Full load test system of electrical power converter and the test method thereof
11460516 · 2022-10-04
Assignee
Inventors
Cpc classification
G01R31/31721
PHYSICS
International classification
G01R31/52
PHYSICS
Abstract
A full load test system of an electrical power converter and the test method thereof is disclosed. The full load test method of the electrical power converter comprises the following steps: (a) providing a power converter under test (PCUT); (b) configuring the PCUT in/on a test circuit; (c) serially connecting the PCUT with at least one bidirectional power converter in the test circuit; (d) connecting the test circuit to an alternating current low voltage three-phase power source; and (e) performing a test of the PCUT under full-load condition.
Claims
1. A method of a full load test of a power converter, comprising: (a) providing a power converter under test (PCUT); (b) configuring said PCUT in a test circuit; (c) serially connecting said PCUT with at least one bidirectional power converter in said test circuit; (d) connecting said test circuit to an alternating current (AC) low voltage power source; and (e) performing a full load test of said PCUT; wherein said PCUT in step (c) is a DC/DC converter, said test circuit is connected in parallel with said AC low-voltage power source and said at least one bidirectional power converter includes a first bidirectional power converter and a second bidirectional power converter, wherein said the test circuit includes a test start point located on said AC low voltage power source, a first filter electrically connected with said test start point, said first bidirectional power converter electrically connected with said first filter, said PCUT electrically connected with said first bidirectional power converter, said second bidirectional power converter connected with said PCUT, a second filter electrically connected with said second bidirectional power converter and a test end point located on said AC low voltage power source to electrically connect with said second filter.
2. The method of claim 1, wherein said AC low-voltage power source is an AC three-phase power source with voltage range from 220 volts to 600 volts.
3. The method of claim 1, wherein said first filter and said second filter are LCL filters.
4. A method of a full load test of a power converter, comprising: (a) providing a power converter under test (PCUT); (b) configuring said PCUT in a test circuit; (c) serially connecting said PCUT with at least one bidirectional power converter in said test circuit; (d) connecting said test circuit to an alternating current (AC) low voltage power source; and (e) performing a full load test of said PCUT; wherein said PCUT in step (c) is an AC/DC converter, said test circuit is connected in parallel with said AC low-voltage power source and said at least one bidirectional power converter includes a first bidirectional power converter, wherein said the test circuit includes a test start point located on said AC low voltage power source, a first filter electrically connected with said test start point, said first bidirectional power converter electrically connected with said first filter, said PCUT electrically connected with said first bidirectional power converter and a test end point located on said AC low voltage power source to electrically connect with said PCUT.
5. The method of claim 4, wherein said first filter is an LCL filter.
6. A method of a full load test of a power converter, comprising: (a) providing a power converter under test (PCUT); (b) configuring said PCUT in a test circuit; (c) serially connecting said PCUT with at least one bidirectional power converter in said test circuit; (d) connecting said test circuit to an alternating current (AC) low voltage power source; and (e) performing a full load test of said PCUT; wherein said PCUT in step (c) is an AC/DC converter, said test circuit does not connect in parallel with said AC low-voltage power source and said at least one bidirectional power converter includes a first bidirectional power converter and a second bidirectional power converter, wherein said the test circuit includes a test start point located on said AC low voltage power source, a first filter electrically connected with said test start point, said first bidirectional power converter electrically connected with said first filter, a loop circuit electrically connected with said first bidirectional power converter, said PCUT electrically connected with said loop circuit, said second bidirectional power converter located on said loop circuit to connect in parallel with said PCUT, a second filter located on said loop circuit to electrically connect with said second bidirectional power converter.
7. The method of claim 6, wherein said first filter and said second filter are LCL filters.
8. A system of a full load test of a power converter, comprising: an alternating current (AC) low voltage power source; a test circuit coupled to said AC low voltage power source; a power converter under test (PCUT) configured in said test circuit; and at least one bidirectional power converter connected in series with said PCUT in said test circuit; wherein said PCUT is a DC/DC converter, said test circuit is connected in parallel with said AC low-voltage power source and said at least one bidirectional power converter includes a first bidirectional power converter and a second bidirectional power converter, wherein said the test circuit includes a test start point located on said AC low voltage power source, a first filter electrically connected with said test start point, said first bidirectional power converter electrically connected with said first filter, said PCUT electrically connected with said first bidirectional power converter, said second bidirectional power converter connected with said PCUT, a second filter electrically connected with said second bidirectional power converter and a test end point located on said AC low voltage power source to electrically connect with said second filter.
9. The system of claim 8, wherein said first filter and said second filter are LCL filters.
10. A system of a full load test of a power converter, comprising: an alternating current (AC) low voltage power source; a test circuit coupled to said AC low voltage power source; a power converter under test (PCUT) configured in said test circuit; and at least one bidirectional power converter connected in series with said PCUT in said test circuit; wherein said PCUT is an AC/DC converter, said test circuit is connected in parallel with said AC low-voltage power source and said at least one bidirectional power converter includes a first bidirectional power converter, wherein said the test circuit includes a test start point located on said AC low voltage power source, a first filter electrically connected with said test start point, said first bidirectional power converter electrically connected with said first filter, said PCUT electrically connected with said first bidirectional power converter and a test end point located on said AC low voltage power source to electrically connect with said PCUT.
11. The system of claim 10, wherein said first filter is an LCL filter.
12. A system of a full load test of a power converter, comprising: an alternating current (AC) low voltage power source; a test circuit coupled to said AC low voltage power source; a power converter under test (PCUT) configured in said test circuit; and at least one bidirectional power converter connected in series with said PCUT in said test circuit; wherein said PCUT is an AC/DC converter, said test circuit does not connect in parallel with said AC low-voltage power source and said at least one bidirectional power converter includes a first bidirectional power converter and a second bidirectional power converter, wherein said the test circuit includes a test start point located on said AC low voltage power source, a first filter electrically connected with said test start point, said first bidirectional power converter electrically connected with said first filter, a loop circuit electrically connected with said first bidirectional power converter, said PCUT electrically connected with said loop circuit, said second bidirectional power converter located on said loop circuit to connect in parallel with said PCUT, a second filter located on said loop circuit to electrically connect with said second bidirectional power converter.
13. The system of claim 12, wherein said first filter and said second filter are LCL filters.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1)
(2)
(3)
(4)
(5)
DETAILED DESCRIPTION OF THE INVENTION
(6) In order to understand the technical features and practical efficacy of the present invention and to implement it in accordance with the contents of the specification, hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.
(7) Referring to
(8) When the process flow in
(9) Referring to
(10) The next step (c) is performed by serially connecting the PCUT 100 with at least one bidirectional power converter in the test circuit T. The at least one bidirectional power converter in the present embodiment includes a first bidirectional power converter 200a and a second bidirectional power converter 200b. Therefore, the test circuit T of this embodiment includes, a test start point S, a first filter 300a, the first bidirectional power converter 200a, the PCUT 100, the second bidirectional power converter 200b, a second filter 300b and a test end point E. The test start point S is located on the AC low voltage power source M, and the first filter 300a is electrically connected with the test start point S. The first bidirectional power converter 200a is electrically connected with the first filter 300a, and the PCUT 100 is electrically connected with the first bidirectional power converter 200a.
(11) The second bidirectional power converter 200b is also electrically connected with the PCUT 100, and the second filter 300b is electrically connected with the second bidirectional power converter 200b. The test end point E is located on the AC low voltage power source M, and the test end point E is electrically connected with the second filter 300b. In this embodiment, both of the first filter 300a and the second filter 300b are LCL filters, so that the whole test circuit T can be stably connected in parallel with the AC low voltage power source M.
(12) Then, the step (d) is performed to connect the test circuit T to the AC low-voltage power source M. As mentioned above, in the embodiment of
(13) In the embodiment of
(14) However, regardless of the test direction of arrow A1 or A2, the full-load power test in this example assumes that the full-load power of the PCUT 100 is 250 kilowatt (kW) and the full-load efficiency is 90%. Under the premise of 90% bi-directional conversion efficiency, the full load test of the AC low-voltage power source M can be completed only with a power source of
(15)
Comparing to the prior art under the same condition, the required power of 278 kW is reduced by 195 kW, and the reduction efficiency of the required power is 70.14%.
(16) Please refer to
(17) The step (c) is performed by serially connecting the PCUT 100 with at least one bidirectional power converter in the test circuit T. At least one bidirectional power converter in the present embodiment includes a first bidirectional power converter 200a. Therefore, the test circuit T of the present embodiment includes a test start point S, a first filter 300a, a first bidirectional power converter 200a, the PCUT 100 and a test end point E. The test start point S is located on the AC low voltage power source M, and the first filter 300a is electrically connected with the test start point S. The first bidirectional power converter 200a is electrically connected with the first filter 300a, and the PCUT 100 is electrically connected with the first bidirectional power converter 200a. The test end point E is located on the AC low voltage power source M, and the test end point E is electrically connected to the PCUT 100. In this embodiment, the first filter 300a is an LCL filter.
(18) Then, the step (d) is performed to connect the test circuit T to the AC low-voltage power source M. As mentioned above, in the embodiment of
(19) In the embodiment of
(20) In these embodiments, the conversion efficiency is 90% in the full load test along the direction of A3 in the embodiment of
(21) However, regardless of the test direction of arrow A3 or A4, under the same condition, the full-load power test in this implementation assumes that the full-load power of the PCUT 100 is 250 kW and the full-load efficiency is 90%. In the embodiment of
(22)
Compared with the prior art under the same condition, the required power of 278 kW is reduced by 225 kW, and the reduction efficiency of the required power is 80.93%.
(23) In the embodiment of
(24)
Compared with the prior art under the same condition, the required power of 278 kW is reduced by 236 kW, and the reduction efficiency of the required power is 84.89%.
(25) Finally, referring to
(26) The step (c) is performed to connect the PCUT 100 in series with at least one bidirectional power converter in the test circuit T. At least one bidirectional power converter in the present embodiment includes a first bidirectional power converter 200a and a second bidirectional power converter 200b. Therefore, the test circuit T of this embodiment includes a test start point S, a first filter 300a, the first bidirectional power converter 200a, a loop circuit C, the PCUT 100, the second bidirectional power converter 200b and a second filter 300b. The test start point S is located on the AC low voltage power source M, and the first filter 300a is electrically connected with the test start point S. The first bidirectional power converter 200a is electrically connected with the first filter 300a, and the loop circuit C is electrically connected with the first bidirectional power converter 200a.
(27) The PCUT 100 and the second bidirectional power converter 200b are also located on the loop circuit C, and the second bidirectional power converter 200b is connected in series with the PCUT 100. The second filter 300b is also electrically connected to the second bidirectional power converter 200b on the loop circuit C. In this embodiment, both the first filter 300a and the second filter 300b are LCL filters, which stabilize the entire test circuit T.
(28) Then, the step (d) is performed to connect the test circuit T to the AC low-voltage power source M. As mentioned above, in the embodiment of
(29) In the embodiment of
(30) When the full load power test is performed according to the embodiment of
(31)
Compared with the prior art under the same condition, the original required power of 326 kW is greatly reduced by 283 kW, and the reduction efficiency of the required power is 86.81%.
(32) The application of the embodiment of the present invention can greatly reduce the power required for full load test of various power converters 100 to be tested, which can not only solve the energy consumption problem, but also achieve the effect of improving the test efficiency.
(33) As is understood by a person skilled in the art, the foregoing preferred embodiments of the present invention are illustrated of the present invention rather than limiting of the present invention. It is intended to cover various modifications and similar arrangements included within the spirit and scope of the appended claims, the scope of which should be accorded the broadest interpretation so as to encompass all such modifications and similar structure. While the preferred embodiment of the invention has been illustrated and described, it will be appreciated that various changes can be made therein without departing from the spirit and scope of the invention.