METHOD FOR ALLOCATING ELECTRICAL POWER TO CRANE EQUIPMENT
20220289527 · 2022-09-15
Inventors
Cpc classification
B66C13/14
PERFORMING OPERATIONS; TRANSPORTING
B66C13/30
PERFORMING OPERATIONS; TRANSPORTING
International classification
B66C13/14
PERFORMING OPERATIONS; TRANSPORTING
B66C13/30
PERFORMING OPERATIONS; TRANSPORTING
Abstract
An allocation method for allocating an available maximum power from at least one power supply source to electrical equipment of a crane, in which the electrical equipment are powered with the available maximum power, includes selecting between: a raw mode in which the available maximum power is allocated over predefined actuation equipment and on accessory equipment predefined among the electrical equipment, the actuation equipment being defined according to a configuration of the crane, and an optimized mode in which the available maximum power is allocated over the predefined actuation equipment, and also over the accessory equipment but according to the cut-off conditions of the accessory equipment, so that according to the cut-off conditions the actuation equipment are powered or not.
Claims
1-20. (canceled)
21. An allocation method for allocating an available maximum power from at least one power supply source to electrical equipment of a crane, in which the electrical equipment are powered by the available maximum power which corresponds to a maximum power that can be delivered by the at least one power supply source, said allocation method being characterized in that it comprises a step of selecting between: a raw mode in which the available maximum power is allocated over predefined actuation equipment and over predefined accessory equipment among the electrical equipment, the actuation equipment being defined according to a configuration of the crane; and an optimized mode in which the available maximum power is allocated over the predefined actuation equipment, and also over the accessory equipment but according to cut-off conditions associated to the accessory equipment, so that according to their respective cut-off conditions the accessory equipment are powered or not.
22. The allocation method according to claim 21, wherein the at least one power supply source designates a primary power supply source and/or a rechargeable secondary power supply source.
23. The allocation method according to claim 21, wherein the actuation equipment comprise mounting equipment which participate in a mounting of the crane by acting on a displacement of part(s) of the crane when the crane is in a mounting configuration in displacing a load.
24. The allocation method according to claim 23, wherein the mounting equipment comprise at least one of the following equipment: a hydraulic folding/unfolding unit allowing to fold/unfold a mast and a jib, a hydraulic wedging unit allowing to wedge the crane on a ground, a hydraulic orientation unit allowing an orientation of a base of the crane, a hydraulic bracket unit allowing an actuation of a mounting bracket.
25. The allocation method according to claim 21, wherein the actuation equipment comprise working equipment that participate in displacing a load when the crane is in a working configuration.
26. The allocation method according to claim 25, wherein the working equipment comprise at least one of the following equipment: a motorized lifting system allowing to lift/lower a load, a motorized distribution system allowing a distribution of a load along a jib, an orientation motorized system allowing an orientation of a jib, a translation motorized system allowing a translation of the crane, a motorized lifting system allowing a lifting of a lulling jib.
27. The allocation method according to claim 21, wherein the accessory equipment comprises at least one of the following system accessory equipment: a heating system to heat a space of the crane, a ventilation or cooling system to ventilate/cool a space of the crane; and the cut-off conditions depend on at least one environmental parameter which is a physical parameter representative of the space of the crane.
28. The allocation method according to claim 27, wherein the environmental parameter is an internal temperature of the space of the crane.
29. The allocation method according to claim 27, wherein the space of the crane is an electrical cabinet internally grouping all or part of the organs participating in the electrical power supply of the crane, or a cockpit.
30. The allocation method according to claim 21, in which the accessory equipment comprise at least one of the following user accessory equipment: a lighting system, an electrical socket; and the cut-off conditions depend on a selection of a classification performed by a user for the or each of the user accessory equipment, amongst the following classifications: a «non-essential» classification which corresponds to an authorization not to power the corresponding user accessory equipment in the optimized mode in favor of the actuation equipment; and an «essential» classification which corresponds to a prohibition not to power the corresponding user accessory equipment in the optimized mode.
31. The allocation method according to claim 21, wherein, in the optimized mode, the actuation equipment are powered by an actuation power which is equivalent to the available maximum power or to the available maximum power minus an accessory power necessary to power the accessory equipment according to the cut-off conditions, and this actuation power is allocated over the actuation equipment according to an allocation scheme selected from the following two allocation schemes: a first scheme in which the actuation equipment are sequentially activated and therefore sequentially powered, so that each actuation equipment is powered, when activated, by the actuation power; and a second scheme in which the actuation equipment are simultaneously activated and therefore simultaneously powered, so that all the actuation equipment are powered together by the actuation power.
32. The allocation method according to claim 31, wherein a storage is implemented in a memory to store of a plurality of preferential allocation modes, each preferential allocation mode being associated with percentages of allocation of the actuation power over the different actuation equipment in the second scheme, and the allocation method implements a selection of a preferential allocation mode to provide an allocation of the actuation power in accordance with said selected preferential allocation mode when the second scheme is selected.
33. A crane comprising electrical equipment intended to be electrically powered from at least one power supply source capable of providing an available maximum power which corresponds to a maximum power that can be delivered by the at least one power supply source, said electrical equipment comprising actuation equipment defined according to a configuration of the crane and accessory equipment, wherein said crane comprises a control/command unit configured for the implementation of the allocation method according to claim 21, said control/command unit being connected, on the one hand, to an interface allowing a selection between the raw mode and the optimized mode and, on the other hand, to an electrical circuit connecting the at least one power supply source to the electrical equipment to control an allocation of the available maximum power according to the selected mode among the raw mode and optimized mode.
34. The crane according to claim 33, wherein the actuation equipment comprise mounting equipment which participate in the mounting of the crane by acting on a displacement of part(s) of the crane when the crane is in a mounting configuration.
35. The crane according to claim 34, wherein the mounting equipment comprise at least one of the following equipment: a hydraulic folding/unfolding unit allowing to fold/unfold a mast and a jib, a hydraulic wedging unit allowing to wedge the crane on the ground, a hydraulic orientation unit allowing an orientation of a base of the crane, a hydraulic bracket unit allowing an actuation of a mounting bracket.
36. The crane according to claim 33, wherein the actuation equipment comprise working equipment that participate in the displacement of a load when the crane is in a working configuration.
37. The crane according to claim 36, wherein the working equipment comprise at least one of the following equipment: a motorized lifting system allowing to lift/lower a load, a motorized distribution system allowing a distribution of a load along a jib, an orientation motorized system allowing an orientation of a jib, a translation motorized system allowing a translation of the crane, a motorized lifting system allowing a lifting of a luffing jib.
38. The crane according to claim 33, wherein the accessory equipment comprise at least one of the following system accessory equipment: a heating system to heat a space of the crane, a ventilation or cooling system to ventilate/cool a space of the crane; and the cut-off conditions depend on at least one environmental parameter which is a physical parameter representative of the space of the crane.
39. The crane according to claim 38, wherein the environmental parameter is an internal temperature of the space of the crane.
40. The crane according to claim 38, wherein the space of the crane is an electrical cabinet internally grouping all or part of the organs participating in the electrical power supply of the crane, or a cockpit.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0079] The invention will be better understood using the detailed description which is exposed below with regard to the appended drawings in which:
[0080]
[0081]
[0082]
[0083]
[0084]
[0085]
[0086]
[0087]
DESCRIPTION
[0088] In the detailed description which will follow of the figures defined above, the same elements or the elements performing identical functions may retain the same references so as to simplify the understanding of the invention.
[0089] The first part of the following description relates to the implementation of a management method «POWER MANAGEMENT» for managing electrical power supply to electrically power electrical equipment 9 of a crane CR, via a conversion circuit Q, from two power supply sources:
[0090] a primary power supply source PRIM (also called primary source), such as for example an electrical network and/or a generating unit, which is capable of providing a primary power PRPOW, and
[0091] a rechargeable secondary power supply source SEC (also called rechargeable secondary source or secondary source), such as for example one or more rechargeable batteries, which is capable of providing a secondary power SECPOW.
[0092] The implementation of the steps of this management method «POWER MANAGEMENT» is shown in
[0093] This management method «POWER MANAGEMENT» implements two monitoring steps which are:
[0094] monitoring of a requested general power RGPOW which corresponds to a power requested by all the electrical equipment 9 of the crane CR, and
[0095] monitoring of a charge level CL of the rechargeable secondary power supply source SEC.
[0096] In addition, this management method «POWER MANAGEMENT» implements, depending on the requested general power RGPOW and the charge level CL, at least the following management modes:
[0097] a recharging mode RECHMOD shown in
[0098] a mixed recharging/powering mode MIXMOD presented in
[0099] a main power supply mode MAINMOD presented in
[0100] a hybrid power supply mode HYBMOD shown in
[0101] an autonomous power supply mode AUTOMOD presented in
[0102] In the management method «POWER MANAGEMENT», the electrical equipment 9 are powered with an available maximum power PMAX which corresponds to the minimum between a maximum conversion power PCONV and a source power PS, wherein the maximum conversion power PCONV corresponds to a maximum power that can be delivered at the output of a conversion circuit Q.
[0103] The source power PS depends on the management mode, and it corresponds to:
[0104] the sum of the secondary power SECPOW and the primary power PRPOW in the hybrid power supply mode HYBMOD of
[0105] the secondary power SECPOW in the autonomous power supply mode AUTOMOD in
[0106] the primary power PRPOW in the main power supply mode MAINMOD of
[0107] the primary power PRPOW minus a recharging power PCH used to recharge the rechargeable secondary power supply source SEC in the mixed recharging/powering mode MIXMOD of
[0108] Moreover, the management method «POWER MANAGEMENT» implements, in the autonomous power supply mode AUTOMOD and in the hybrid power supply mode HYBMOD, an adaptation of the secondary power SECPOW as a function of at least the charge level CL, said secondary power SECPOW being less than or equal to a maximum secondary power SECPOWMAX which corresponds to a maximum power that can be delivered by the rechargeable secondary power supply source SEC.
[0109] Thus, and with reference to
[0110] either connected to the electrical equipment 9 of the crane CR to participate in their electrical power supply, which leads to the hybrid power supply mode HYBMOD or to the autonomous power supply mode AUTOMOD;
[0111] either disconnected from the electrical equipment 9 of the crane CR so as not to take part in their electrical power supply, which leads to the main power supply mode MAINMOD or to the mixed recharging/powering mode MMEXT.
[0112] If, at the end of the power supply step C1, the rechargeable secondary source SEC is disconnected, then it is the main power supply mode MAINMOD or the mixed recharging/powering mode MIXMOD which is selected, and it is followed by the execution of a step F1, or «POWER ALLOCATION» step, to initiate an allocation method «POWER ALLOCATION» (described below) for allocating the available maximum power PMAX. As a reminder, the available maximum power PMAX corresponds to:
[0113] in the main power supply mode MAINMOD, at least between the maximum conversion power PCONV and the primary power PRPOW; and
[0114] in the mixed recharging/powering mode MIXMOD, at least between the maximum conversion power PCONV and the primary power PRPOW minus the recharging power PCH.
[0115] If, however, at the end of the power supply step C1, the rechargeable secondary source SEC is connected (that is to say that the power supply will use the rechargeable secondary source SEC), then it is followed by the execution of a step of selecting a mode C2, or «MODE SELECTION» step, which consists in selecting between the hybrid power supply mode HYBMOD and the autonomous power supply mode AUTOMOD.
[0116] This POWER SUPPLY step C1 followed by this mode selection step C2 thus leads to selecting the management mode. Depending on various parameters, and in particular the requested general power RGPOW, the availability of the primary power supply source PRIM and the primary power PRPOW, these selection steps C1, C2 can operate automatically for the management mode selection.
[0117] Thus, when the requested general power RGPOW is non-zero, the following management modes can be automatically implemented or selected (during the two successive selection steps C1, C2):
[0118] the autonomous power supply mode AUTOMOD is automatically implemented (or selected) if the primary power supply source PRIM is not available;
[0119] the main power supply mode MAINMOD or the mixed recharging/powering mode MIXMOD is automatically implemented (or selected) according to the charge level CL of the rechargeable secondary power supply source SEC, if the primary power supply source PRIM is available and if the requested general power RGPOW is less than the primary power PRPOW;
[0120] the hybrid power supply mode HYBMOD is automatically implemented (or selected) if the primary power supply source PRIM is available and if the requested general power RGPOW is greater than the primary power PRPOW.
[0121] After the mode selection step C2, the management method «POWER MANAGEMENT» implements a selection, in the hybrid power supply mode HYBMOD and in the autonomous power supply mode AUTOMOD, of a management sub-mode among several management sub-modes comprising at least:
[0122] an automatic sub-mode «AUTO» in which the secondary power SECPOW is controlled to correspond to ka times the maximum secondary power SECPOWMAX, wherein ka is a coefficient which is less than or equal to 1 and which decreases with the charge level CL until the charge level CL drops below a low threshold LOW;
[0123] an economical sub-mode «ECO» in which the secondary power SECPOW is controlled to correspond to ke times the secondary maximum power SECPOWMAX, wherein ke is a coefficient less than ka and which decreases with the charge level CL until the charge level CL drops below a low threshold LOW;
[0124] an extreme sub-mode «EXTR» in which the secondary power SECPOW corresponds to the maximum secondary power SECPOWMAX whatever the value of the charge level CL of the rechargeable secondary power supply source SEC.
[0125] The low threshold LOW can be comprised between 5 and 15% of a charge capacity of the rechargeable secondary power supply source SEC and a high threshold HIGH can be comprised between 40 and 60% of a charge capacity of the rechargeable secondary power supply source SEC.
[0126] With reference to
[0127] If the sub-mode selected during the sub-mode selection step C3 is the automatic sub-mode «AUTO», then a step of controlling a charge level C3-1 is executed, or «CHARGE LEVEL CONTROL» step, during which the charge level CL of the rechargeable secondary power supply source SEC is measured and is compared with the low threshold LOW and the high threshold HIGH.
[0128] If, during the charge level control step C3-1, the charge level CL of the rechargeable secondary power supply source SEC is lower than the low threshold LOW, then a step S3-1 is executed, or step «KA=0», which sets the coefficient ka to zero, so that the secondary power SECPOW is zero. In other words, if the charge level CL is less than 5 to 15% of the charge capacity, then the rechargeable secondary power supply source SEC is providing no power. At the end of this step S3-1, the management method «POWER MANAGEMENT» automatically switches to a standby mode designated by «STANDBY» in
[0129] If, during the charge level control step C3-1, the charge level CL of the rechargeable secondary power supply source SEC is comprised between the low threshold LOW and the high threshold HIGH, then a step S3-2 is executed, or step «KA=KAMIN», which sets the coefficient ka to a value kamin, kamin being comprised between 0.5 and 0.7. In other words, and for example, if the charge level CL of the battery is 30% of its charge capacity, then the provided secondary power SECPOW is equal to kamin times the secondary maximum power SECPOWMAX, namely SECPOW=kamin.Math.SECPOWMAX. This step S3-2 is followed by a step F3-2, or «POWER ALLOCATION» step, which implements the allocation method «POWER ALLOCATION» for allocating the available maximum power PMAX, wherein the available maximum power PMAX corresponds to the minimum between the power of maximum conversion PCONV and the source power PS which is equivalent to the secondary power SECPOW which is equal to kamin.Math.SECPOWMAX in this automatic sub-mode «AUTO» of the autonomous power supply mode AUTOMOD. These steps S3-2 and F3-2 are executed as long as the charge level CL is comprised between the low threshold LOW and the high threshold HIGH and, if the charge level CL drops below the low threshold LOW, then step S3-1 is executed.
[0130] If during the charge level control step C3-1, the charge level CL of the rechargeable secondary power supply source SEC is greater than the high threshold HIGH, then a step S3-3 is executed, or step «KA=KAMAX», which sets the coefficient ka to a value kamax, kamax being greater than kamin and for example comprised between 0.8 and 1. In other words, and for example, if the charge level CL of the battery is 90% of its charge capacity, then the provided secondary power SECPOW is equal to kamax times the secondary maximum power SECPOWMAX, namely SECPOW=kamax.Math.SECPOWMAX. This step S3-3 is followed by a step F3-3, or «POWER ALLOCATION» step, which implements the allocation method «POWER ALLOCATION» for allocating the available maximum power PMAX, wherein the available maximum power PMAX corresponds to the minimum between the maximum conversion power PCONV and the source power PS which is equivalent to the secondary power SECPOW which is equal to kamax.Math.SECPOWMAX in this automatic sub-mode «AUTO» of the autonomous power supply mode AUTOMOD. These steps S3-3 and F3-3 are executed as long as the charge level CL is higher than the high threshold HIGH and, if the charge level CL drops below the high threshold HIGH, then steps S3-2 and F3-2 are executed.
[0131] If the sub-mode selected during the sub-mode selection step C3 is the economical sub-mode «ECO», then a step of controlling a charge level C3-2 is executed, or «CHARGE LEVEL CONTROL» step, during which the charge level CL of the rechargeable secondary power supply source SEC is measured and is compared with the low threshold LOW and the high threshold HIGH.
[0132] If during the charge level control step C3-2, the charge level CL of the rechargeable secondary power supply source SEC is lower than the low threshold LOW, then a step S3-4 is executed, or step «KE=0», which sets the coefficient ke to zero, so that the secondary power SECPOW is zero. In other words, if the charge level CL is less than 5 to 15% of the charge capacity, then the rechargeable secondary power supply source SEC is providing no power. At the end of this step S3-4, the method «POWER MANAGEMENT» automatically switches to a standby mode designated by «STANDBY» in
[0133] Thus, in the autonomous power supply mode AUTOMOD, and whether in the automatic sub-mode «AUTO» or in the economical sub-mode «ECO», the management method «POWER MANAGEMENT» automatically switches to the standby mode «STANDBY» after the charge level CL of the rechargeable secondary power supply source SEC drops below the low threshold LOW, wherein in this standby mode «STANDBY» only predefined safety equipment among the equipment of the crane CR are powered to allow the crane CR to be safe-guarded, and for example to be placed in a weather vane state. In the standby mode STANDBY, the secondary power SECPOW can be controlled to correspond to the maximum secondary power SECPOWMAX in order to power this safety equipment at least the time the crane CR is safe-guarded, namely placed in a weather vane state.
[0134] This safety equipment may comprise equipment which will, for example, allow the jib to be lifted before releasing it in orientation so that it is free to turn with the wind while offering a reduced radius of gyration, the jib is then described as being put in a weather vane state.
[0135] If during the charge level control step C3-2, the charge level CL of the rechargeable secondary power supply source SEC is comprised between the low threshold LOW and the high threshold HIGH, then a step S3-5, or step «KE=KEMIN», which sets the coefficient ke to a value kemin, kemin being comprised between 0.2 and 0.4. In other words, and for example, if the charge level CL of the battery is 30% of its charge capacity, then the provided secondary power SECPOW is equal to kemin times the maximum secondary power SECPOWMAX, namely SECPOW=kemin.Math.SECPOWMAX. This step S3-5 is followed by a step F3-5, or «POWER ALLOCATION» step, which implements the allocation method «POWER ALLOCATION» for allocating the available maximum power PMAX, wherein the available maximum power PMAX corresponds to the minimum between the maximum conversion power PCONV and the source power which is equivalent to the secondary power SECPOW which is equal to kemin.Math.SECPOWMAX in this economical sub-mode «ECO» of the autonomous power supply mode AUTOMOD. These steps S3-5 and F3-5 are executed as long as the charge level CL is comprised between the low threshold LOW and the high threshold HIGH and, if the charge level CL drops below the low threshold LOW, then step S3-4 is executed.
[0136] If during the charge level control step C3-2, the charge level CL of the rechargeable secondary power supply source SEC is greater than the high threshold HIGH, then a step S3-6 is executed, or step «KE=KEMAX», which sets the coefficient ke to a value kemax, kemax being greater than kemin and kemax being for example comprised between 0.6 and 0.8. In other words, and for example, if the charge level CL of the battery is 90% of its capacity, then the secondary power SECPOW is equal to kemax times the secondary maximum power SECPOWMAX, namely SECPOW=kemax.Math.SECPOWMAX. This step S3-6 is followed by a step F3-6, or «POWER ALLOCATION» step, which implements the allocation method «POWER ALLOCATION» for allocating the available maximum power PMAX, wherein the available maximum power PMAX corresponds to the minimum between the maximum conversion power PCONV and the source power which is equivalent to the secondary power SECPOW which is equal to kemax.Math.SECPOWMAX in this economical sub-mode «ECO» of the autonomous power supply mode AUTOMOD. These steps S3-6 and F3-6 are executed as long as the charge level CL is higher than the high threshold HIGH and, if the charge level CL drops below the high threshold HIGH, then steps S3-5 and F3-5 are executed.
[0137] In principle, the value of kemax is greater than that of kemin, and kamax is greater than kemax, and kamin is greater than kemin.
[0138] If the sub-mode selected during the sub-mode selection step C3 is the extreme sub-mode «EXTR», then a step F3-0, or «POWER ALLOCATION» step, is executed which implements the allocation method «POWER ALLOCATION» for allocating the available maximum power PMAX, wherein the available maximum power PMAX corresponds to the minimum between the maximum conversion power PCONV and the source power which is equivalent to the secondary power SECPOW which is equal to SECPOWMAX in this extreme sub-mode «EXTR» of the autonomous power supply mode AUTOMOD.
[0139] According to one possibility, in the extreme sub-mode «EXTR» in step F3-0, when the charge level CL of the rechargeable secondary power supply source SEC drops below the low threshold LOW then the method «POWER MANAGEMENT» switches automatically in the standby mode «STANDBY» described above, during which only the safety equipment of the crane CR are powered to allow the crane CR to be safe-guarded.
[0140] With reference to
[0141] If the sub-mode selected during the sub-mode selection step C4 is the automatic sub-mode «AUTO», then a charge level control step C4-1 is executed, or «CHARGE LEVEL CONTROL» step, during which the charge level CL of the rechargeable secondary power supply source SEC is measured and is compared with the low threshold LOW and the high threshold HIGH.
[0142] If, during the charge level control step C4-1, the charge level CL of the rechargeable secondary power supply source SEC is lower than the low threshold LOW, then a step S4-1 is executed, or step «KA=0», which sets the coefficient ka to zero, so that the secondary power SECPOW is zero. In other words, if the charge level CL is less than 5 to 15% of the charge capacity, then the rechargeable secondary power supply source SEC does not provide any power, and thus the source power PS is entirely provided by the primary power supply source PRIM. This step S4-1 is followed by a step F4-1, or «POWER ALLOCATION» step, which implements the allocation method «POWER ALLOCATION» for allocating the available maximum power PMAX, wherein the available maximum power PMAX corresponds to the minimum between the maximum conversion power PCONV and the source power PS which is equivalent to the primary power PRPOW, namely PS=PRPOW, in this automatic sub-mode «AUTO» of the hybrid power supply mode HYBMOD.
[0143] If during the charge level control step C4-1, the charge level CL of the rechargeable secondary power supply source SEC is comprised between the low threshold LOW and the high threshold HIGH, then a step S4-2, or step «KA=KAMIN», which sets the coefficient ka to the value kamin, kamin being comprised between 0.5 and 0.7. In other words, and for example, if the charge level CL of the battery is 30% of its charge capacity, then the provided secondary power SECPOW is equal to kamin times the secondary maximum power SECPOWMAX, namely SECPOW=kamin.Math.SECPOWMAX. This step S4-2 is followed by a step F4-2, or «POWER ALLOCATION» step, which implements the allocation method «POWER ALLOCATION» for allocating the available maximum power PMAX, wherein the available maximum power PMAX corresponds to the minimum between the maximum conversion power PCONV and the source power PS which is equivalent to the sum of the primary power PRPOW and the secondary power SECPOW, namely PS=PRPOW+kamin.Math.SECPOWMAX in this automatic sub-mode «AUTO» of the hybrid power supply mode HYBMOD. These steps S4-2 and F4-2 are executed as long as the charge level CL is higher than the low threshold LOW and, if the charge level CL drops below the low threshold LOW, then steps S4-1 and F4-1 are executed.
[0144] If during the charge level control step C4-1, the charge level CL of the rechargeable secondary power supply source SEC is greater than the high threshold HIGH, then a step S4-3 is executed, or step «KA=KAMAX», which sets the coefficient ka to the value kamax, kamax being comprised between 0.8 and 1. In other words, and for example, if the NC charge level of the battery is 90% of its charge capacity, then the provided secondary power SECPOW is equal to kamax times the maximum secondary power SECPOWMAX, namely SECPOW=kamax.Math.SECPOWMAX. This step S4-3 is followed by a step F4-3, or «POWER ALLOCATION» step, which implements the allocation method «POWER ALLOCATION» for allocating the available maximum power PMAX, wherein the available maximum power PMAX corresponds to the minimum between the maximum conversion power PCONV and the source power PS which is equivalent to the sum of the primary power PRPOW and the secondary power SECPOW, namely PS=PRPOW+kamax.Math.SECPOWMAX in this automatic sub-mode «AUTO» of the hybrid power supply mode HYBMOD. These steps S4-3 and F4-3 are executed as long as the charge level CL is higher than the high threshold HIGH and, if the charge level CL drops below the high threshold HIGH, then steps S4-2 and F4-2 are executed.
[0145] If the sub-mode selected during the sub-mode selection step C4 is the economical sub-mode «ECO», then a step of controlling a charge level C4-2 is executed, or «CHARGE LEVEL CONTROL» step, during which the charge level CL of the rechargeable secondary power supply source SEC is measured and is compared with the low threshold LOW and the high threshold HIGH.
[0146] If, during the charge level control step C4-2, the charge level CL of the rechargeable secondary power supply source SEC is lower than the low threshold LOW, then a step S4-4 is executed, or step «KE=0», which sets the coefficient ke to zero, so that the secondary power SECPOW is zero. In other words, if the charge level CL is less than 5 to 15% of the charge capacity, then the rechargeable secondary power supply source SEC does not provide any power, and thus the source power PS is entirely provided by the primary power supply source PRIM. This step S4-4 is followed by a step F4-4, or «POWER ALLOCATION» step, which implements the allocation method «POWER ALLOCATION» for allocating the available maximum power PMAX, wherein the available maximum power PMAX corresponds to the minimum between the maximum conversion power PCONV and the source power PS which is equivalent to the primary power PRPOW, namely PS=PRPOW, in this economical sub-mode «ECO» of the hybrid power supply mode HYBMOD.
[0147] If during the charge level control step C4-2, the charge level CL of the rechargeable secondary power supply source SEC is comprised between the low threshold LOW and the high threshold HIGH, then a step S4-5, or step «KE=KEMIN», which sets the coefficient ke to the value kemin, kemin being comprised between 0.2 and 0.4. In other words, and for example, if the charge level CL of the battery is 30% of its charge capacity, then the provided secondary power SECPOW is equal to kemin times the maximum secondary power SECPOWMAX, namely SECPOW=kemin.Math.SECPOWMAX. This step S4-5 is followed by a step F4-5, or «POWER ALLOCATION» step, which implements the allocation method «POWER ALLOCATION» for allocating the available maximum power PMAX, wherein the available maximum power PMAX corresponds to the minimum between the maximum conversion power PCONV and the source power PS which is equivalent to the sum of the primary power PRPOW and of the secondary power SECPOW, namely PS=PRPOW+kemin.Math.SECPOWMAX in this economical sub-mode «ECO» of the hybrid power supply mode HYBMOD. These steps S4-5 and F4-5 are executed as long as the charge level CL is higher than the low threshold LOW and, if the charge level CL drops below the low threshold LOW, then steps S4-4 and F4-4 are executed.
[0148] If during the charge level control step C4-2, the charge level CL of the rechargeable secondary power supply source SEC is greater than the high threshold HIGH, then a step S4-6 is executed, or step «KE=KEMAX», which sets the coefficient ke to the value kemax, kemax being comprised between 0.6 and 0.8. In other words, and for example, if the charge level CL of the battery is 90% of its charge capacity, then the provided secondary power SECPOW is equal to kemax times the secondary maximum power SECPOWMAX, namely SECPOW=kemax.Math.SECPOWMAX. This step S4-6 is followed by a step F4-6, or «POWER ALLOCATION» step, which implements the allocation method «POWER ALLOCATION» for allocating the available maximum power PMAX, wherein the available maximum power PMAX corresponds to the minimum between the maximum conversion power PCONV and the source power PS which is equivalent to the sum of the primary power PRPOW and of the secondary power SECPOW, namely PS=PRPOW+kemax.Math.SECPOWMAX in this economical sub-mode «ECO» of the hybrid power supply mode HYBMOD. These steps S4-6 and F4-6 are executed as long as the charge level CL is higher than the high threshold HIGH and, if the charge level CL drops below the high threshold HIGH, then steps S4-5 and F4-5 are executed.
[0149] If the selected sub-mode during the sub-mode selection step C4 is the extreme sub-mode «EXTR», then a step F4-0, or «POWER ALLOCATION» step, is executed which implements the allocation method «POWER ALLOCATION» for allocating the available maximum power PMAX, wherein the available maximum power PMAX corresponds to the minimum between the maximum conversion power PCONV and the source power PS which is equivalent to the sum of the primary power PRPOW and the secondary power SECPOW which is equal to SECPOWMAX, namely PS=PRPOW+SECPOWMAX in this extreme sub-mode «EXTR» of the hybrid power supply mode HYBMOD.
[0150] According to one possibility, in the extreme sub-mode «EXTR» in step F4-0, when the charge level CL of the rechargeable secondary power supply source SEC drops below the low threshold LOW then the management method «POWER MANAGEMENT» automatically switches in the standby mode «STANDBY» described above, during which only the safety equipment of the crane CR is powered to allow the crane CR to be safe-guarded, and for example to be placed in a weather vane state.
[0151] The second part of the following description relates to the implementation of the allocation method «POWER ALLOCATION» for allocating the available maximum power PMAX to the various electrical equipment 9 of the crane CR, regardless of the management mode among the hybrid power supply mode HYBMOD, autonomous power supply mode AUTOMOD, main power supply mode MAINMOD and mixed recharging/powering mode MIXMOD. The purpose of this allocation method «POWER ALLOCATION» is to optimize the allocation of the available maximum power PMAX, in particular when this available maximum power PMAX is insufficient to power all the electrical equipment 9 of the crane CR at full capacity.
[0152] As previously described, the available maximum power PMAX depends on the management mode, the management sub-mode and the charge level CL of the rechargeable secondary power supply source SEC, with an available maximum power
[0153] PMAX which is equivalent to the minimum between the maximum conversion power PCONV and the source power PS which is equivalent to:
[0154] in step F1 in main power supply mode MAINMOD, the primary power PRPOW (namely PS=PRPOW),
[0155] in step F1 in mixed recharging/powering mode MIXMOD, the primary power PRPOW minus the recharging power PCH (namely PS=PRPOW−PCH);
[0156] in step F3-2 in automatic sub-mode «AUTO» of the autonomous power supply mode AUTOMOD, the secondary power SECPOW which is equal to kamin.Math.SECPOWMAX (namely PS=SECPOW=kamin.Math.SECPOWMAX);
[0157] in step F3-3 in automatic sub-mode «AUTO» of the autonomous power supply mode AUTOMOD, the secondary power SECPOW which is equal to kamax.Math.SECPOWMAX (namely PS=SECPOW=kamax.Math.SECPOWMAX);
[0158] n step F3-5 in economical sub-mode «ECO» of the autonomous power supply mode AUTOMOD, the secondary power SECPOW which is equal to kemin.Math.SECPOWMAX (namely PS=SECPOW=kemin.Math.SECPOWMAX);
[0159] in step F3-6 in economical sub-mode «ECO» of the autonomous power supply mode AUTOMOD, the secondary power SECPOW which is equal to kemax.Math.SECPOWMAX (namely PS=SECPOW=kemax.Math.SECPOWMAX);
[0160] in step F3-0 in extreme sub-mode «EXTR» of the autonomous power supply mode AUTOMOD, the secondary power SECPOW which is equal to SECPOWMAX (namely PS=SECPOW=SECPOWMAX);
[0161] in step F4-1 in automatic sub-mode «AUTO» of the hybrid power supply mode HYBMOD, the primary power PRPOW (namely PS=PRPOW),
[0162] in step F4-2 in automatic sub-mode «AUTO» of the hybrid power supply mode HYBMOD, the sum of the primary power PRPOW and the secondary power SECPOW which is equal to kamin.Math.SECPOWMAX (namely PS=PRPOW+SECPOW=PRPOW+kamin.Math.SECPOWMAX),
[0163] in step F4-3 in automatic sub-mode «AUTO» of the hybrid power supply mode HYBMOD, the sum of the primary power PRPOW and the secondary power SECPOW which is equal to kamax.Math.SECPOWMAX (namely PS=PRPOW+SECPOW=PRPOW+kamax.Math.SECPOWMAX),
[0164] in step F4-4 in economical sub-mode «ECO» of the hybrid power supply mode HYBMOD, the primary power PRPOW (namely PS=PRPOW),
[0165] in step F4-5 in economical sub-mode «ECO» of the hybrid power supply mode HYBMOD, the sum of the primary power PRPOW and the secondary power SECPOW which is equal to kemin.Math.SECPOWMAX (namely PS=PRPOW+SECPOW=PRPOW+kemin.Math.SECPOWMAX),
[0166] in step F4-6 in economical sub-mode «ECO» of the hybrid power supply mode HYBMOD, the sum of the primary power PRPOW and the secondary power SECPOW which is equal to kemax.Math.SECPOWMAX (namely PS=PRPOW+SECPOW=PRPOW+kemax.Math.SECPOWMAX),
[0167] in step F4-0 in extreme sub-mode «EXTR» of the hybrid power supply mode HYBMOD, the sum of the primary power PRPOW and the secondary power SECPOW which is equal to SECPOWMAX (namely PS=PRPOW+SECPOW=PRPOW+SECPOWMAX).
[0168] Referring to
[0169] a raw mode «RAWMOD» in which the available maximum power PMAX is allocated over predefined actuation equipment 91, 92 and over predefined accessory equipment 93, 94 among the electrical equipment 9 of the crane CR, the actuation equipment 91, 92 being defined according to a crane CR configuration; and
[0170] an optimized mode «OPTMOD» in which the available maximum power PMAX is allocated over the predefined actuation equipment 91, 92, and also over the accessory equipment 93, 94 but also according to cut-off conditions associated to the accessory equipment 93, 94, so that according to their respective cut-off conditions the accessory equipment 93, 94 are powered or not.
[0171] The actuation equipment 91, 92 may comprise mounting equipment 91 which participates in the mounting of the crane CR when the crane CR is in a mounting configuration designated by «MOUNTING» in
[0172] The mounting equipment 91 may comprise at least one of the following equipment: a hydraulic folding/unfolding unit allowing a mast and a jib to be folded/unfolded, a hydraulic wedging unit enabling the crane to be wedged on the ground, a hydraulic orientation unit allowing an orientation of a base of the crane, a hydraulic bracket unit allowing an actuation of a mounting bracket. In general, in the mounting configuration, in other words during the mounting/dismounting phases of the crane, either a single mounting equipment 91 is actuated (for example the hydraulic folding/unfolding unit), or several mounting equipment 91 are actuated successively and individually because the mounting/dismounting phases are sequenced.
[0173] The working equipment 92 may comprise at least one of the following equipment: a motorized lifting system 920 allowing lifting/lowering of a load, a motorized distribution system 921 allowing a distribution of a load along a jib, a motorized orientation system 922 allowing orientation of a jib, a motorized translation system allowing translation of the crane, a motorized lifting system allowing lifting of a luffing jib (or tilting jib). In general, in the working configuration, in other words during the phases of displacing a load, several working equipment 92 are actuated simultaneously, and sometimes are successively and individually actuated.
[0174] For the rest of the description, three working equipment 92 will be considered for the crane CR when in working configuration, namely:
[0175] the motorized lifting system 920 which receives an electrical lifting power PLIFT, which is less than or equal to the electrical power required by this motorized lifting system 920;
[0176] the motorized distribution system 921 which receives an electrical distribution power PDIST, which is less than or equal to the requested electrical power by this motorized distribution system 921;
[0177] the motorized orientation system 922 which receives an orientation electrical power PORI EN, which is less than or equal to the electrical power required by this motorized orientation system 922.
[0178] The accessory equipment 93, 94 are equipment which do not take part in the operations of mounting and displacing a charge or a structural element of the crane CR, and these accessory equipment 93, 94 may comprise one or more system accessory equipment 93 and/or one or more user accessory equipment 94.
[0179] The system accessory equipment 93 may comprise at least one of the following equipment:
[0180] a heating system 931 to heat a space 71 in the crane CR, such as for example a cockpit;
[0181] a ventilation or cooling system 932 to ventilate/cool a space 72 in the crane CR;
[0182] and the cut-off conditions for these system accessory equipment 931, 932, in the optimized mode «OPTMOD», can depend on at least one environmental parameter which is a physical parameter representative of the space 71, 72 of the crane CR. According to one possibility, this environmental parameter is an internal space temperature of the crane CR.
[0183] The space 72 of the crane CR can correspond to an electrical cabinet internally grouping all or part of the organs participating in the power supply of the crane CR. In other words, in the optimized mode «OPTMOD», the heating of the cockpit 71, and the ventilation or cooling of this electrical cabinet 72 will depend on the cut-off conditions which are a function of the internal temperature respectively in this cockpit 71 and in this electrical cabinet 72.
[0184] The user accessory equipment 94 may comprise at least one of the following equipment: a lighting system 941, an electrical socket 942; and the cut-off conditions for this user accessory equipment 94, in the optimized mode «OPTMOD», may depend on a selection of a classification performed by a user for the or each of the user accessory equipment 94, amongst the following classifications:
[0185] a «non-essential» classification which corresponds to an authorization not to power the corresponding user accessory equipment 94 in the optimized mode OPTMOD in favor of the actuation equipment 91, 92; and
[0186] an «essential» classification which corresponds to a prohibition not to power the corresponding user accessory equipment 94 in the optimized mode OPTMOD.
[0187] Referring to
[0188] And in the same way, if during the initial selection step T1, the optimized mode OPTMOD is selected, then a step of selecting a configuration T2 is executed, or «CONFIGURATION SELECTION» step, in which a choice of a crane configuration is made between the mounting configuration and the working configuration.
[0189] If, in the raw mode RAWMOD, during the configuration selection step T3, the mounting configuration is selected, then a step E3-1, or «ALLOCATION PMAX» step, is executed during which the available maximum power PMAX is allocated over the actuation equipment 91, 92 (which here are the mounting equipment 91) and over the accessory equipment 93, 94, such that this/these mounting equipment 91 receive an actuation power PACT which is equivalent to the available maximum power PMAX reduced by a power accessory PACC, namely PACT=PMAX−PACC; the accessory power PACC corresponding to the electrical power requested by the accessory equipment 93, 94 or the power necessary to power this accessory equipment 93, 94. This step E3-2 is followed by a step E3-3, or «ALLOCATION PACT» step, during which the actuation power PACT is allocated over the mounting equipment 91, so that each mounting equipment 91 receives an electrical power which is less than or equal to this actuation power PACT. If only one mounting equipment 91 is involved (for example the hydraulic folding/unfolding unit) then all the actuation power PACT are allocated to this single mounting equipment 91.
[0190] If, however, in the raw mode RAWMOD, during the configuration selection step T3, the working configuration is selected, then a step E3-2, or «ALLOCATION PMAX» step, is executed during which the available maximum power PMAX is allocated over the actuation equipment 91, 92 (which are here the working equipment 92) and over the accessory equipment 93, 94, such that this/these working equipment 92 receive an actuation power PACT which is equivalent to the available maximum power PMAX minus the accessory power PACC, namely PACT=PMAX−PACC. This step E3-2 is followed by a step E3-4, or «ALLOCATION PACT» step, during which the actuation power PACT is allocated over the various working equipment 92, so that each working equipment 92 receives an electrical power which is less than or equal to this actuation power PACT which amounts to, in the embodiment described above, PLIFT≤PACT, PDIST≤PACT and PORIEN≤PACT.
[0191] In the optimized mode OPTMOD, the actuation equipment 91, 92 can be powered by the actuation power PACT which is equivalent:
[0192] either to the available maximum power PMAX if the cut-off conditions are such that all the accessory equipment 93, 94 are cut off (therefore turned off or not powered), so PACT=PMAX;
[0193] or to the available maximum power PMAX minus the accessory power PACC, so PACT=PMAX−PACC, this accessory power PACC corresponding to the electrical power requested by the accessory equipment 93, 94 which is/are not cut according to the cut-off conditions.
[0194] Thus, the accessory equipment 93, 94 will be divided into:
[0195] cut accessory equipment, which are accessory equipment whose cut-off conditions are satisfied such that those cut accessory equipment are not electrically powered; and
[0196] uncut accessory equipment, which are accessory equipment whose cut-off conditions are not satisfied such that those uncut accessory equipment are not electrically powered.
[0197] For user accessory equipment 94, cut accessory equipment are accessory equipment for which a «non-essential» classification has been selected, and uncut accessory equipment are accessory equipment for which an «essential» classification has been selected.
[0198] Thus, with reference to
[0199] In a first situation, if at least one cut-off condition is not satisfied, then a step E4-1, or «ALLOCATION PMAX» step, is executed during which the available maximum power PMAX is allocated over the actuation equipment 91, 92 (which are here the mounting equipment 91) and on the uncut accessory equipment, so that this/these mounting equipment 91 receive an actuation power PACT which is equivalent to the available maximum power PMAX minus the accessory power PACC, namely PACT=PMAX−PACC. This step E4-1 is followed by a step E4-3, or «ALLOCATION PACT» step, during which the actuation power PACT is allocated over the mounting equipment 91, so that each mounting equipment 91 receives an electrical power which is less than or equal to this actuation power PACT. If only one mounting equipment 91 is involved (for example the hydraulic folding/unfolding unit) then all the actuation power PACT is allocated to this single mounting equipment 91.
[0200] In a second situation, if on the other hand all the cut-off conditions are satisfied, then a step E4-2 is executed, or «ALLOCATION PMAX» step, during which the available maximum power PMAX is allocated only to the actuation equipment 91, 92 (which here are the mounting equipment), so that this/these mounting equipment 91 receive an actuation power PACT which is equivalent to the available maximum power PMAX, namely PACT=PMAX. This step E4-2 is followed by a step E4-4, or «ALLOCATION PACT» step, during which the actuation power PACT is allocated over the mounting equipment 91, so that each mounting equipment 91 receives an electrical power which is less than or equal to this available maximum power PMAX. If only one mounting equipment 91 is involved, then all the available maximum power PMAX is allocated to this single mounting equipment 91.
[0201] In the same way, if during the configuration selection step T2, the working configuration is selected, then a step of verifying the cut-off conditions T5 is executed, or the «CUT-OFF VERIFICATION» step, in which the cut-off conditions of different accessory equipment 93, 94 are controlled, which leads to two situations.
[0202] In a first situation, if at least one cut-off condition is not satisfied, then a step E5-1, or «ALLOCATION PMAX» step, is executed during which the available maximum power PMAX is allocated over the actuation equipment 91, 92 (which here are the working equipment 92) and on the uncut accessory equipment, so that this/these working equipment 92 receive an actuation power PACT which is equivalent to the available maximum power PMAX minus the accessory power PACC, namely PACT=PMAX−PACC.
[0203] In a second situation, if however, all the cut-off conditions are satisfied, then a step E5-2 is executed, or the «ALLOCATION PMAX» step, during which the available maximum power PMAX is allocated only to the actuation equipment 91, 92 (which here are the working equipment 92), so that this/these working equipment 92 receive an actuation power PACT which is equivalent to the available maximum power PMAX, namely PACT=PMAX.
[0204] The step E5-1 is followed by a step of selecting a scheme T6, or «SCHEME SELECTION» step, and similarly step E5-1 is followed by a step of selecting a scheme T7, or «SCHEME SELECTION» step.
[0205] The scheme selection step T6 or T7 is a step during which a selection of an allocation scheme for an allocation of the actuation power PACT over the different working equipment 92 is made, amongst the following two allocation schemes:
[0206] a first scheme SCH1 in which the working equipment 92 are sequentially activated and therefore sequentially powered (that is to say one after the other, in a non-combined manner), so that each working equipment 92 is powered, when activated, by the actuation power PACT; and
[0207] a second scheme SCH2 in which the working equipment 92 are simultaneously activated and therefore simultaneously powered (that is to say one at the same time as the other, in a combined manner), so that all the working equipment 92 are powered together by the actuation power PACT.
[0208] Thus, if the first scheme SCH1 is selected during the scheme selection step T6, then a step E6-1, or «ALLOCATION PACT» step, is executed during which the actuation power PACT (with the reminder PACT=PMAX−PACC) is integrally and sequentially allocated to each working equipment 92 when activated, so that each working equipment 92 receives, when activated, an electrical power which is less than or equal to this actuation power PACT. On the other hand, if the second scheme SCH2 is selected during the scheme selection step T6, then a step E6-2, or «ALLOCATION PACT» step, is executed during which the actuation power PACT (with reminder PACT=PMAX−PACC) is allocated over the different working equipment 92 which are activated (and therefore require energy) in a combined manner.
[0209] Similarly, if the first scheme SCH1 is selected during the scheme selection step T7, then a step E7-1, or «ALLOCATION PACT» step, is executed during which the actuation power PACT (with reminder PACT=PMAX) is integrally and sequentially allocated to each working equipment 92 when activated, so that each working equipment 92 receives, when activated, an electrical power which is less than or equal to this actuation power PACT. On the other hand, if the second scheme SCH2 is selected during the scheme selection step T7, then a step E7-2, or «ALLOCATION PACT» step, is executed during which the actuation power PACT (with reminder PACT=PMAX) is allocated over the different working equipment 92 which are activated (and therefore require energy) in a combined manner.
[0210] According to one possibility, a storage in a memory of a plurality of preferential allocation modes is implemented, each preferential allocation mode being associated with percentages of allocation of the actuation power PACT over the different working equipment 92 in the second scheme, with for example an allocation as follows:
PACT=PLIFT+PDIS+PORIEN,
[0211] with PLIFT=q1.Math.PACT, PDIS=q2.Math.PACT et PORIEN=q3.Math.PACT;
[0212] wherein q1, q2 and q3 are allocation quantities or percentages, with q1+q2+q3=1.
[0213] Each preferential allocation mode is thus associated with different allocation quantities or percentages q1, q2 and q3. These allocation modes are implemented if the actuation power PACT is less than the sum of the powers requested by the working equipment 92. Indeed, if the actuation power PACT is greater than or equal to the sum of the powers requested by the working equipment 92, then all the working equipment 92 can be powered to their full power.
[0214] Also, the allocation method «POWER ALLOCATION» can implement a step for selecting an allocation mode, or «ALLOCATION MODE SELECTION» step, so that the step E6-2 or the step E7-2 executes an allocation of the actuation power PACT to the different working equipment 92 in accordance with the selected preferential allocation mode.
[0215] The rest of the description concerns the crane CR which comprises the electrical equipment 9 electrically powered, via the conversion circuit Q presented in
[0216] This crane CR comprises:
[0217] a monitoring unit M to monitor the requested general power RGPOW which corresponds as a reminder to the power requested by all the electrical equipment 9 and to monitor the charge level CL of the rechargeable secondary power supply source SEC, and
[0218] the control/command unit CC connected to the monitoring unit M and to the conversion circuit Q, and configured to implement the management method «POWER MANAGEMENT» of
[0219] There may be a recharging electrical interface 22 between the primary power supply source PRIM and the rechargeable secondary power supply source SEC intended to adapt the voltage provided by the primary power supply source PRIM to a recharging voltage of the rechargeable secondary power supply source SEC. The electrical recharging interface 22 makes it possible to recharge the rechargeable secondary power supply source SEC when the primary power supply source PRIM is connected and the electrical power consumption of the crane CR is lower than the primary power PRPOW provided by the primary power supply source PRIM.
[0220] The control/command unit CC is also configured for the implementation of the allocation method «POWER ALLOCATION» of
[0221] Also, this control/command unit CC is connected, on the one hand, to a user interface INT allowing a selection between the raw mode RAWMOD and the optimized mode OPTMOD and, on the other hand, to an electrical circuit connecting the at least one power supply source to the electrical equipment 9 to control an allocation of the available maximum power PMAX according to the mode selected among the raw mode RAWMOD and the optimized mode OPTMOD.
[0222] According to one possibility, the primary power supply source PRIM delivers a primary power supply voltage of the single-phase or three-phase type, for example 230 or 400 volts, and the conversion circuit Q ensures a conversion of said primary power supply voltage into a three-phase power supply voltage. The three-phase power supply voltage can be obtained by assembling three single-phase converters coupled or synchronized together to generate a three-phase power supply voltage.
[0223] The monitoring unit M can be a microcontroller and the conversion circuit Q can be an electrical converter AC/AC comprising a rectifier RECT and an inverter INV as shown in
[0224] According to one embodiment, the monitoring unit M selects the power supply source among the primary power supply source PRIM and the rechargeable secondary power supply source SEC thanks to a switching on or off electrical switches 10, 11, 12. The electrical switches 10, 11, 12 presented in
[0225] If the switch 10 is off, then the transfer of power from the primary power supply source PRIM to the electrical equipment 9 of the crane CR is activated. If the switch 11 is off, then the transfer of power from the primary power supply source PRIM to the rechargeable secondary power supply source SEC is activated, in other words the rechargeable secondary power supply source SEC is recharged. If the switch 12 is off, then the transfer of power from the rechargeable secondary power supply source SEC to the electrical equipment 9 of the crane CR is activated.
[0226] The conversion circuit Q can also comprise at least one frequency converter not represented in
[0227] The crane CR further comprises the user interface INT connected to the control-command unit CC to:
[0228] select the management sub-mode among the previously described management sub-modes which are the automatic sub-mode «AUTO», the economical sub-mode «ECO» and the extreme sub-mode «EXTR«,
[0229] select between the raw mode «RAWMOD» and the optimized mode «OPTMOD»,
[0230] select the classification of user accessory equipment 94 from the «mon-essential» classification and the «essential» classification;
[0231] select the allocation scheme among the first scheme SCH1 and the second scheme SCH2;
[0232] select a preferential allocation mode among the preferential allocation modes stored in the memory.
[0233] The control-command unit CC can be connected to the monitoring unit M by a communication bus 15 so that the control-command unit CC can permanently receive information on electrical quantities from the monitoring unit M such as an input voltage of the rectifier RECT or even an output voltage of the inverter INV, so that the control-command unit CC can adjust parameters of the conversion circuit Q such as turning on or off the electrical switches 10, 11, 12 for example.
[0234] The control-command unit CC can further receive from the monitoring unit M the power supply mode implemented by the power supply management method «POWER MANAGEMENT» or else a value of the primary power supply voltage.
[0235] The control-command unit CC can transfer to the monitoring unit M the primary power PRPOW entered by a user in the user interface INT and which can be used by the monitoring unit M for calculating the available maximum power PMAX.
[0236] Furthermore, according to one embodiment, the control-command unit CC is capable of finding the power supply mode implemented by the power supply management method «POWER MANAGEMENT» on the basis of the state of the electrical switches 10, 11, 12 or on the basis of a value of the primary voltage sent by the monitoring unit M via the communication bus 15.
[0237] According to one possibility, the control-command unit CC first calculates the available maximum power PMAX according to the power supply source(s) providing the electrical power, as well as the implemented power supply mode, then the control-command unit CC manages the allocation of the available maximum power PMAX over the different electrical equipment 9 of the crane CR.
[0238] According to one possibility, a user of the crane CR, for example a pilot of the crane CR, informs the primary power PRPOW, the management sub-mode and one or more preferential allocation modes.
[0239] According to one possibility, the control-command unit CC indicates to the user of the crane CR via the user interface INT the charge level CL of the rechargeable secondary power supply source SEC, the implemented power supply mode and a standby information if the system switches to a standby mode.
[0240] The charge level CL of the rechargeable secondary power supply source SEC is estimated by the control-command unit CC from, for example, a recharging and discharging current of the rechargeable secondary power supply source SEC, thus, the control-command unit CC can for example know the capacity of the battery in Ah or Wh. A calibration can be performed when the rechargeable secondary power supply source SEC is fully charged.