Method and system for servicing a well
11162337 · 2021-11-02
Assignee
Inventors
Cpc classification
E21B43/126
FIXED CONSTRUCTIONS
E21B37/00
FIXED CONSTRUCTIONS
E21B17/20
FIXED CONSTRUCTIONS
E21B17/1007
FIXED CONSTRUCTIONS
International classification
E21B43/12
FIXED CONSTRUCTIONS
B05D7/22
PERFORMING OPERATIONS; TRANSPORTING
E21B17/20
FIXED CONSTRUCTIONS
Abstract
A method and system for servicing a well. Servicing a well often includes running a service string into a production string, which may include a rod string. A service portion is provided in the production string during completion. The service portion is located at or uphole of a large rod string feature. The service portion has a greater inside diameter than production tubing and other standard production string components. The service portion provides sufficient clearance for the service string alongside the large feature. The large feature may be, for example, a PCP stator, a centralizer, or a rod collar. The large feature may be pulled uphole into the service portion prior to running in the service string, allowing servicing downhole of the large feature without pulling the entire rod string. The service portion may also mitigate rod wear in deviated or other portions of the well.
Claims
1. A method of completing a well comprising: providing a production string extending between a downhole end and an uphole end; and providing an increased inside diameter (“ID”) portion of the production string at a selected location in the production string for mitigating rod wear on the production string at the selected location caused by a rod string when the rod string is located within the production string, wherein an ID of the increased ID portion is greater than an ID of the production string along at least half of the length of the production string other than at the increased ID portion, thereby providing for an increased clearance between an ID surface of the production string and an outside diameter (“OD”) surface of the rod string at the increased ID portion relative to an ID surface of the production string and an OD surface of the rod string at the at least half of the total length of the production string.
2. The method of claim 1 wherein the selected location is in a deviated portion of the wellbore.
3. The method of claim 1 wherein the selected location is in a heel of the wellbore.
4. The method of claim 1 wherein the increased ID portion of the production string has a hardness of about 80 Rockwell C.
5. The method of claim 1 wherein the increased ID portion of the production string is hardened by boranizing or applying a coating to the increased ID portion.
6. The method of claim 1 wherein the production string comprises a low wear insert along at least a portion of the increased ID portion of the production string.
7. The method of claim 1 wherein the production string other than the increased ID portion comprises joints of production tubing and collars connecting the joints.
8. The method of claim 7 wherein: the production tubing has an OD of about 3.5″; the production tubing has an ID of about 3.0″; the collars have an OD of about 4.5″; the increased ID portion has an ID of about 3.5″; and the increased ID portion has an OD of about 4.5″.
9. The method of claim 7 wherein: the production tubing has an OD of about 4.5″; the production tubing has an ID of about 4.0″; the collars have an OD of about 5.5″; the increased ID portion has an ID of about 4.5″; and the increased ID portion has an OD of about 5.5″.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1) Embodiments of the present disclosure will now be described, by way of example only, with reference to the attached figures, in which features sharing reference numerals with a common final two digits of a reference numeral correspond to similar features across multiple figures (e.g. the service tool 10, 110, 210, 310, 410, 510, 610, 710, 810, 910, 1010, 1110, etc.).
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
(17)
(18)
(19)
(20)
DETAILED DESCRIPTION
(21) Generally, the present disclosure provides methods and systems for servicing a downhole target portion of a production string having a rod string therein using a service string. The methods and systems provided herein facilitate running a service string downhole past a large feature of the rod string, the large feature occupying a sufficiently large portion of the production tubing's cross-sectional area to complicate or prevent passage of the service string past the large feature within the production tubing.
(22) The methods and systems disclosed herein may be applied to servicing a stator of a progressive cavity pump (a “PCP”) using coiled tubing, in which case the target portion of the production string is a PCP stator, the service string is coiled tubing, and the large feature is a PCP rotor pulled from the PCP stator. In typical production tubing, a major diameter of the PCP rotor is sufficiently large to complicate or prevent passage of coiled tubing.
(23) When producing fluids from an underground formation, the PCP may be located at or near the end of a string of production tubing run into the reservoir to provide artificial lift for producing the fluids. Where the fluid is a heavy oil or other viscous hydrocarbon, PCPs may be a common choice for an artificial lift solution. A PCP may be common choice in a reservoir known to include heavy hydrocarbons with a large amount of particulate debris (e.g. sand, etc.). During use in such reservoirs, the PCP may become clogged with debris, or “sanded off”, which may be corrected by servicing. Such servicing may be provided by delivery of fluids to the PCP stator from coiled tubing for cleaning the PCP stator.
(24) The PCP stator may be located at the downhole end of the production string. The helical PCP rotor may be located at the downhole end of the rod string. The rod string is received within the production string. A helical stator cavity is defined within the PCP stator. A helix of the PCP rotor corresponds to a helix of the stator cavity and the rotor is received within the stator cavity. The outside surface of the PCP rotor and the inside surface of the stator cavity are correspondingly shaped to advance a cavity defined between the PCP rotor and the PCP stator uphole when the rotor is rotated relative to the stator.
(25) Pulling the PCP rotor from the PCP stator may be necessary to service the PCP stator. In many such cases, the entire rod string is pulled. Where the PCP is sanded off or otherwise plugged with particulate debris, coiled tubing may be used to deliver fluids to the PCP stator for cleaning, and the entire rod string may be pulled to allow the coiled tubing to be run in to the PCP stator. The entire rod string is pulled where the inside diameter of production tubing does not accommodate both the PCP rotor and the coiled tubing. This is often the case with standard production tubing as the rotor is often the portion of the rod string with the greatest outside diameter. In particular, servicing a PCP stator on a production string prepared from production tubing having an outside diameter of 4.5″ or 3.5″ may require pulling the entire rod string to allow ¾″ coiled tubing to be run in to the PCP stator. Similarly, servicing a PCP stator on a production string prepared from production tubing having an outside diameter of 2.375″ or 2.875″ may require pulling the entire rod string to allow ½″ coiled tubing to be run in to the PCP stator. This is illustrated by the features of standard API interference-fit threaded production tubing shown in Table 1 (with acronyms for outside diameter “OD”, inside diameter “ID”, and major dimension diameter “MD” used in Table 1):
(26) TABLE-US-00001 TABLE 1 Dimensions of API interference-fit threaded tubing, PCP rotors, and coiled tubing Tubing OD Collar OD Tubing ID PCP Rotor MD Coil OD 2.375″ 3.063″ 1.995″ 1.625″ 0.50″ 2.875″ 3.668″ 2.441″ 2.297″ 0.50″ 3.5″ 4.5″ 3″ 2.75″ 0.75″ 4.5″ 5.5″ 3.958″ 3.00 to 3.75″ 0.75″
(27) As shown above, coiled tubing having an outside diameter of 0.75″ will not clear a PCP rotor in 3.5″ API interference fit threaded tubing (4.5″ outside diameter collars). In 4.5″ API interference fit threaded tubing (5.5″ outside diameter collars), coiled tubing with an outside diameter of 0.75″ will have less than 0.25″ of clearance with smaller PCP rotors (e.g. 3.00″, etc.), and will not clear the larger PCP rotors (e.g. 3.75″, etc.). For a given production tubing outside diameter, such as 4.5″, a PCP rotor having a larger major diameter, such as 3.75″, will provide a greater flow rate than a PCP rotor having a smaller major diameter, such as 3.00″.
(28) Methods and systems described herein may facilitate servicing a PCP stator with coiled tubing without pulling the entire rod string before servicing. A service portion is included in the production string uphole of the PCP stator. The service portion has a length sufficient to accommodate the length of the PCP rotor and an inside diameter sufficient to accommodate the major diameter of the PCP rotor and a coiled tubing string. To service the PCP stator with the coiled tubing, the rotor is pulled uphole into the service portion. The coiled tubing may be run in through the service tool with the PCP rotor received within the service portion, facilitating access to the PCP stator by the coiled tubing. The service portion may be defined within a service tool located in the production string.
(29) Servicing a PCP stator with coiled tubing is a particular application of the methods and systems disclosed herein. However, as is implicit by the exemplary nature of such application to a PCP stator using coiled tubing, the methods and systems disclosed herein apply more generally.
(30) The methods and systems disclosed herein facilitate using a service string to service a downhole target portion of a production string having a large feature located on a rod string uphole of the target portion, wherein the tubing making up the production string has an insufficient inside diameter to accommodate both the service string and the large feature. The methods and systems disclosed herein include providing a greater inside diameter along the production string uphole of the large feature, accommodating the large feature and the service string along at least a portion of the production string to allow the service string access to the production string downhole from the large feature without pulling the entire rod string.
(31) The service portion may be provided within a service tool located in the production string uphole of the large feature. The rod string need be pulled only by the distance required to locate the large feature within the greater diameter portion of the production string. The closer the service tool is to the production position of the large feature, the shorter the distance that the rod string would be pulled uphole by to facilitate servicing the production string at the target portion. Where the service tool is proximately or immediately uphole of the production position, the distance that the large feature would be pulled uphole to locate it within the service tool is less than where the service tool is distally uphole of the production position, but may still result in less effort and rig time than pulling the entire rod string.
(32) The methods and systems disclosed herein also have application to providing additional inside diameter in portions of a production string which have a greater risk of rod wear, such as in a heel of a horizontal wellbore or in a deviated portion of a wellbore (horizontal or vertical).
(33) Service Tool
(34)
(35) A service portion 25 of the bore 18 extends along a service length 20 of the service tool 10. The service length 20 may extend along the body 12 and a portion of each connection adapter 30. In the service portion 25 along the service length 20, the bore 18 has a service inside diameter 22. The service length 20 is sufficient to accommodate the entire length of a selected large feature of a rod string (e.g. a PCP rotor, a rod centralizer, a rod collar, etc.) within the bore 18 having the service inside diameter 22. The service inside diameter 22 may be selected with reference to an outside diameter of the large feature. The service inside diameter 22 is sufficient to accommodate the large feature and a service string (e.g. a coiled tubing string, etc.) within the bore 18.
(36) The service tool 10 defines a maximum outside diameter 24 selected with reference to features of a production string with which the service tool 10 is intended to be used. The maximum outside diameter 24 may be the outside diameter of the majority of the body 12 and of the connection adapters 30 as shown in
(37) Along the service portion 25, the body 12 defines a body wall thickness 26 and the connection adapter 30 defines an adapter wall thickness 39. The maximum outside diameter 24, the body wall thickness 26, and the adapter wall thickness 39 may define constraints on maximizing the service inside diameter 22.
(38) Service Tool in Production String Uphole of PCP Stator
(39)
(40) The PCP stator 54 may be located at or proximate the downhole end 53 of the production string 50. Alternatively, multiple PCP stators may be located in series on the production string, with a service tool uphole of each PCP stator (e.g. where a charge PCP is used in addition to a production PCP, where two production PCPs are applied, etc.). In addition, the presence of a rod collar on the rod string 60 may also benefit from locating a short service tool 10 uphole of the rod collars. The rod collars may be an example of the large feature 265 of the rod string 260 in
(41) A rod string 60 is located within the production string 50. The rod string 60 extends between an uphole end 61 and a downhole end 63. A rod 62 (e.g. rod joints connected with each other, a continuous rod, etc.) extends between the uphole end 61 and a PCP rotor 64 at or proximate the downhole end 63. The PCP rotor 64 is located within the helical cavity 56, defining a progressing cavity 58 between the PCP stator 54 and the PCP rotor 64. When the PCP rotor 64 is rotated relative to the PCP stator 54, the progressing cavity 58 advances uphole, providing artificial lift. Where multiple PCP stators are located in series on the production string, corresponding multiple PCP rotors are also located on the production string (not shown). The PCP rotor extends along the rod string 60 for a PCP rotor length 67 and has a major diameter 68 along the PCP rotor length 67.
(42)
(43)
(44)
(45) Some features of a service tool 10 for use with standard API interference fit threaded tubing (having outside diameters of 2.375″, 3.875″, 3.5″, and 4.5″) are shown in Table 2 alongside the PCP rotor MD and Coil OD (with the same acronyms as Table 1):
(46) TABLE-US-00002 TABLE 2 Dimensions of service tool, corresponding tubing, PCP rotors, and coiled tubing Tubing OD Tool OD Tool ID PCP Rotor MD Coil OD 2.375″ 3.25″ 2.75″ 1.625″ 0.50″ 2.875″ 4.0″ 3.25″ 2.297″ 0.50″ 3.5″ 4.5″ 3.5″ 2.75″ 0.75″ 3.5″ 4.5″ 3.826″ 2.75″ 0.75″ 4.5″ 5.5″ 4.5″ 3.00 to 3.75″ 0.75″
(47) As shown above, coiled tubing having an outside diameter of 0.75″ will clear a PCP rotor in a service tool designed for use with 3.5″ outside diameter API interference fit threaded tubing (4.5″ outside diameter collars). In 4.5″ outside diameter API interference fit threaded tubing (5.5″ outside diameter collars), coiled tubing have an outside diameter of 0.75″ will clear a PCP rotor having a major dimension of up to 3.75″. The service portion 25 would have a service portion length 20 at least as long as the PCP rotors. Some PCP rotors may be between about 20 and 30 feet long.
(48) Connections
(49) The bore 18 may be in communication with the production string 50 by connecting the service tool 10 with API interference fit or other standardized production tubing threaded collars or other box ends at the pin-end connection adapters 30. When the service tool 10 is assembled and ready for connection with the production string 50, the body 12 is connected with the pair of connection adapters 30.
(50) The body 12 extends between a first end 14 and a second end 16. A first connection portion 15 of the body 12 is proximate the first end 14 and a second connection portion 17 of the body 12 is proximate the second end 16. The first and second connection portions 15, 17 facilitate connecting the body 12 with the connection adapters 30.
(51) The service tool 10 provides sufficient clearance for the coiled tubing string 70 and the PCP rotor 64 or other large feature by maintaining the service inside diameter 22 along the service length 20, with the service length 20 being at least as great as the PCP rotor length 67 or other large feature length. As a result, the first and second connection portions 15, 17 may be designed to facilitate maximizing the body wall thickness 26 along the connection portions 15, 17 while maintaining the service inside diameter 22. In the service tool 10, each of the first and second connection portions 15, 17 defines a threaded box end for connecting with a corresponding pin end. Box ends on the service tool 10 allow the body wall thickness 26 to be maximized along the first and second connection portions 15, 17 compared with pin ends as the first and second connection portions 15, 17 (not shown).
(52) The first and second connection portions 15, 17 may be threaded with a service threading 28 selected to facilitate maximizing the service inside diameter 22 and the body wall thickness 26 within a constraint on the outside diameter 24. The constraint on the outside diameter 24 may be selected to have the outside diameter 24 match the outside diameter of production tubing collars for the production string with which the service tool 10 will be used. The service threading 28 may be selected to facilitate optimizing for connection strength and body wall thickness 26 to provide a service tool 10 suitable for use with production tubing having a given size of API interference fit threading. The service threading 28 may have greater connection strength and body wall thickness 26, while maintaining the constraints on the service inside diameter 22 and the outside diameter 24, compared with using the given size of API interference fit threading on the first and second connection portions 15, 17.
(53) The service threading 28 may be tapered, such as with an API interference fit thread, and may have an external upset end. However, such service threading 28 may be distinct from and incompatible with API interference fit threading. As shown above in Tables 1 and 2, the service inside diameter 22 may be equal to the outside diameter of production tubing 52 joints with which the service tool 10 is to be used, which would not allow for preparing a box-end API connection with the service inside diameter 22. The service threading 28 may have a pitch of 8 or 10, and may be round, v-thread, Acme, or stub-Acme threading, or any suitable type of threading. Such threading may be used for connections between the service tool 10 and connection adapters 30, allowing communication between the service tool 10 and production tubing 52 with API interference fit thread sizes of between about 2.375″ and about 4.5″.
(54) The connection adapter 30 may be used to connect the service tool 10 with the tubing collar 57, the PCP stator 54, or any suitable box-end tubular, that is threaded other than with the service threading 28. In
(55) The production string connection portion 33 may be threaded with production string threading 31 that matches other threading used in the production string 50 (e.g. API interference fit threading on the production tubing 52, the PCP stator 54, and a tubing collar 57, etc.). The adapter connection portion 35 may be threaded with the service threading 28.
(56) A production end inside diameter 36 may be defined along the production string connection portion 33. The production end inside diameter 36 may be similar to the production string inside diameter 55 found in the production tubing 52 or PCP stator 54 used with the service tool 10. When connecting a pin-pin connection adapter 30 (as shown) with pin-pin production tubing 52, the production string connection portion 33 may be threaded into the tubing collar 57. The production string connection portion 33 may be a box end (not shown) to facilitate connection with a pin end joint of production tubing, rather than with the tubing collar 57.
(57) An adapter end inside diameter 37 may be defined along the adapter connection portion 35. The adapter end inside diameter 37 may be greater than the production side inside diameter 36 and may be sufficient to accommodate the PCP rotor 64 and the coiled tubing string 70. The adapter end inside diameter 37 may be substantially equal to the service inside diameter 22 as shown, extending the service portion 25 along the adapter connection portion 35 and continuous with the rest of the production string 50 from the production string connection portion 33 through to the production string 50. In addition, in cases where the service tool 10 is assembled on a rig, the box-box arrangement of the body 12 may mitigate confusion of the body 12 with a pup joint or with a production tubing joint 52 for a longer body 12. Similarly, the pin-pin arrangement of the connection adapter 30 may mitigate confusion of the connection adapter 30 with a connector 57.
(58) The adapter connection portion 35 may include a box-end connection with the service threading 28 for connecting with a service tool having a pin end (not shown). However, maximizing the body wall thickness 26 along the first and second connection portions 15, 17 while maintaining the service inside diameter 22 and a limit on the outside diameter 24 is facilitated where the first and second connection portions 15, 17 are box end connections rather than pin end connections. The required body wall thickness 26 to maintain the integrity of the service tool 10 and its connections with the production string 50 will depend on the material used to prepare the body 12. Where the body 12 is prepared from L-80 high-alloy steel, integrity and connections with the production string 50 will be maintained at a lower body wall thickness 26 along the first and second connection portions 15, 17 than if the body 12 were prepared with J-55 low-carbon steel.
(59) J-55 low-carbon steel is a lower-cost material than L-80 high-carbon steel, as is often the case with weaker grades of steel compared with stronger grades of steel. As a result, the body 12, which is larger than the connection adapter 30, may be prepared with box end first and second connection portions 15, 17, and the connection adapter 30 may be prepared with pin end first and second adapter connection portions 33, 35. This may facilitate preparing the larger connection tool 10 from a lower-cost material (e.g. J-55 low-carbon steel), and preparing the smaller connection adapter 30 from a higher-cost material (e.g. L-80 high-carbon steel), while maintaining adequate body wall thickness 26 and adapter wall thickness 39. All else being equal, pin ends are thinner than box ends, meaning that for a given set of constraints including service inside diameter 22 and maximum outside diameter 24, less body wall thickness 26 will be available as a design consideration when engineering pin ends compared with box ends. The connection adapter 30 is a smaller component than the body 12 and can be manufactured from a higher cost material more cost effectively than the body 12. Based on at least this, an economic advantage may be provided by using having box ends on the body 12, which is larger than the connection adapter 30, because lower-cost materials may be used to manufacture the body 12 relative to manufacturing the connection adapter 30. Alternatively, where differing materials are not necessary, for the same constraints on service inside diameter 22 and maximum outside diameter 24, a stronger connection may be maintained by maximizing the strength of the body 12 and of the connection adapter 30.
(60) Body Sub-Assemblies
(61)
(62) Each sub-assembly 140 extends between a first sub end 142 and a second sub end 144. A first sub connection portion 143 extends inwardly along the sub-assembly 140 from the first sub end 142. A second sub connection portion 145 extends inwardly along the sub-assembly 140 from the second sub end 144. The first and second sub connection portions 143, 145 each define a box end of the sub-assembly 140 on which the first and second sub connection portions 143, 145 are located.
(63) The sub connector 180 is used to connect individual sub-assemblies 140 into the tool body 112. The bore 118 extends through the sub-assemblies 140, the sub connectors 180, and the connection adapters 130. The sub connector 180 extends between a first connector end 182 and a second connector end 184. A first sub connector portion 183 extends inwardly from the first connector end 182. A second sub connector portion 185 extends inwardly from the second connector end 184. Each of the first and second sub connectors portions 183, 184 defines a pin end for connecting with a corresponding box end, as is present at each sub connection portion 143, 145. Essentially, the sub connector 180 plays a similar role to the connection adapters 130 as between sub-assemblies 140. The sub connectors 180 differ from the connection adapters 130 in that the sub connectors include the service threading 128 on both first and second sub connectors portions 183, 184, and maintain a single sub connector inside diameter 186 throughout of the bore 118 along the sub connector 180. The sub connector inside diameter 186 may be substantially equal to the inside diameter 122.
(64) Location in the Production String
(65) The service tool 10 may also be included at other portions of a production string where additional inside diameter may facilitate servicing, prolong life of the production string, or provide other features. The service portion 25 may be located to provide the service inside diameter 22 along a portion of the wellbore 6 where rod wear on the production string 50 from the rod string 60 is exacerbated, as illustrated by the examples below. The greater clearance between the rod string 60 and the production string 50 provided by the service portion 25 may mitigate damage to production string 50 (at the service tool 10), to the rod string 60, or both, by reducing the pressure between the rod string 60 and the production string 50.
(66)
(67)
(68)
(69)
(70) Other Service Tool Features
(71) The service tool 10 may be prepared from hardened steel to prevent wear from the PCP rotor 64 or other components of the rod string 60 during close clearance with the service string 70. A hardened inside surface of the service tool would also provide advantages in production strings where the service tool 10 is located in a region of the wellbore having an increased tendency for rod wear (e.g. see the production strings 450, 550 in
(72)
(73)
(74)
(75)
(76)
(77)
(78) Examples Only
(79) In the preceding description, for purposes of explanation, numerous details are set forth in order to provide a thorough understanding of the embodiments. However, it will be apparent to one skilled in the art that these specific details are not required.
(80) The above-described embodiments are intended to be examples only. Alterations, modifications and variations can be effected to the particular embodiments by those of skill in the art. The scope of the claims should not be limited by the particular embodiments set forth herein, but should be construed in a manner consistent with the specification as a whole.