Construction method for upright lifting of large-tonnage box girder to bridge, and erection method for large-tonnage box girder
11391004 ยท 2022-07-19
Assignee
- China Railway No. 2 Engineering Group Co. LTD. (Chengdu, CN)
- Xinyun Engineering Company of China Railway No. 2 Engineering Group, Co., LTD. (Chengdu, CN)
Inventors
- Yusen YE (Chengdu, CN)
- Jiannan CHEN (Chengdu, CN)
- Chuanwei PAN (Chengdu, CN)
- Guohui LIN (Chengdu, CN)
- Mengqiang CHEN (Chengdu, CN)
- Shilong LI (Chengdu, CN)
- Chao Li (Chengdu, CN)
- Qiang Wang (Chengdu, CN)
- Jianjun CHEN (Chengdu, CN)
- Da LI (Chengdu, CN)
- Haoxian TANG (Chengdu, CN)
Cpc classification
B66C19/00
PERFORMING OPERATIONS; TRANSPORTING
E01D21/06
FIXED CONSTRUCTIONS
International classification
E01D21/00
FIXED CONSTRUCTIONS
E01D21/06
FIXED CONSTRUCTIONS
Abstract
A construction method for the upright lifting of a large-tonnage box girder to a bridge, and an erection method for the large-tonnage box girder. The construction method comprises: constructing a lifting station (2) at reserved bridge piers (1); disposing a girder lifting base (3), lifter traveling rails (4), and a mounting lifter (6) in the lifting station (2); directly erecting a box girder (7) by the lifter (6) in a way that the lifter (6) travels to a position above the base (3) and erects the box girder (7). The erection method further comprises: lifting by the lifter (6) a single set of transport and erection apparatuses or two sets of transport and erection apparatuses to a bridge, a girder transport vehicle (9) cooperating with a bridge erecting machine (10) to repeatedly complete the erection of the box girder (7); hoisting by the lifter (6) the transport and erection apparatus off the bridge; lifting by the lifter (6) the box girder (7) within the scope of the reserved bridge pier (1) to the erected box girder (7); and constructing the reserved bridge piers (1); completing by the lifter (6) the erection of the box girder (7) within the scope of the reserved bridge piers (1). The construction and erection methods for the box girder occupy a small space and have high efficiency.
Claims
1. A construction method for a large-tonnage box girder, comprising the following steps: S1: constructing a lifting station; reserving a plurality of bridge piers on a bridge line for temporary non-construction, constructing a lifting station at reserved bridge piers, arranging a plurality of girder lifting bases in the lifting station, and constructing lifter traveling rails and installing lifters on both sides of the bridge piers along the longitudinal center lines of the bridge piers; S2: directly erecting a box girder by the lifter; S21: transporting a box girder to be erected to the girder lifting base for storage; S22: causing the lifter to travel directly above the girder lifting base and lifting the box girder to be erected to the height of the bridge floor; S23: longitudinally moving the lifter to a position of the bridge span to be erected and erecting the box girder to be erected; S24: repeating the steps S21 to S23, erecting a next box girder to be erected until the total size of the box girders directly erected by the lifter is larger than the external size of the transport and erection apparatus; S3: lifting by the lifter the transport and erection apparatus to the bridge; S31: transporting by a girder transport vehicle a bridge erecting machine to a lifting station; S32: respectively lifting by the lifter the bridge erecting machine and the girder transport vehicle to the bridge, and placing the box girder erected in the step S2; S4: lifting by the lifter the box girder to the bridge; S41: transporting by a transporter the box girder to be erected to the girder lifting base for storage; S42: causing the lifter to travel directly above the girder lifting base and lifting the box girder to be erected to the height of the vehicle loading; S43: longitudinally moving the lifter to be directly above the girder transport vehicle, and placing the box girder to be erected on the girder transport vehicle; S5: causing the girder transport vehicle to cooperate with the bridge erecting machine to complete the erection of the box girder; longitudinally moving the bridge erecting machine to a position of the bridge span to be erected, transporting by the girder transport vehicle the box girder to be erected to the bridge erecting machine, and causing the girder transport vehicle to cooperate with the bridge erecting machine to complete the erection of the box girder; S6: repeating the steps S4 to S5, and erecting the next box girder to be erected until the erection of all the box girders in the same direction is completed; S7: hoisting by the lifter the transport and erection apparatus off the bridge; S71: transporting by the girder transport vehicle the bridge erecting machine to the box girder near the lifting station; S72: respectively hoisting by the lifter the bridge erecting machine and the girder transport vehicle off the bridge; S8: turning the bridge erecting machine and the girder transport vehicle under the bridge; S9: repeating the steps S2-S7, completing the erection of all box girders in the other direction, and hoisting the transport and erection apparatus off the bridge; S10: lifting by the lifter all the box girders to be erected in the range of the reserved bridge piers to the bridge, and simultaneously placing the box girders to be erected on the erected box girders; S11: constructing the reserved bridge piers; S12: directly erecting by the lifter the box girders to be erected within the range of the reserved bridge piers to a position of the bridge span to be erected, thereby completing the erection construction of the large-tonnage box girders for the whole bridge.
2. The method according to claim 1, wherein: in the step S2, erecting by the lifter the box girders in both directions of the bridge, wherein a plurality of box girders are arranged on both sides of the lifting station, and the total size of the box girders directly erected by the lifter in each direction is larger than the external size of the transport and erection apparatus; in the step S3, lifting by the lifter two sets of transport and erection apparatuses to the box girders in both directions; in the step S4, respectively placing the box girders lifted by the lifter on two girder transport vehicles in different directions; in the step S5, causing the girder transport vehicle in each direction to cooperate with the corresponding bridge erecting machine to complete box girder erection; in the step S6, repeating the steps S4 to S5, and erecting the next box girder to be erected until the erection of all the box girders in the both directions is completed; and in the step S7, hoisting by the two sets of transport and erection apparatuses off the bridge, wherein the steps S8 and S9 are omitted.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15) Reference numerals: 1-bridge pier, 2-lifting station, 3-girder lifting base, 4-lifter traveling rail, 5-transporter channel, 6-lifter, 7-box girder to be erected, 8-erected box girder, 9-girder transport vehicle, and 10-bridge erecting machine.
DETAILED DESCRIPTION
(16) The present invention will now be described in further detail with reference to experimental examples and specific embodiments. However, it should not be understood that the scope of the above-described subject matter of the present invention is limited to the following embodiments, and the technology implemented based on the disclosure is within the scope of the present invention.
Embodiment 1
(17) As shown in
(18) S1: Constructing a Lifting Station 2;
(19) As shown in
(20) S2: directly erecting a box girder by the lifter 6;
(21) S21: transporting by a transporter the box girder 7 to be erected to the girder lifting base 3 for storage, as shown in
(22) S22: causing the lifter 6 to travel directly above the girder lifting base 3 and lifting the box girder 7 to be erected to the height of the bridge floor, as shown in
(23) S23: longitudinally moving the lifter 6 to a position of the bridge span to be erected and erecting the box girder 7 to be erected, as shown in
Embodiment 2
(24) As shown in
(25) S24: repeating the steps S21 to S23, erecting a next box girder 7 to be erected in the same direction until the total size of the box girders directly erected by the lifter 6 is larger than the external size of the transport and erection apparatus, wherein the external size of the transport and erection apparatus comprises the length and the width of the bridge erecting machine and the girder transport vehicle.
(26) S3: lifting by the lifter 6 the transport and erection apparatus to the bridge;
(27) S31: transporting by the girder transport vehicle 9 the bridge erecting machine 10 to the lifting station 2, wherein the center line of the girder transport vehicle 9 is adjusted by using a slanted traveling function of the girder transport vehicle 9, so that the center line of the girder transport vehicle 9 and the center line of the bridge line substantially coincide, as shown in
(28) S32: respectively lifting by the lifter 6 the bridge erecting machine 10 and the girder transport vehicle 9 to the bridge, and placing them on the erected box girder 8 in the step S2, as shown in
(29) S4: lifting by the lifter 6 the box girder to the bridge;
(30) S41: transporting by a transporter the box girder 7 to be erected to the girder lifting base 3 for storage, as shown in
(31) S42: causing the lifter 6 to travel directly above the girder lifting base 3 and lifting the box girder 7 to be erected to the height of the vehicle loading;
(32) S43: longitudinally moving the lifter 6 to be directly above the girder transport vehicle, and placing the box girder 7 to be erected on the girder transport vehicle 9, as shown in
Embodiment 3
(33) As shown in
(34) S5: causing the girder transport vehicle 9 to cooperate with the bridge erecting machine 10 to complete the erection of the box girder;
(35) longitudinally moving the bridge erecting machine 10 to a position of the bridge span to be erected, transporting by the girder transport vehicle 9 the box girder to be erected to the bridge erecting machine 10, and causing the girder transport vehicle 9 to cooperate with the bridge erecting machine 10 to complete the erection of the box girder, as shown in
(36) S6: repeating the steps S4 to S5, and erecting the next box girder to be erected until the erection of all the box girders in the same direction is completed;
(37) S7: hoisting by the lifter the transport and erection apparatus off the bridge;
(38) S71: transporting by the girder transport vehicle the bridge erecting machine to the box girder near the lifting station;
(39) S72: respectively hoisting by the lifter the bridge erecting machine and the girder transport vehicle off the bridge;
(40) S8: turning the bridge erecting machine and the girder transport vehicle under the bridge;
(41) S9: repeating the steps S2-S7, completing the erection of all box girders in the other direction, and hoisting the transport and erection apparatus off the bridge;
(42) S10: lifting by the lifter the remaining box girders to be erected (the box girders to be erected in the range of the reserved bridge piers) to the bridge, and simultaneously placing the box girders to be erected on the erected box girders;
(43) S11: constructing the reserved bridge piers;
(44) S12: directly erecting by the lifter the remaining box girders to be erected (the box girders to be erected within the range of the reserved bridge piers) to the bridge span position to a position of the bridge span to be erected, thereby completing the erection construction of the large-tonnage box girders for the whole bridge.
Embodiment 4
(45) As shown in
(46) S1: Constructing a Lifting Station 2;
(47) As shown in
(48) S2: directly erecting a box girder by the lifter 6;
(49) S21: transporting by a transporter the box girder 7 to be erected to the girder lifting base 3 for storage, as shown in
(50) S22: causing the lifter 6 to travel directly above the girder lifting base 3 and lifting the box girder 7 to be erected to the height of the bridge floor, as shown in
(51) S23: longitudinally moving the lifter 6 to a position of the bridge span to be erected and erecting the box girder 7 to be erected, as shown in
(52) S24: repeating the steps S21 to S23, erecting the box girder 7 to be erected in both directions of the bridge, completing erection work of a plurality of box girders on both sides of the lifting station 2 until the total size of the box girders directly erected by the lifter 6 in each direction is larger than the external size of the transport and erection apparatus, wherein the external size of the transport and erection apparatus comprises the length and the width of the bridge erecting machine and the girder transport vehicle.
(53) S3: lifting by the lifter 6 two sets of transport and erection apparatuses to the bridge;
(54) S31: transporting by the girder transport vehicle 9 the bridge erecting machine 10 to the lifting station 2, wherein the center line of the girder transport vehicle 9 is adjusted by using a slanted traveling function of the girder transport vehicle 9, so that the center line of the girder transport vehicle 9 and the center line of the bridge line substantially coincide, as shown in
(55) S32: respectively lifting by the lifter 6 the bridge erecting machine 10 and the girder transport vehicle 9 to the bridge, and placing them on the erected box girder 8 in the step S2, as shown in
(56) S4: lifting by the lifter 6 the box girder to the bridge;
(57) S41: transporting by a transporter the box girder 7 to be erected to the girder lifting base 3 for storage, as shown in
(58) S42: causing the lifter 6 to travel directly above the girder lifting base 3 and lifting the box girder 7 to be erected to the height of the vehicle loading;
(59) S43: longitudinally moving the lifter 6 to be directly above the girder transport vehicle, and placing the box girder 7 to be erected on two girder transport vehicle 9 in different directions, as shown in
(60) S5: causing the girder transport vehicle 9 to cooperate with the bridge erecting machine 10 to complete the erection of the box girder;
(61) longitudinally moving the bridge erecting machine 10 to a position of the bridge span to be erected, transporting by the girder transport vehicle 9 the box girder 1 to be erected to the bridge erecting machine 10, and causing the girder transport vehicle 9 to cooperate with the bridge erecting machine 10 to complete the erection of the box girder, as shown in
(62) S6: repeating the steps S4 to S5, and erecting the next box girder to be erected until the erection of all the box girders in the both directions is completed;
(63) S7: hoisting by the lifter two sets of the transport and erection apparatuses off the bridge;
(64) S71: transporting by the girder transport vehicle the bridge erecting machine to the box girder near the lifting station;
(65) S72: respectively hoisting by the lifter the bridge erecting machine and the girder transport vehicle off the bridge;
(66) S8: lifting by the lifter the remaining box girders to be erected (the box girders to be erected in the range of the reserved bridge piers) to the bridge, and simultaneously placing the box girders to be erected on the erected box girders;
(67) S9: constructing the reserved bridge piers;
(68) S10: directly erecting by the lifter the remaining box girders to be erected (the box girders to be erected within the range of the reserved bridge piers) to the bridge span position to a position of the bridge span to be erected, thereby completing the erection construction of the large-tonnage box girders for the whole bridge.
(69) The above embodiments are used only to describe the invention and do not limit the technical solutions described in the invention. Although the present invention has been described in detail with reference to the above-described embodiments, the present invention is not limited to the above-described embodiments, and thus any modifications or equivalent substitutions may be made thereto; and all changes and modifications that do not depart from the spirit and scope of the invention are intended to be covered by the following claims.