Method and system for manufacturing laminated shaped product
11273511 ยท 2022-03-15
Assignee
Inventors
- Shinji Sato (Hyogo, JP)
- Takeshi Yamada (Hyogo, JP)
- Takemasa Yamasaki (Hyogo, JP)
- Keisuke Okita (Hyogo, JP)
Cpc classification
B23K9/1735
PERFORMING OPERATIONS; TRANSPORTING
B23K9/04
PERFORMING OPERATIONS; TRANSPORTING
B33Y10/00
PERFORMING OPERATIONS; TRANSPORTING
B22F10/28
PERFORMING OPERATIONS; TRANSPORTING
B33Y30/00
PERFORMING OPERATIONS; TRANSPORTING
B22F2203/11
PERFORMING OPERATIONS; TRANSPORTING
B22F10/22
PERFORMING OPERATIONS; TRANSPORTING
B22F2999/00
PERFORMING OPERATIONS; TRANSPORTING
B22F12/90
PERFORMING OPERATIONS; TRANSPORTING
B23K9/042
PERFORMING OPERATIONS; TRANSPORTING
B22F10/22
PERFORMING OPERATIONS; TRANSPORTING
B22F10/28
PERFORMING OPERATIONS; TRANSPORTING
B22F10/25
PERFORMING OPERATIONS; TRANSPORTING
B22F2999/00
PERFORMING OPERATIONS; TRANSPORTING
B22F12/90
PERFORMING OPERATIONS; TRANSPORTING
B33Y50/02
PERFORMING OPERATIONS; TRANSPORTING
B23K9/0956
PERFORMING OPERATIONS; TRANSPORTING
Y02P10/25
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
International classification
B33Y30/00
PERFORMING OPERATIONS; TRANSPORTING
B23K9/04
PERFORMING OPERATIONS; TRANSPORTING
B33Y10/00
PERFORMING OPERATIONS; TRANSPORTING
Abstract
A method for producing an additively manufactured object includes melting and solidifying a filler metal by use of an arc, and depositing and forming a plurality of layers of molten beads to produce a built-up object, and the method includes: shaping the molten bead of a previous layer; and monitoring a temperature of the molten bead of the previous layer. Shaping of the molten bead of a next layer is started when the temperature of the molten bead of the previous layer is equal to or lower than an allowable interpass temperature.
Claims
1. A method for producing an additively manufactured object, comprising melting and solidifying a filler metal by use of an arc, and depositing and forming a plurality of layers of molten beads to produce a built-up object, the method comprising: depositing the molten bead of a previous layer; monitoring a temperature of the molten bead of the previous layer, wherein deposition of the molten bead of a next layer is started when the temperature of the molten bead of the previous layer is equal to or lower than an allowable interpass temperature, and measuring a cooling time until the temperature of the molten bead of the previous layer is cooled down to the allowable interpass temperature from a temperature at a start of deposition, wherein the total of a deposition time of the molten bead per layer and a travel time of a welding torch is set to be not less than the cooling time (tc).
2. The method for producing an additively manufactured object according to claim 1, wherein a deposition time of the molten bead per layer is set to be not less than the cooling time.
3. The method for producing an additively manufactured object according to claim 2, wherein the deposition time of the molten bead per layer is set to be the cooling time.
4. A method for producing an additively manufactured object, comprising melting and solidifying a filler metal by use of an arc, and depositing and forming a plurality of layers of molten beads to produce a built-up object, the method comprising: depositing the molten bead; monitoring a temperature of the molten bead; and measuring a cooling time until the temperature of the molten bead is cooled down to an allowable interpass temperature from a temperature at a start of deposition, wherein the number of welding torches in depositing the molten bead is set to an integer value of a quotient obtained by dividing a deposition time of the molten bead per layer by the cooling time.
5. The method for producing an additively manufactured object according to claim 2, wherein the deposition time of the molten bead per layer is adjusted by changing at least one of current, voltage and welding speed during the depositing while a heat input amount per unit length of the molten bead during the depositing is kept constant.
6. The method for producing an additively manufactured object according to claim 2, wherein the deposition time of the molten bead per layer is adjusted by changing at least one of current, voltage and welding speed during the depositing so that a cross-sectional area of the molten bead during the depositing is kept constant.
7. A system for producing an additively manufactured object, depositing and forming a plurality of layers of molten beads to produce a built-up object, the system comprising: a deposition device configured to melt and solidify a filler metal by use of an arc based on layer profile data representing a profile of each layer obtained by dividing the built-up object into a plurality of mutually parallel layers, and deposit and form a plurality of layers of the molten beads; a temperature sensor configured to measure a temperature of the molten bead every time the molten bead is formed; and a control device configured to control the deposition device so that deposition of the molten bead of a next layer is started when a temperature of the molten bead of a previous layer is equal to or lower than an allowable interpass temperature, and configured to measure a cooling time until the temperature of the molten bead of the previous layer is cooled down to the allowable interpass temperature from a temperature at a start of deposition, wherein the total of a deposition time of the molten bead per layer and a travel time of a welding torch is set to be not less than the cooling time (tc).
8. The method for producing an additively manufactured object according to claim 3, wherein the deposition time of the molten bead per layer is adjusted by changing at least one of current, voltage and welding speed during the depositing while a heat input amount per unit length of the molten bead during the depositing is kept constant.
9. The method for producing an additively manufactured object according to claim 4, wherein the deposition time of the molten bead per layer is adjusted by changing at least one of current, voltage and welding speed during the depositing while a heat input amount per unit length of the molten bead during the depositing is kept constant.
10. The method for producing an additively manufactured object according to claim 3, wherein the deposition time of the molten bead per layer is adjusted by changing at least one of current, voltage and welding speed during the depositing so that a cross-sectional area of the molten bead during the depositing is kept constant.
11. The method for producing an additively manufactured object according to claim 4, wherein the deposition time of the molten bead per layer is adjusted by changing at least one of current, voltage and welding speed during the depositing so that a cross-sectional area of the molten bead during the depositing is kept constant.
Description
BRIEF DESCRIPTION OF DRAWINGS
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
DESCRIPTION OF EMBODIMENTS
(9) The production method and production system for an additively manufactured object according to each embodiment of the present invention are described in detail below based on drawings. The following embodiments are examples embodying the present invention and are not intended to limit the technical scope of the present invention.
First Embodiment
(10) As illustrated, in
(11) Referring also to
(12) The additively manufactured object 11 illustrated in
(13) The welding robot 20 is an articulated robot and includes the welding torch 22 at the tip of a leading arm 21. The leading arm 21 is three-dimensionally movable, and the welding torch 22 can move to any position in any posture by controlling the posture and position of the leading arm 21 by the control device 50.
(14) The welding torch 22 includes a substantially tubular shield nozzle to which a shielding gas is supplied, a contact tip (not shown) disposed inside the shield nozzle, and a filler metal W held in the contact tip and supplied with a melting current. The welding torch 22 generates an arc to melt and solidify the filler metal W while feeding the filler metal W and flowing a shielding gas, and the molten bead 61 is deposited on a substrate 60 to form the additively manufactured object 11. The welding torch 22 may employ a non-consumable electrode with which a filter metal is supplied from the outside.
(15) The temperature sensor 30 measures the temperature of the molten bead 61 deposited just before, and a contact measurement sensor may be used, but since the deposited molten bead 61 is at a high temperature, a non-contact measurement sensor such as thermoviewer or infrared temperature sensor is preferred.
(16) In this embodiment, the temperature sensor 30 measures the temperature at the deposition start position of each layer.
(17) The control device 50 controls the welding robot 20 and the temperature sensor 30 to deposit a plurality of molten beads 61, thereby shaping the additively manufactured object 11.
(18) The CAD/CAM device 51 creates profile data of the additively manufactured object 11 to be formed and then produces layer profile data representing the profile of each of the layers L1 . . . Lk by dividing the object into a plurality of layers (see
(19) The control device 50 controls the movement of the welding robot 20 based on, for example, the layer profile data, the movement track for the welding torch 22, and the interpass temperature Tp, which are stored in the memory 53, as well as the temperature of the molten bead 61 deposited just before, which is measured by the temperature sensor 30. In addition, the control device 50 has a built-in timer 54 for measuring the cooling time tc until the temperature of the molten bead 61 of each layer is cooled down to the allowable interpass temperature Tp from the temperature at the start of shaping.
(20) The procedure for shaping the additively manufactured object 11 by the production system 10 for an additively manufactured object of this embodiment is described in detail below by referring to
(21) First, profile data representing the profile of the additively manufactured object 11 is created by the CAD/CAM device 51, and the input profile data. (CAD data) is divided into a plurality of layers L1 . . . Lk to produce layer profile data representing the profile of each of the layers L1 . . . Lk. The layer profile data representing the profile of each of the layers L1 . . . Lk serves as the movement track of the welding torch 22, i.e., the deposition track of the weld bead 61.
(22) Division of the profile data of the additively manufactured object 11 into a plurality of layers is preferably division in the direction substantially orthogonal to the deposition direction of the molten bead 61. More specifically, in the case of forming the additively manufactured object 11 by depositing the molten bead 61 in the vertical direction, the data is divided in the horizontal direction, and in the case of forming the additively manufactured object 11 by depositing the molten bead 61 in the horizontal direction, the data is divided in the vertical direction.
(23) Subsequently, the track planning unit 52 creates a specific deposition plan for the molten bead 61, such as movement track for the welding torch 22 in each of the layers L1 . . . Lk and planned height of the molten bead 61 when the molten bead 61 of each of the layers L1 . . . Lk is deposited.
(24) As illustrated in
(25) Deposition of the molten bead 61 of a next layer (second layer) is started when the temperature of the molten bead 61 of the previous layer (first layer) becomes equal to or lower than the allowable interpass temperature Tp. According to this configuration, the molten bead 61 of the next layer is prevented from flattening, running down, etc. After that, deposition is repeated for all layers up to the layer Lk in the same manner as above while monitoring the temperature of the previous layer, and the good additively manufactured object 11 can thereby be shaped.
(26)
(27) In Example illustrated in
(28) In addition, when the deposition time tf of the molten bead 61 per layer is set to the cooling time tc, the molten bead 61 can be continuously deposited in the shortest time without temporarily stopping the arc, and the production efficiency is enhanced.
(29) Setting of the deposition time tf of the molten bead 61 per layer may be adjusted by changing at least one of current, voltage and welding speed during the depositing while a heat input amount per unit length of the molten bead during the depositing is kept constant.
(30) Alternatively, setting of the deposition time tf per layer of the molten bead 61 may be adjusted by changing at least one of current, voltage and welding speed during the depositing so that a cross-sectional area of the molten bead during the depositing is kept constant. According to this configuration, stable deposition can be achieved while maintaining high deposition efficiency and ensuring deposition precision.
(31) As described above, according to the production method and production system for additively manufactured object of this embodiment, a molten bead of a previous layer is deposited, and the temperature of the molten bead 61 of the previous layer is monitored by the temperature sensor 30. Deposition of the molten bead of a next layer is started when the temperature of the molten bead 61 of the previous layer falls to be equal to or lower than the allowable interpass temperature Tp. According to this configuration, stable additive manufacturing by an arc can be achieved while ensuring deposition precision.
(32) More specifically, the cooling time tc, which is the time until the temperature of the molten bead 61 of the previous layer is cooled down to the allowable interpass temperature from the temperature at the start of deposition, is measured, and the deposition time tf of the molten bead 61 per layer should be set to be equal to or more than the cooling time tc.
(33) From the viewpoint of enhancing the production efficiency, it is preferable to set the deposition time tf so that the deposition time tf per layer is equal to or more than the cooling time tc and the difference between the deposition time tf per layer and the cooling time tc is small.
(34)
(35) In this case, the deposition time tf of the molten bead 61 per layer may be set to be equal to or more than the cooling time tc, but when the total of the deposition time tf of the molten bead 61 per layer and the travel time of the welding torch 22 is set to be not less than the cooling time tc, the production efficiency can be more enhanced.
(36) In a first modified example of this embodiment, after the same built-up model 11A as the additively manufactured object 11 (see,
(37) More specifically, in the production method for an additively manufactured object as a first modified example, a filler metal is melted and solidified using an arc, and a plurality of layers of molten beads 61 are deposited and formed to create the same built-up model 11A as the built-up object 11. At this time, the temperature of the molten bead 61 of each layer in the built-up model 11A is monitored. Furthermore, each cooling time until the temperature of the molten bead 61 of each layer in the built-up model 11A is cooled down to the allowable interpass temperature from the temperature at the start of deposition is acquired by measurement or calculation. Deposition of the molten bead 61 of a next layer relative to the molten bead 61 of a previous layer in the built-up object 11 is started when the time from the start of deposition of the molten bead 61 of a previous layer in the built-up model 11A becomes equal to or more than the cooling time of the previous layer. Also by such a production method of the first modified example, additive manufacturing by stable arc can be achieved while ensuring deposition precision.
(38) In addition, when the deposition time tf of the molten bead per layer in the built-up object 11 is, similarly to this embodiment, set to the cooling time, the production efficiency can be enhanced.
(39) The deposition time of the molten bead 61 of each layer in forming the built-up model 11A is set to be longer than the deposition time in forming the built-up object 11 so as to unfailingly prevent the built-up model 11A from becoming unstable.
(40) Furthermore, in a second modified example of this embodiment, the cooling time until the temperature of the molten bead of each layer is cooled down to the allowable interpass temperature from the temperature at the start of deposition may be calculated by simulation analysis.
(41) More specifically, the production method for an additively manufactured object as a second modified example includes a step of analyzing the cooling time until the temperature of the molten bead 61 of each layer is cooled down to the allowable interpass temperature from the temperature at the start of deposition, and deposition of the molten bead 61 of a next layer relative to each layer is started when the time from the start of deposition of the molten bead 61 of each layer becomes equal to or more than the cooling time of each layer.
Second Embodiment
(42) The production method and production system for an additively manufactured object according to a second embodiment of the present invention are described in detail below by referring to
(43) In this embodiment, in the case where the deposition time tf of the molten bead 61 per layer to be deposited using one welding torch 22 is very long compared with the cooling time tc, a plurality of molten beads 61 are simultaneously deposited using a plurality of welding torches 22 to enhance the production efficiency.
(44) More specifically, the number of welding torches 22 in depositing the molten bead 61 is set to an integer value of the quotient obtained by dividing the deposition time tf of the molten bead 61 per layer to be deposited using one welding torch 22, by the cooling time tc. For example, as illustrated in
(45) In this embodiment, as for the cooling time tc, a cooling time until the molten bead 61 of a previous layer is cooled to the allowable interpass temperature from the temperature at the start of deposition is measured, and the number of welding torches 22 is determined when the molten bead 61 of a next layer is deposited. However, in the case of manufacturing the same built-up object, cooling times until the molten beads 61 of all layers are cooled to the allowable interpass temperature from the temperature at the start of deposition may be measured when a first built-up object is manufactured, the longest cooling time may be set as the cooling time tc, and the number of welding torches 22 in manufacturing second and subsequent built-up objects may be set based on the cooling time tc.
(46) Other configurations and actions are the same as those of the first embodiment.
(47) The present invention is not limited to the above-described embodiments, and modifications, improvements, etc. can be appropriately made therein.
(48) For example, the temperature sensor 30 may be configured to monitor the temperature at the deposition start position of each layer, and in the case where the cooling time until the temperature of the measured molten bead 61 reaches the allowable interpass temperature is predictable in advance, deposition of the molten bead of a next layer may be started based on the predicted cooling time tc.
(49) In addition, the temperature of the molten bead 61 may be monitored at a plurality of sites and in this case, it is preferred that at each monitoring site, the temperature is equal to or lower than the allowable interpass temperature when the molten bead of a next layer is deposited.
(50) This application is based on Japanese Patent Application No. 2017-061063 filed on Mar. 27, 2017, the entire subject matter of which is incorporated herein by reference.
REFERENCE SIGNS LIST
(51) 10 Production system for additively manufactured object 11 Additively manufactured object (built-up object) 11A Built-up model 20 Welding robot (deposition device) 30 Temperature sensor 50 Control device 61 Molten bead L1 . . . Lk Layer tc Cooling time tf Deposition time of molten bead per layer Tp Interpass temperature