various changes and improvements made to the technical solution of the present invention by those of ordinary skill in the art without departing from the design spirit of the present invention shall fall within the protective scope of the appended claims of the present invention.