METHOD FOR STRENGTHENING AND LIFTING HIGH-RISE BUILDING HAVING RAFT FOUNDATION
20220098819 · 2022-03-31
Inventors
Cpc classification
E02D3/12
FIXED CONSTRUCTIONS
E02D35/00
FIXED CONSTRUCTIONS
International classification
Abstract
Disclosed is a method for strengthening and lifting a high-rise building that has a raft foundation, comprising: arranging a plurality of measuring points at intervals around the outer contour of a building, and determining the side to be lifted of the building according to the elevation of the measuring points; distributing a plurality of reinforcement grouting holes perpendicular to a raft foundation at intervals within the range of the raft foundation, and using pressure grouting in the reinforcement grouting holes to form a reinforcement under the raft foundation; laying downwardly inclined lifting holes on the outer side of the raft foundation at two ends close to the side to be lifted of the building; and performing simultaneous pressure grouting in the lifting holes to lift the side to be lifted of the building.
Claims
1. A method for strengthening and lifting a high-rise building having a raft foundation, comprising: S1, arranging measuring points: a bottom of the building comprising a raft foundation, arranging a plurality of measuring points at intervals around an outer wall of the building, and determining one side where two points with larger settlement volumes in four corners of the building are located as a side to be lifted according to elevations of the measuring points; S2, forming a reinforcement: arranging a plurality of reinforcement grouting holes perpendicular to the raft foundation at intervals within a range of the raft foundation, and performing pressure grouting in the reinforcement grouting holes to form a continuous and complete reinforcement greater than a thickness of the raft under the raft foundation; S3, arranging lifting holes: arranging vertical lifting holes on the raft foundation tightly close to a load bearing wall at a position close to two ends of the load bearing wall on the side to be lifted of the building, wherein the vertical lifting holes penetrates through the raft foundation, and bottoms of the holes extends to a position close to a bottom of the reinforcement; or arranging downwardly inclined lifting holes on an outer side of the raft foundation, wherein the bottom of the holes extends to a position close to the bottom of the reinforcement and is located directly below the load bearing wall; S4, lifting: performing pressure grouting in the lifting holes simultaneously to lift the side to be lifted of the building, and during the lifting, controlling a lifting speed of two corners of the building of the side to be lifted such that elevations of the two corners is finally lifted simultaneously to a same height as the elevation of corresponding corners of a side not to be lifted of the building; and S5, forming a reinforced pile foundation: drilling a plurality of pile foundation holes on the raft foundation, wherein a drill rod extends from the pile foundation holes into a soil layer below the bottom of the reinforcement, and in a drilling and/or retreating procedure, performing pressure grouting segment by segment and layer by layer to form a continuous reinforced pile foundation; and wherein the reinforced pile foundation and the reinforcement are combined to form a pile plate reinforced structure for supporting the raft foundation and the building thereon together.
2. The method for strengthening and lifting a high-rise building having a raft foundation according to claim 1, wherein the drill rod repeatedly drills and retreats in the pile foundation hole for grouting, pressure grouting is performed twice in each segment of the soil layer; a first pressure grouting is filling grouting, and an irregular grouting body is formed around the drill rod after the filling grouting; a second pressure grouting is performed inside the irregular grouting body formed by the filling grouting, in the second pressure grouting, grout uniformly diffuses to a periphery and uniformly mixes with soil body to form a short cylinder with a center of a horizontal section coinciding with a center of the drill rod; all upper and lower continuous short cylinders form a reinforced composite pile foundation, and the reinforced composite pile foundation and the reinforcement are combined to form a pile plate reinforced structure for supporting the raft foundation and the building thereon together.
3. The method for strengthening and lifting a high-rise building having a raft foundation according to claim 2, wherein, in S5, the drill rod of a drilling and grouting machine drilling to a design depth at one time to perform filling grouting, wherein after the grouting reaches a certain grouting pressure and stabilizes, or after an injection rate of the grout satisfies a design requirement, the injected grout fills a relatively less compact area of the soil body around the drill rod, and solidifies within 10 s-60 s, to form the irregular grouting body; the drill rod retreating upward by a retreating length of L and stopping the retreating, and performing filling grouting continually, wherein after the grouting reaches a certain grouting pressure and stabilizes, or after the injection rate of the grout satisfies the design requirement, stopping the grouting to form the irregular grouting body; the drill rod drilling downward again by an advancing length of a half of the retreating length L, then stopping the drilling and performing pressure grouting; in the range of the irregular grouting body, the grout uniformly diffuses to the periphery, after the grouting reaches a certain pressure and stabilizes, or after the injection rate of the grout satisfies the design requirement, the grout uniformly mixes with the surrounding soil body and solidifies to form the short cylinder with a certain strength, and the center of the horizontal section of the short cylinder coincides with the center of a grouting pipe; repeating the drilling, the retreating and the grouting until the bottom of the reinforcement is reached.
4. The method for strengthening and lifting a high-rise building having a raft foundation according to claim 2, wherein, in S5, the drill rod drilling to a length L below the bottom of the reinforcement and performing filling grouting, and after the grouting reaches a certain grouting pressure and stabilizes, or after the injection rate of the grout satisfies the design requirement, stopping the grouting; the injected grout fills soil voids and through gap channels surrounding the drill rod or fills a relatively less compact area of the soil body surrounding the drill rod, and solidifies within 10 s-60 s; the grout solidifies to form a tree-root-like grouting body or the irregular grouting body; the drill rod retreating upwards by a retreating length of a half of a drilling length L, then stopping the retreating and performing pressure grouting; in a range of the tree-root-like grouting body or the irregular grouting body, the grout uniformly diffuses to the periphery, after the grouting reaches a certain pressure and stabilizes, or after the injection rate of the grout satisfies the design requirement, the grout uniformly mixes with the surrounding soil body and solidifies to form the short cylinder with a certain strength, and the center of the horizontal section of the short cylinder coincides with the center of a grouting pipe; repeating the drilling, the retreating and the grouting until the design depth is reached; pulling out the drill rod upwards and during the pulling out and injecting the grout meanwhile to fill the drilling holes tightly.
5. The method for strengthening and lifting a high-rise building having a raft foundation according to claim 1, wherein, in S5, during the filling grouting and the pressure grouting, a pressure value between 0-20 m is 0.5 MPa-2.5 MPa, a pressure value between 20 m-30 m is 2.5 MPa-3.5 MPa, a pressure value between 30 m-40 m is 3.5 MPa-4.5 MPa, and a pressure value between 40 m-50 m is 4.5 MPa-5.5 MPa.
6. The method for strengthening and lifting a high-rise building having a raft foundation according to claim 1, wherein, a secondary grouting is performed in the reinforcement, and between a top surface of the reinforced pile foundation and a bottom surface of the raft foundation so that a top end of the reinforced pile foundation extends to the bottom surface of the raft foundation.
7. The method for strengthening and lifting a high-rise building having a raft foundation according to claim 1, further comprising: S4-1, filling and reinforcing: arranging a reinforcing hole in a middle position of the raft foundation, wherein a bottom of the reinforcing hole extends to a joint surface of the raft foundation and the reinforcement; performing grouting at a bottom end of the reinforcing hole to fill all voids between the bottom surface of the raft foundation and the top surface of the reinforcement tightly.
8. The method for strengthening and lifting a high-rise building having a raft foundation according to claim 1, wherein, a plurality of densification lifting holes are arranged at intervals between original lifting holes along a length direction of a wall body on the side to be lifted; pressure grouting is performed in all the lifting holes at the same time to lift the side to be lifted of the building, and when lifting, a lifting speed of the load bearing wall of the building at each lifting point is controlled so that each point of the side to be lifted of the building is uniformly lifted, until each point of the side to be lifted is lifted simultaneously to a same height as an elevation of a corresponding position of the side not to be lifted of the building.
9. The method for strengthening and lifting a high-rise building having a raft foundation according to claim 1, wherein, in S3, the lifting holes are arranged on an outer side of the raft foundation, two lifting holes are correspondingly arranged at each building corner of the side to be lifted, and the two lifting holes are respectively located on outer sides of two outer contour lines perpendicular to each other of the raft foundation; bottoms of the two lifting holes respectively extend directly below two load bearing walls that are perpendicular to each other.
10. The method for strengthening and lifting a high-rise building having a raft foundation according to claim 1, wherein, in S4, during the lifting, an intermittent grouting lifting is adopted, in which the grouting is firstly performed for lifting by a certain height, the grouting is suspended for a period of time, and then the grouting is performed for lifting by a certain height.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0041]
[0042]
[0043]
[0044]
[0045]
[0046]
[0047]
[0048]
[0049]
[0050]
[0051]
[0052]
[0053]
[0054]
[0055]
[0056]
[0057]
[0058]
[0059]
[0060]
DETAILED DESCRIPTION
[0061] The present application will be described below in further detail with reference to the accompanying drawings.
[0062] With reference to
[0063] S1, arranging measuring points: uniformly arranging a plurality of measuring points at intervals around the outer contour of a building, measuring the elevation of each measuring point by using a level gauge, and determining that one side where two points with large settlement volumes in four corners of the building are located is a side to be lifted according to the elevation of the measuring point.
[0064] S2, forming a reinforcement 3: with reference to
[0065] As shown in
[0066] Referring back to
[0067] Then, lifting grouting is performed in segments with a grouting pressure of 0.8-1.5 MPa. Each time when one segment is lifted, the grouting is performed on one segment. The lifting is 0.3-0.5 m at each time, up to the bottom of the raft foundation. The grouting is then performed by adopting a hole-jumping method. After all the reinforcement grouting holes 31 have been grouted, a continuous and complete reinforcement 3 is formed at the bottom of the raft foundation.
[0068] S3, arranging lifting hole 4: with reference to
[0069] The depth of the lifting hole 4 should be 5-10 times of the thickness of the raft foundation 1 to ensure that there is sufficient buffer zone between the grout outlet and the bottom of the raft foundation 1 to avoid damage to the raft foundation 1; at the same time, grouting and lifting effect can be considered and material waste can be avoided. Since the thickness of the raft foundation 1 has a certain linear relationship with the height of the building, the higher the building is, the thicker the thickness of the raft foundation 1 is, and likewise, the higher the building is, the greater the force required for lifting and the greater the thickness of the buffer zone is required. So the thickness of the raft foundation 1 is selected as the basic parameter for setting the depth of the lifting hole 4.
[0070] S4, lifting: according to many field lifting experiences, in the process of actually building lifting, if only one corner point of the building is lifted during lifting, it will cause the side not to be lifted of the building to be lifted jointly. As shown in
[0071] When lifting, pressure grouting is simultaneously performed into the lifting hole 4 at the side to be lifted of the controlled building, the grout adopted by pressure grouting is a two-component grout, grouts of different components are pressed into the soil body at the grout outlet at the bottom of the grouting pipe or drill rod and converge to react and solidify, the initial setting time is 5-60 s, and the grouting pressure is 1.2-2.5 Mpa. At this time, taking the side not to be lifted as the rotation axis for the side to be lifted, the side to be lifted of the building is slowly lifted to avoid the side not to be lifted being jointly lifted. During the lifting, the elevation data of each measuring point of the building is collected by adopting a level gauge and real-time monitoring is performed. The lifting speed of the two corners of the building on the side to be lifted is controlled by adjusting the grouting pressure and the concentration of the grout so that the two corners are lifted at a constant speed, and are finally, simultaneously lifted to the same height as the elevation of the corresponding corners on the side not to be lifted of the building. In the grouting procedure, the lifting speed is controlled so that the two corners reach the final elevation at the same time. This technical measure prevents the corner on the side not to be lifted from being lifted jointly when grouting is continued on the other corner while one corner stops.
[0072] Further, intermittent grouting and lifting is adopted during grouting lifting. Firstly the grouting lifting is performed for a certain height, the grouting is suspended for a certain time, and then the grouting lifting is performed for a certain height. Each lifting is generally 1 cm, and the suspending time is generally 12-24 h. The intermittent grouting lifting first lifts the building and then suspends to redistribute the stress in the building. After the building is adapted to the stress after lifting, the grouting lifting is performed for a certain height to avoid secondary damage to the building during lifting and ensure the structural stability of the building.
[0073] Referring back to
[0074] After the lifting is completed, corner 11 and corner 14 of the building have the same elevation and corner 12 and corner 13 have the same elevation. At this time, if the elevation difference between corner 11 and corner 13 is not large, for example, less than 2 cm, the lifting may not be performed; if there is a large difference in the elevation between the two, for example, more than 5 cm, it can be determined whether to perform the lifting again according to the actual situation. If the lifting is to be continued, the edge where corner 12 and corner 13 are located is defined as the side to be lifted, and then steps S3 and S4 are repeated, and finally, the four corner points (namely, all the elevations of the raft foundation 1) are lifted to a uniform elevation to be substantially flush.
[0075] S5, reinforcing: in conjunction with
[0076] S6, forming a reinforced pile foundation: as shown in
[0077] Both the integrally advancing grouting and integrally retreating grouting can be used in the construction of reinforced pile foundation in ordinary foundation and stratum. However, when the foundation is a special stratum such as volcanic ash, collapsible loess, and miscellaneous fill, etc., adopting the conventional grouting process cannot form a completely and effectively supporting reinforced pile foundation due to the lack of geological compactness or the existence of void channel. At this time, it is necessary to adopt the process of repeatedly recycling drilling and retreating to form a reinforced composite pile foundation 6. The specific construction steps of strengthening the composite pile foundation 6 are introduced in combination with the conditions of the volcanic ash stratum.
[0078] In step S6-1, in conjunction with
[0079] Step S6-2, as shown in
[0080] Step S6-3, after drilling to the design depth, filling grouting is performed; as shown in
[0081] step S6-4, as shown in
[0082] step S6-5, as shown in
[0083] step S6-6, referring to
[0084] As shown in
[0085] Preferably, before the integrally grouting strengthening operation, grouting parameter tests of the reinforced composite pile foundation 6 are conducted within the range of the house, and test pile construction is performed according to the pressure and other parameters disclosed above; after the test pile is completed, the geological drilling rig is adopted to drill a hole and take out the core at the center radius of 3 m of the reinforced composite pile foundation 6, and then it is observed whether the core sample is continuous reinforcement with good strength instead of ordinary soil body. The above parameters are mainly used to strengthen the foundation below the raft foundation 1 of the high-rise building. When the test is performed according to the above parameters outside the range of the raft foundation 1 of the site of the engineering project, the diameter of the grout diffusion increases to 6 m, which is completely different from the effective radius of the reinforced composite pile foundation 6 formed by grouting inside the range of the raft foundation 1.
[0086] The principle analysis of the construction process for reinforced composite pile foundation 6 is as follows: as shown in
[0087] When the pressure grouting is performed by drilling and inserting downward into the range of the filled grouting body again, since the relatively less compact area around the drill rod 93 has been filled during filling grouting, the grouting will uniformly apply pressure to the soil body around the drill rod 93 so that the grout will uniformly permeate into the void between the surrounding soil body and the volcanic ash, thereby solidifying and forming a short cylinder 61 with a certain strength, and the center of the horizontal section of the short cylinder 61 coincides with the center of the drill rod 93. Pressure grouting is mainly controlled by the injection rate and secondarily controlled by the pressure. When the grouting pressure reaches a design value, but the injection rate is still lower than 50% of the design injection rate, the grouting pressure should be increased appropriately, and the grouting should be continued; when the injection rate reaches more than 70% of the design injection rate, the grouting can be stopped and retreating can be performed. As shown in
[0088] Preferably, a secondary pressure grouting is performed in reinforcement 3 and between the top surface of the reinforced composite pile foundation 6 and the bottom surface of the raft foundation 1 so that the top end of the reinforced composite pile foundation 6 extends to the bottom surface of the raft foundation 1 to form a reinforced structure with better stress bearing.
[0089] S7, hole sealing: after the grouting is completed, all the drilling holes and removed protective layers on the raft foundation 1 are sealed and leveled with cement mortar with the same mark as or one mark higher the mark of the raft foundation 1.
Embodiment 2
[0090] When the foundation of the building is a special stratum such as collapsible loess and miscellaneous fill, the hole drilling and grouting operation adopts the integrally advancing grouting process, but not the integrally retreating grouting. Because the drill rod needs to be drilled to the design depth at one time in the integrally retreating grouting construction, in the procedure of drilling into the design depth, the water ejected from the drill bit part will soften the surrounding soil body, resulting in the secondary settlement of the building. When the collapsible loess is drilled, although the drilling speed is high and there is not much water flowing out at the drill bit, the collapsible loess will sink once in the water. So it is impossible to use the scheme of one-time drilling into the design depth. When drilling into the miscellaneous fill soil layer, it often encounters backfilled schist and so on. When drilling into the schist, the drilling speed slows down and more water flows out at the drill bit, which will soften the surrounding soil body and cause the secondary settlement of the building. With advancing drilling grouting is adopted, the soil body can be solidified in time by the injected grout to prevent the secondary settlement of the building.
[0091] The embodiment describes in detail how to form reinforcement 3 and a reinforced composite pile foundation 6 in a special stratum such as collapsible loess, miscellaneous fill, and the like.
[0092] Step S2, forming reinforcement 3: the difference from embodiment 1 is that the retreating grouting process is changed to the advancing grouting process. Specifically, when grouting, a drilling and grouting machine is adopted for hole drilling and grouting. A drill rod 93 drills from a reinforcement grouting hole 31 into a certain depth below the bottom of a raft foundation 1, for example, for 1.5 m, and then grouting is started, and after the grouting pressure reaches 0.8 MPa, drilling is continued for 1.5 m and grouting is started; the above operation is repeated repeatedly until drilling into the design depth (at 16 m). Finally, the drill rod 93 is pulled out and the drill hole is simultaneously filled with grout. Other reinforcement grouting holes 31 are then grouted by adopting the hole-jumping method. After all the reinforcement grouting holes 31 are grouted, a continuous and complete reinforcement 3 is formed at the bottom of the raft foundation 1.
[0093] Step S6, forming a reinforced pile foundation 6:
[0094] In step S6-1′, a plurality of pile foundation holes 7 is drilled on the raft foundation 1.
[0095] Step S6-2′, as shown in
[0096] Hereinafter,
[0097] Step S6-3′, as shown in
[0098] Step S6-4′, as shown in
[0099] In step S6-5′, the drill rod 93 is pulled out upward, and meanwhile, the drilling hole is filled and compacted by injecting the grout.
[0100] In step S6-6′, as shown in
[0101] It should be noted that the grouting is performed only once at each depth to form the reinforcement 3, but since the reinforcement 3 forms a whole piece reinforcement at the bottom of the raft foundation 1, the reinforcement 3 mainly bears the stress integrally; the interval between two adjacent piles of the reinforced composite pile foundation 6 is far, so the piles are independently stressed, and the surrounding soil body has a small constraint force on the pile body, so it is necessary to repeatedly advance and retreat to form a pile foundation structure with an effective diameter.
[0102] Preferably, a secondary pressure grouting is performed in the reinforcement 3 and between the top surface of the reinforced composite pile foundation 6 and the bottom surface of the raft foundation 1 so that the top end of the reinforced composite pile foundation 6 extends to the bottom surface of the raft foundation 1 to form a reinforced structure with better stress bearing.
Embodiment 3
[0103] In embodiment 1, the lifting hole 4 is provided on the outer side of the raft foundation 1, avoiding the hole drilling of the raft foundation 1, protecting the raft foundation 1 from damage, and drilling without the need to adopt special tools such as water drill, thereby improving the working efficiency. However, sometimes there is insufficient operating space at the periphery of the building, and in this case, as shown in
[0104] A rebar protective layer on the surface of the raft foundation 1 is broken at the lifting hole 4 to expose the raft rebar. A water drill is used to drill downward between the rebar gaps of the raft foundation 1 to form a reinforcement grouting hole 31.
[0105] There are two reasons for using the vertical drilling hole in the scheme. One is that raft foundation 1 is provided therein with a rebar mesh close to the upper surface and the lower surface. When inclined hole drilling is performed, the probability of drilling onto the rebar is very high. The construction schedule is seriously affected by drilling at a plurality of replacement positions, and the structure of raft foundation 1 is damaged. After the protective layer is broken, the rebar gap can be accurately found, and since the gap positions of the upper layer and lower layer of the rebar mesh sheets of the raft foundation 1 are opposite, drilling vertically can substantially pass through the rebar gap of the lower layer, thereby greatly improving the construction efficiency and minimizing the structural damage.
[0106] The other reason is that after the inclined hole drilling, although the bottom of the lifting hole 4 extends to be directly below the load bearing wall 2, which is advantageous for grouting lifting, since the lifting holes 4 are inclined in one direction towards the center of the building and in one direction towards the periphery of the building compared with the inclinedly arranged hole in embodiment 1, the material used for the lifting hole 4 inclined outwards exceeds more than 30% of the material used for the lifting hole 4 inclined inwards under the same conditions through practical operation on site. The scheme of arranging holes vertically and tightly contacting with the load bearing wall 2 in the embodiment saves more than 15% of the material compared with the scheme of lifting hole 4 inclined outwards.
[0107] Preferably, a number of reinforcement grouting holes 31 can be arranged in advance on the inner side of the load bearing wall 2 on the side to be lifted and provided tightly contacting with the load bearing wall 2. A part of the reinforcing lifting holes 4 can be selected as the lifting reinforcing holes during the lifting grouting operation.
Embodiment 4
[0108] With reference to
[0109] In the reinforcement grouting and lifting grouting mentioned in the above embodiments, as well as the filling grouting and pressure grouting in the procedure of forming the reinforced composite pile foundation, the injected grout used is a two-component composite grout. For the convenience of expression, they are named grout A and grout B. The two grouts respectively reach the grout outlet of the grouting pipe (namely, the drill rod 93) from different channels of the drill rod, are pressed into the surrounding soil body at the grout outlet, and converge in the soil body to perform a chemical reaction. The initial set is completed in a short time.
[0110] The injected grout can be any one of the prior art as long as it can meet the initial setting time requirement and has good permeability.
[0111] The following injected grout formula can be adopted: grout A consists of the following raw materials in parts by weight: 70-90 parts of metal oxide and/or metal hydroxide, 0.5-1.2 parts of composite retarder, 0.5-0.7 parts of water reducer, 0.7-1.5 parts of acid-base buffer agent, 3-5 parts of composite stabilizer, and 0.5-1.5 parts of composite surfactant. The oxidation metal can be a combination of any two of magnesium oxide, aluminum oxide, magnesium phosphate, and the like; the composite retarder is at least two of urea, borax, and sodium tripolyphosphate; the water reducer can be a polycarboxylic acid water reducer or a naphthalene water reducer; the acid-base buffer agent is magnesium carbonate or potassium hydroxide; the composite stabilizer is at least two of hydroxymethyl cellulose, n-alkyl cetyl alcohol, starch ether, and cellulose ether; the composite surfactant is at least two of alkyl polyoxyethylene ether, benzyl phenol polyoxyethylene ether, and alkane sulfonate. When two or more different materials mentioned above are used in each of the above separate components, they can be formulated in an equal order of magnitude, the two being arranged primarily to prevent one from failing so that the overall composite grout effect is more stable.
[0112] Grout B consists of the following raw materials in parts by weight: 30-40 parts of phosphate and 0.2-1 parts of the defoaming agent. The phosphate can be diammonium hydrogen phosphate or potassium dihydrogen phosphate; the defoaming agent can be the organosilicon defoaming agent or polyether defoaming agent.
[0113] Grout A and grout B are mixed with water in a weight ratio of 100:40-50 respectively to be stirred to form a grout, and are pressed into the grout injecting pipe via different pipelines, converge at the grout outlet and react, and solidify in the soil body.
[0114] The embodiments in the detailed description are preferred embodiments of the present application, and are not intended to limit the scope of the present application. So: all equivalent changes made in accordance with the structure, shape, and principle of the present application should be covered by the scope of the present application.
[0115] In the drawings, 1, raft foundation; 2, load bearing wall; 3, reinforcement; 31, reinforcement grouting hole; 4, lifting hole; 41, densification lifting hole; 5, reinforcing hole; 6, reinforced composite pile foundation; 61, short cylinder; 7, pile foundation hole; 8, irregular grouting body; 91, gap channel; 92, tree-root-like grouting body; 93, drill rod; 94, pipe pile; and 11-14, four corner points.