Device for Emptying a Wireline Operated Wellbore Debris Clean Out Tool and a Method for Using the Device
20220010641 · 2022-01-13
Inventors
Cpc classification
E21B27/00
FIXED CONSTRUCTIONS
E21B37/00
FIXED CONSTRUCTIONS
International classification
E21B27/00
FIXED CONSTRUCTIONS
Abstract
A circulation unit for connecting to a lubricator suitable for housing a wireline operated tool string for collecting debris within a petroleum well is described. The circulation unit comprises a house with an upper lubricator connection and at least one lower internal seal member adapted to seal against an outer surface of the tool string. The circulation unit has an outlet above the seal member, the outlet being connected to a reservoir. The circulation unit has a lower lubricator connection. The house, upper lubricator connection and lower lubricator connection form a through passage for the tool string. The upper lubrication connection and lower lubrication connection are adapted for connection to a pressurized lubricator. The tool string includes a wellbore cleanout tool with filling means. The wellbore cleanout tool comprises an outlet for unloading collected debris in a lubricator assembly comprising the lubricator and the circulation unit. The method for unloading the filled wellbore cleanout tool in the circulation unit is also described.
Claims
1. A circulation unit for connecting to a lubricator, said lubricator is suitable for housing a wireline operated tool string for collecting debris within a petroleum well, said circulation unit comprises: a house provided with an upper lubricator connection and with at least one lower internal seal member, said at least one lower internal seal member is adapted to seal against an outer surface of the tool string, and the circulation unit is provided with an outlet above the at least one lower internal seal member, said outlet being connected to a reservoir, the circulation unit provided with a lower lubricator connection; the house, the upper lubricator connection and the lower lubricator connection form a through passage for the tool string; and the upper lubrication connection and the lower lubrication connection are adapted for connection to a pressurized lubricator.
2. The circulation unit according to claim 1, wherein the at least one lower internal seal member seals against the tool string in an active position.
3. The circulation unit according to claim 1, wherein the circulation unit comprises a second upper seal member above the outlet.
4. The circulation unit according to claim 1, wherein the circulation unit comprises an inlet above the at least one internal lower seal member.
5. The circulation unit according to claim 4, wherein the inlet (20) is positioned below the second upper seal member.
6. The circulation unit according to claim 1, wherein the circulation unit comprises an opening means for displacing a displaceable sliding port on the tool string.
7. The circulation unit according to claim 1, wherein the lubricator and the circulation unit form a lubricator assembly.
8. The circulation unit according to claim 7, wherein the lubricator assembly is provided with a filter cleaning unit for cleaning a filter in the tool string.
9. The circulation unit according to claim 8, wherein the filter cleaning unit is positioned below the circulation unit.
10. The circulation unit according to claim 1, wherein the tool string comprises a wellbore cleanout tool forming a leading end portion and an opposite outlet end portion, and provided with filling means at an inlet at the leading end portion, wherein the outlet end portion comprises an outlet mandrel at an outlet for unloading collected debris, said outlet mandrel comprises a gate portion with through holes, and the tool string further comprises a sliding port provided with a filter adapted to cover the gate portion and slidable to uncover the gate portion, and the sliding port is adapted to be displaced within the lubricator.
11. A method for unloading a filled wellbore cleanout tool forming a leading end portion and an opposite outlet end portion, and being part of a tool string, the method comprising: positioning the tool string within a lubricator assembly (16) comprising a lubricator and a circulation unit; sealing a lower seal member within the circulation unit against an outer surface of the tool string; the wellbore cleanout tool is being provided with an outlet forming a gate portion, and positioning the gate portion within the circulation unit above the lower seal member; uploading collected debris in the wellbore cleanout tool in the circulation unit through holes positioned in the gate portion, and transporting unloaded debris out of the circulation unit through an outlet positioned above the lower seal member; and filling fresh liquid into the wellbore cleanout tool from the lubricator below the circulation unit through an inlet at the leading end portion.
12. The method according to claim 11, wherein the circulation unit being provided with an opening means, and the opening means displacing a sliding port to uncover the through holes in the gate portion.
13. The method according to claim 11, wherein the lubricator assembly being provided with a filter cleaning unit, and cleaning a filter in the wellbore cleanout tool's outlet by displacing the tool string until the outlet is positioned within the filter cleaning unit.
14. The method according to claim 13, wherein the filter is positioned on a sliding port.
15. The method according to claim 13, wherein the filter is positioned on a wall of the wellbore cleanout tool below a sliding port.
Description
[0044] In the following are described examples of preferred embodiments illustrated in the accompanying drawings, wherein:
[0045]
[0046]
[0047]
[0048]
[0049]
[0050]
[0051]
[0052]
[0053]
[0054]
[0055]
[0056]
[0057] In the drawings, the reference numeral 100 indicates a known arrangement for a pressure-controlled wireline intervention in a petroleum well (not shown).
[0058] As is common on many wireline operations on offshore installations, the riser 130 extends above a deck 101 through a hole 102. Depending on local conditions the deck 101 may be e.g. a hatch deck, a skid deck or an intervention deck. The pressure control device 180 is adapted to the type of cable 190. E.g. if the cable 190 is a slick line, the pressure control device 180 is a stuffing box system, if the cable 190 is a braided wire line cable, the pressure control device 180 is a grease injection head (GIH), as known to the skilled person.
[0059] The lubricator 160 forms a sluice for the tool string 200. The pressure control device 180 forms a tight pressure barrier at the top, and the quick test sub 150 may form a tight pressure barrier at the bottom of the lubricator 160. As per prior art way of conducting a wireline based wellbore cleanout operation, each time the tool string 200 is to be removed from the lubricator 160 after a run into the well, the cut valve/work valve 120 is closed, and the manifold 155 or the manifold 135 is opened to reduce the pressure, and the lubricator 160 is drained for fluid through the manifold 155 or the manifold 135. In some cases, the lubricator 160 is additionally flushed with nitrogen to remove all residuals and any hydrocarbon gases. Thereafter the lubricator 160 is opened, usually in the quick test sub 150. Thereafter the lubricator 160 is lifted off the quick test sub 150, whereupon the tool string 200 is laid down on deck using methodology as would be known to a person skilled in the art. For operations involving a known wellbore cleanout tool, when the tool is laid down, debris unloading is performed, together with any between-run maintenance, prior to hoisting it into the lubricator 160 again for another run in the well. This is a time-consuming procedure, and the operators may also be exposed to associated risks such as falling objects, exposure to hydrocarbons and other wellbore material such as low radioactivity material.
[0060] An arrangement 1 for a pressure-controlled wireline intervention in a petroleum well provided with a circulation unit 2 is shown in
[0061] According to one embodiment of the invention, the outlet 30 is connected to a reservoir such as a debris separator 3 by a tube system 31. The tube system 31 is provided with valves 33. The tube system 31 guides hydrocarbons, water, sand and other unloaded debris from a cleanout tool 230 from the lubricator 160 to the debris separator 3. The tube system 31 is robust and suited for the purpose. The debris separator 3 may be a test separator permanently installed on the facility or a temporary installed test separator. A temporary installed debris separator 3 may be connected to a permanently installed test separator further downstream. For this embodiment, the intention being to perform the unloading of the wellbore cleanout tool 230 without bleeding off the lubricator 160 pressure, or at least, with the lubricator partially pressurized, which is beneficial from a time consumption point of view. For this embodiment, it is seen as an advantage to provide the riser 130, lubricator 160, tube system 31 and debris separator 3 with pressure gauges 35. The pressure gauges 35 may be digital gauges. The digital gauges could also be sensors for detecting; temperature, density, particle, volume and flow. In this embodiment, the well pressure is the driving force for emptying the cleanout tool 230. Well fluid enters an inlet 233 at a leading end portion 231 of the wellbore cleanout tool 230 and drives the collected debris out of the wellbore cleanout tool 230 and lubricator 160 via the outlet 30 and into the separator 3.
[0062] The circulation unit's 2 house 29 is further provided with an inlet 20 for an injection of a cleaning fluid. The cleaning fluid may be a wash medium, such as a well fluid, monoethyl glycol (MEG), water, nitrogen gas, etc. For the embodiment shown in
[0063] In another embodiment of the invention, shown in
[0064] The tool string 200 is shown in
[0065] The wellbore cleanout tool 230 working principle may be an auger-based collecting system, a suction tool collecting system with or without a bit in the end, or a suction, jetting and rotating collecting system. Alternatively, the collecting system mechanism may be a mechanical collecting device (not shown) used on a mechanical tool string where gravitation forces are used to displace the collecting device into the debris and thereby filling the collecting device.
[0066]
[0067] The circulation unit 2 is shown in a first embodiment in
[0068] The circulation unit 2 is shown in a second embodiment in
[0069] The wellbore cleanout tool 230 comprises an outlet mandrel 43 at the outlet 4 (see
[0070] The sliding port 41 may be provided with a resilient biasing means (not shown) that bias the sliding port 41 axially along the outlet mandrel 43 to cover the gate portion 45 when the wellbore cleanout tool 230 is run and operated in the well. The resilient biasing means may be a coil spring. After hoisting the wellbore cleanout tool 230 out after an ended cleanout run in the well, upon entering the circulation unit 2, an opening means within the circulation unit 2 displaces the sliding port 41 axially towards the front tool 240 when the outlet 4 is displaced upwardly within the circulation unit 2. The opening means may be the constriction 25 which is adapted to open the sliding port 41. As per this embodiment, upon hoisting the wellbore cleanout tool 230 into the circulation unit 2, the biasing means is further tensioned by the axial displacement of the sliding port 41 towards the front tool 240. After unloading, the wellbore cleanout tool 230 is lowered downwardly out of the circulation unit 2, whereupon the biasing means forces the sliding port 41 axially along the outlet mandrel 43 towards the cable head 210, covering the through holes 49 in the gate portion 45 again. In an alternative embodiment, the circulation unit 2 is provided with a locking profile (not shown) which engage with locking dogs onto the sliding port 41 to facilitate shifting this open, as would be appreciated by a person skilled in the art. In yet another embodiment, the circulating unit 2 is provided with orientation means that engage with corresponding orientation means in the outlet 4, that orient and align the holes in the gate portion 45 with respect to the holes in the outlet 30 of the circulation unit 2.
[0071] In an alternative embodiment (not shown) a portion of the outlet mandrel 43 is provided with a filter in the mandrel wall adjacent the gate portion 45. The filter is exposed when the sliding port 41 is axially displaced to cover the through holes 49 of the gate portion 45.
[0072] In a further alternative embodiment, the tool string 200 is not provided with a filter at the outlet 4. This may be the case for a wellbore cleanout tool 230 that uses flow to create a suction and/or jetting effect to clean the well, and where there is a debris retention filter in the internals of the tool. In this embodiment the sliding port 41 covers the gate portion 45 when the wellbore cleanout tool 230 collects debris downhole. For all embodiments, the gate portion 45 of the wellbore cleanout tool 230 is in direct contact and/or communication with the wellbore cleanout tool's 230 collecting chambers housing the collected debris.
[0073] During collection of debris within the well, the sliding port 41 covers the gate portion 45 as shown in
[0074] Operation of the outlet 4 is shown in
[0075]
[0076] In an alternative embodiment, the lubricator 160 is further provided with a filter cleaning unit 5 as shown in
[0077] In a further alternative embodiment, the lubricator 160 is further provided with an inspection unit (not shown). The inspection unit may be an optical camera, an infrared camera, an X-Ray scanner, an ultrasound scanner, a magnetic resonance scanner or an inspection window. This inspection unit may be a supplement to tool string instrumentation to check and verify the debris collecting tool string before an additional roundtrip into the well.
[0078] The tool string 200 is shown in an alternative embodiment in
[0079] The wellbore cleanout tool 230 may comprise transporting means (not shown) such as a pump or an auger to transport debris into the wellbore cleanout tool's 230 collecting chamber. In one embodiment, the front tool 240 assists in loosening consolidated debris within the well. Typically, a motor (not shown) within the motor housing 225 is supplied with electrical energy through the cable 190, whereupon it powers relevant tool modules such as the front tool 240, a pump or an auger. In one embodiment, the sliding port 41 serves an active purpose in the downhole cleanout operation by retaining the debris within the wellbore cleanout tool 230. In alternative embodiments, debris retention means such as filters may be located elsewhere in the wellbore cleanout tool 230. Here, the sliding port 41 mainly serves the purpose of establishing communication between the wellbore cleanout tool's 230 collecting chamber and the circulation unit 2 during the unloading activity on surface. When the wellbore cleanout tool 230 is full, or all debris has been collected from the well, the tool string 200 is hoisted out of the well and returned to the lubricator 160.
[0080] In one embodiment, the wellbore cleanout tool 230 is a mechanical bailer or pump bailer, with a top portion of the bailer adapted as per the invention herein, such as with a spring forced sliding sleeve that uncovers a gate portion 45 when the bailer abuts the constriction in the circulation unit 2, enabling the unloading of debris from the bailer via the circulation unit 2 as per methods described herein.
[0081] In one embodiment the circulation unit 2 may be provided with a tool catcher (not shown) that grips the tool string 200 and keep the tool string fixed in a correct position. In other embodiments the tool catcher 170 grips the tool string 200.
[0082] In one embodiment of the invention, the valves which isolates the lubricator 160 from the well may be closed after the tool string 200 is fixated. In another embodiment they remain open. This may depend on regulatory guidelines, relevant operational constraints, conditions at the well site, and on what type of debris receiving and debris management system that is being used to unload debris on the surface e.g. debris separator 3 or non-pressurized tank 300.
[0083] For any of the above embodiments, it is considered advantageous that the wellbore cleanout tool's 230 surroundings inside the pressure control arrangement 1 being filled with liquid and not gas. If gas is present, it would be preferred to close the valves and fill the surroundings between the tool string 200 and the lubricator 160 with a suitable liquid, such as monoethyl glycol (MEG).
[0084] After fixation of the tool string 200, the lower seal 23 is activated. If the circulation unit 2 is provided with an upper seal 22, the upper seal 22 is activated. The portion of an annulus below the lower seal 23 is then isolated from the annulus above the lower seal 23. If an upper seal 22 is present, the annulus above the upper seal 22 is then isolated from the annulus below the upper seal 22. An annulus portion forms between the activated lower seal 23 and the activated upper seal 22.
[0085] The inlet 20 is positioned in the annulus portion above the lower seal 23, and below the upper seal 22, if the upper seal 22 is present. The outlet 30 is positioned in the annulus portion above the lower seal 23, and below the upper seal 22, if the upper seal 22 is present. The gate portion 45 is positioned in the annulus portion above the lower seal 23, and below the upper seal 22, if the upper seal 22 is present, as well.
[0086] For the embodiment of the invention using a debris separator 3 capable of operating at elevated pressure conditions, this is connected to the outlet 30. A wash medium (not shown), such as well fluid, MEG, water or nitrogen gas flows or is being pumped through the injection hose 21 and the inlet 20 and enters the annulus portion within the circulation unit 2. This flow may clean the gate portion 45. The wellbore cleanout tool 230 is now ready for unloading.
[0087] Unloading may be performed by several methods. In one embodiment, where the pressure control arrangement 1 is kept at an elevated pressure during unloading, the pressure within the debris separator 3 may be lowered to create a pressure difference between the debris separator 3 and the pressure control arrangement 1. Debris is unloaded by flow from the pressure control arrangement 1 and/or the well, through the wellbore cleanout tool 230, out the gate portion 45 and the outlet 30 to the debris separator 3, the flow being caused by said pressure difference.
[0088] In another embodiment, a flow of cleansing fluid may be provided to the leading end portion 231 by the pump 6 pumping cleansing fluid into the inlet 60 on the pressure control arrangement 1 that is located below the circulation unit 2, such as the manifold 135. The resulting flow causing the unloading of debris from the wellbore cleanout tool 230 to take place out the gate portion 45 and the outlet 30 to the debris separator 3 or a non-pressurized disposal tank 300.
[0089] In another embodiment, the flow of wash medium through the circulation unit 2 may create a similar suction effect within the wellbore cleanout tool 230.
[0090] In a preferred embodiment of the invention, in order to unload the wellbore cleanout tool 230, the means for filling and/or operating the wellbore cleanout tool 230 such as an auger, a pump or other working mechanism of the wellbore cleanout tool 230, being activated at the same time as pumping fluids by the pump 6 into the wellbore cleanout tool 230 via the leading end portion 231, out the gate portion 45 and the outlet 30 to the debris separator 3 or a non-pressurized disposal tank 300 as described above.
[0091] In one embodiment, the main means for unloading debris upwards in the wellbore cleanout tool 230, out through the gate portion 45 and the outlet 30 being the same means as are used for collecting debris and filling the wellbore cleanout tool 230 downhole, such as an auger, a pump or other working mechanism of the wellbore cleanout tool 230, or a combination of such means.
[0092] According to a preferred embodiment, the pressure difference between the wellbore cleanout tool's 230 inlet at the leading end portion 231, and the circulation unit 2 is monitored to control the unloading operation. Cleaning fluid from the manifold 63 enters the wellbore cleanout tool's 230 inlet at the leading end portion 231 to drive out and in addition volumetric replace any unloaded debris. In one embodiment, volumetric displacement monitoring means are used to verify that the wellbore cleanout tool 230 collected debris downhole, and in addition for monitoring and verifying the unloading operation in general.
[0093] For the embodiment where the collected debris of the wellbore cleanout tool 230 is unloaded into a dedicated debris separator 3, the cleaning fluid may be residual fluid from the lubricator 160 and/or the well. For this embodiment, the cut valve/work valve 120 may be kept open whilst unloading the wellbore cleanout tool 230, whereupon unloading of the wellbore cleanout tool 230 takes place by well fluids flushing through the wellbore cleanout tool 230, the circulation unit 2, via the tube system 31 and into the debris separator 3. The flow rate may be controlled by the debris separator's 3 outlet valves, and the unloading continues until all collected debris from the wellbore cleanout tool 230 has been unloaded to the debris separator 3. The debris separator 3 may further be provided with a measuring glass so that the volume of collected debris is monitored. By this procedure, unloading of the wellbore cleanout tool 230 is performed in a fully closed system without any hazardous exposure of chemicals to the crew.
[0094] According to a preferred embodiment, for cases where the wellbore cleanout tool 230 is unloaded to a debris separator 3 or a non-pressurized disposal tank 300, cleaning fluid is pumped into the lubricator 160 below the lower seal 23, e.g. through the manifold 135 on the riser 130. The debris separator 3 or disposal tank 300 may be provided with means for monitoring weight to assess the amount of collected debris.
[0095] When the unloading is completed, the inlet 20 and the outlet 30 are closed. In one embodiment, the wellbore cleanout tool 230 is provided with a PCP pump (Progressive Cavity Pump, also known as a Moineau pump after the inventor) or other suitable pump type as a means for filling the wellbore cleanout tool 230. Here, upon unloading the wellbore cleanout tool 230, functionality of the PCP pump (verification of functionality prior to a subsequent run) is checked by running the pump against the closed volume inside the closed circulation unit 2. If pressure is rising and maintained at some elevated value, this being an indication that the tool's pump is working properly.
[0096] If the wellbore cleanout tool 230 is provided with a check valve (not shown) at the wellbore cleanout tool's 230 lower end portion, the check valve may be tested by closing the outlet 30 and by pumping a fluid through the inlet 20. Pressure will build up inside the wellbore cleanout tool 230 if the check valve is intact and working properly.
[0097] According to a preferred embodiment, when the tool string 200 is disconnected from the tool catcher inside the circulation unit 2 or the tool catcher 170, the inlet 20 and the outlet 30 are closed automatically as a safety measure. In one embodiment, this is verified by a sensor. In one embodiment, it is not possible to disconnect the tool string 200 from the tool catcher before the inlet 20 and the outlet 30 are completely closed.
[0098] The seals 22 and 23 are deactivated prior to disconnecting the tool string 200.
[0099] Before the next round-trip in the well, a filter test may be performed by flushing fluid through the wellbore cleanout tool 230 and through the filter whilst measuring delta pressure across it. Dependent on the arrangement, this may be performed in several different ways. In one embodiment, where the filter 41 is embedded in sliding port 47, prior to testing the filter, the through holes 49 in the gate portion 45 are closed by sliding the sliding port 47 to a closed position. This may be achieved by slightly lowering the tool string 200 within the circulation unit 2. If the tool string 200 is provided with a pump, the pump may be used to create fluid circulation to verify the filter with respect to plugging and restriction. If the tool string 200 is not provided with a pump, the lower seal 23 is activated to isolate the outside of the lower portion of the tool string 200 from the outside of the upper portion. Then, fluid is pumped into the lubricator 160 through the manifold 135 via the pump 6 and led into and through the wellbore cleanout tool 230 and the filter whilst monitoring delta pressure, to verify that the filter has not been plugged or damaged.
[0100] When performing flow tests through the wellbore cleanout tool 230 and filter 47 after unloading, fluids should pass unrestricted through the wellbore cleanout tool 230 and through the filter 47. If any resistance monitored, e.g. pressure drop of significance is observed, this indicates that the filter 47 is blocked or partly blocked. If so, according to one embodiment of the invention, the tool string 200 is lowered such that the filter 47 is positioned within the filter cleaning unit 5. The filter cleaning unit 5 is activated and the nozzles 53 spray a pressurized cleaning fluid over the filter 47. The wellbore cleanout tool 230 may be hoisted and lowered several times past active nozzles 53 to clean the filter 47 properly. In one embodiment, where the filter is located in the wall of the mandrel 43 below the sliding port 41, e.g. closer to the front tool 240, the filter cleaning procedure is the same.
[0101] In one embodiment, other equipment in the tool string 200, such as electrical motor(s) assemblies, wireline, tractor and anchoring means (not shown) may also be tested and/or prepared for a subsequent run with the tool string 200 hanging within the intact (not disconnected) lubricator 160. For example, lubricator 160 modules could be tailored for filling relevant tools with hydraulic oil between runs. After successful testing the tool string 200 is ready for another decent into the well.
[0102] Several modifications are possible within the frame of the present invention. The outlet 4 may be positioned closer to the inlet portion of the wellbore cleanout tool 230. There may be more than one outlet 4. The filter cleaning unit may be positioned within the circulation unit 2. This would be appreciated by a person skilled in the art.
[0103] For all embodiments, the invention provides the advantage that unloading of the wellbore cleanout tool 230 is performed within the lubricator 160, avoiding disconnecting and/or remove the lubricator 160 for unloading the wellbore cleanout tool 230.
[0104] For the embodiment where the wellbore cleanout tool 230 is unloaded into a pressurized debris separator 3, no pressure safety barrier is broken, and pressure testing before the next decent is not necessary. The process is a closed process and the field crew is not exposed to hazardous chemicals.
[0105] For all embodiments, the associated wireline operation for removing debris from a petroleum well becomes more efficient than previous known art and techniques conveyed on wireline. Experience indicate that prior art technology for removing debris from a well on wireline could be conducted in a pace of approximately three runs (trips in the well) per 24 hours as a high estimate. The inventors estimate that applying a design and method according to the present invention, enables six runs and even more per 24 hours, in particular if combining with novel types of wireline that permit a substantially higher running speed than wireline technology of current art.
[0106] It should be noted that the above-mentioned embodiments illustrate rather than limit the invention, and that those skilled in the art will be able to design many alternative embodiments without departing from the scope of the appended claims. In the claims, any reference signs placed between parentheses shall not be construed as limiting the claim. Use of the verb “comprise” and its conjugations does not exclude the presence of elements or steps other than those stated in a claim. The article “a” or “an” preceding an element does not exclude the presence of a plurality of such elements.
[0107] The mere fact that certain measures are recited in mutually different dependent claims does not indicate that a combination of these measures cannot be used to advantage.