MONITORING METHOD AND APPLICATION DEVICE FOR A MULTI-COMPONENT VISCOUS MATERIAL
20220274076 ยท 2022-09-01
Assignee
Inventors
- Tobias ROSENAUER (Eberdingen-Nussdorf, DE)
- Christian KAMMERER (Knittlingen-Hohenklingen, DE)
- Erich Lehner (Bad Friedrichshall, DE)
Cpc classification
B05C11/1013
PERFORMING OPERATIONS; TRANSPORTING
B01F2101/2305
PERFORMING OPERATIONS; TRANSPORTING
B01F25/43141
PERFORMING OPERATIONS; TRANSPORTING
B01F25/431
PERFORMING OPERATIONS; TRANSPORTING
B01F35/71805
PERFORMING OPERATIONS; TRANSPORTING
B05C17/00553
PERFORMING OPERATIONS; TRANSPORTING
B01F2101/36
PERFORMING OPERATIONS; TRANSPORTING
International classification
B05C11/10
PERFORMING OPERATIONS; TRANSPORTING
Abstract
A method monitors a device for applying an at least two-component viscous material to workpieces, including a metering unit having a number of metering valves corresponding with the number of viscous material components, and a static mixer detachably secured to the metering unit for component blending. The static mixer has a material inlet facing the metering unit and a material outlet facing away from the metering unit. Each metering valve has a supply channel sealingly connectable to a valve seat for supplying the respective component to the static mixer. A number of material applications are carried out consecutively, each having an identical predetermined time between start and end of the application. During the applications, between the start and the end, at predetermined times, the pressure in at least one supply channel is measured by a pressure sensor and preferably measured in all supply channels by a respective pressure sensor.
Claims
1. A method for monitoring an apparatus (10) for application of an at least two-component viscous material onto workpieces, which apparatus has a metering unit (12) having a number of metering valves (18) that corresponds to the number of components of the viscous material, as well as a static mixer (14) for blending the components, detachably attached to the metering unit (12), wherein the static mixer (14) has a material inlet (30) that faces the metering unit (12) and a material outlet (32) that faces away from the metering unit (12), and wherein each metering valve (18) has a supply channel (48) that can be closed off at a valve seat (22), for supplying the corresponding component to the static mixer (14), wherein a number of material applications are carried out, one after the other, which applications have an identical, predetermined time progression between an application start (52) and an application end (62), in each instance, wherein during the material applications, the pressure is measured in at least one of the supply channels (48), by means of a pressure sensor (50), at predetermined time points between the application start (52) and the application end (62), and preferably in all the supply channels (48), by means of a pressure sensor (50), in each instance.
2. The method according to claim 1, wherein the measured pressure values of the material applications are compared with stored reference values.
3. The method according to claim 2, wherein the material applications are preceded by at least one test run, during which material is dispensed by the metering unit (12) and applied to a test workpiece, for example, and which run has the same time progression between a test application start and a test application end as the material applications, and during which run the pressure is measured and documented at the same predetermined measurement time points as in the case of the material applications, in at least one of the supply channels (48), between the test application start and the test application end, by means of a pressure sensor (50), and wherein the measured pressure values of the material applications are compared with the corresponding measured pressure values of the test run.
4. The method according to claim 3, wherein during the test run, the pressure is measured and documented in each of the supply channels (48), at multiple predetermined measurement points between the test application start and the test application end, by means of a pressure sensor (50), in each instance, and wherein the pressure is measured in each supply channel (48) at the same predetermined time points as in the test run, between the application start (52) and the application end (62), and for each of the supply channels (48), the measured pressure values of the material applications are compared with the corresponding measured pressure values of the test run.
5. The method according to claim 3, wherein the pressure in the corresponding supply channel (48) is measured at discrete time points, in each instance, during the test run and during the material application.
6. The method according to claim 5, wherein the pressure in the corresponding supply channel (48) is measured at constant time intervals, in each instance, during the test run and during the material application.
7. The method according to claim 1, wherein the pressure in the corresponding supply channel (48) is measured continuously during the test run and/or during the material application.
8. The method according to claim 1, wherein the pressure in the corresponding supply channel (48) is measured ahead of the valve seat (22) in the flow direction of the component in question.
9. The method according to claim 1, wherein a signal device generates a warning signal if one or more measured pressure values of a material application deviate(s) from the corresponding reference value(s) or from the measured pressure value(s) of the test run by more than a predetermined tolerance.
10. The method according to claim 9, wherein the warning signal is varied as a function of the size of the deviation.
11. An apparatus for application of an at least two-component viscous material to workpieces, which apparatus has a metering unit (12) having a number of metering valves (18) that corresponds to the number of components of the viscous material, as well as a static mixer (14) for blending the components, which is detachably affixed to the metering unit (12), wherein the static mixer (14) has a material inlet (30) facing the metering unit (12) and a material outlet (32) facing away from the metering unit (12), and wherein each metering valve (18) has a supply channel (48) for supplying the corresponding component to the static mixer (14), which channel can be closed off at a valve seat (22), wherein a pressure sensor (50) for measuring the pressure of the component in question is arranged in at least one of the supply channels (48).
12. The apparatus according to claim 11, comprising an evaluation device for evaluation of the at least one pressure sensor (50), which device has a data memory for storing the measured values.
13. The apparatus according to claim 12, comprising a signal device for generating warning signals as a function of the measured values evaluated by the evaluation device.
Description
[0011] In the following, the invention will be explained in greater detail using an exemplary embodiment shown schematically in the drawing. This shows:
[0012]
[0013]
[0014] The apparatus 10, shown in part in the drawing (
[0015] The static mixer 14 has a coupling part 26 that engages into the coupling device 20 and is detachably fixed in place on the latter. The static mixer 14 furthermore has a blending pipe 28 that extends from a material inlet 30 at its first end to a material outlet 32 at its second end. The blending pipe is widened at the material inlet 30 and communicates there with the metering valves 18. At the material outlet 32, it is conically narrowed. It has an inner pipe 34 that has the material inlet 30 and the material outlet 32, in which pipe a blending spiral 36 is arranged. Furthermore it has a support pipe 38 composed of metal, which extends over the major portion of the length of the inner pipe 34 and lies against the outer mantle surface of the latter. During application of the two-component adhesive, the two components (basic component and hardener) are each dispensed into the material inlet 30 by means of one of the metering valves 18, in a metered manner, and passed to the blending spiral 36. In the blending spiral 36, the two components blend on their way to the material outlet 32.
[0016] Two supply channels 48 run through the metering unit 12, which channels open into the material inlet 30, in each instance, and can be blocked and released at the valve seats 22, by means of the valve needles 24. Each of the supply channels 48 serves for supplying one of the two components. In each of the supply channels 48 there is a pressure sensor, not shown in detail, on the side of the corresponding valve seat 22 that faces away from the static mixer 14, in other words ahead of the corresponding valve seat 22 in the flow direction of the components, at the location indicated with the reference symbol 50, with which sensor the pressure in the corresponding supply channel 48 can be measured. The measured values of the pressure sensors 50 are evaluated in an evaluation device, not shown in any detail.
[0017] Application of the adhesive takes place with volume control, wherein a predetermined amount or a predetermined volume of each of the two components per time unit is always introduced into the static mixer 14. In
[0018] As long as the properties of the apparatus 10 do not change as the result of wear or clogging with hardened material, for example, and the predetermined volume streams have an identical time progression during every material application, the pressure curves 64, 66 plotted above the time axis 46 are identical, to a great extent, during every material application. The present invention makes use of this fact to monitor the material application. For this purpose, a test application of the material takes place before the first material application, which test serves to generate reference values. During the test application, material is applied to a test workpiece or simply just dispensed by the metering unit 12, for example into a waste container, between a test application start and a test application end, the time interval between which is identical with the interval between the application start 52 and the application end 62, wherein the volume streams of the components are controlled in such a manner that their time progression is identical with the time progression of the volume streams of the subsequent material applications. The pressure curves measured during the test run, which are not shown separately here, but essentially correspond to the pressure curves 64, 66 shown in
[0019] In summary, the following should be stated: The invention relates to, among other things, a method for monitoring an apparatus 10 for application of an at least two-component viscous material onto workpieces, which apparatus has a metering unit 12 having a number of metering valves 18 that corresponds to the number of components of the viscous material, as well as a static mixer 14 for blending the components, detachably attached to the metering unit 12, wherein the static mixer 14 has a material inlet 30 that faces the metering unit 12 and a material outlet 32 that faces away from the metering unit 12, and wherein each metering valve 18 has a supply channel 48 that can be closed off at a valve seat 22, for supplying the corresponding component to the static mixer 14, wherein a number of material applications are carried out, one after the other, which applications have an identical, predetermined time progression between an application start 52 and an application end 62, in each instance, wherein the material applications are preceded by at least one test run, during which material is dispensed by the metering unit 12 and applied to a test workpiece, for example, and which run has the same time progression between a test application start and a test application end as the material applications, and during which test run the pressure is measured and documented in at least one of the supply channels 48, by means of a pressure sensor 50, at multiple predetermined measurement time points between the test application start and the test application end, and wherein the pressure in the same supply channel 48 is measured during the material applications, between the application start 52 and the application end 62, at the same predetermined time points as in the test run, and the measured pressure values of the material applications are compared with the corresponding measured pressure values of the test run.