PREFABRICATED CONCRETE PIER TOP FORM
20220112671 ยท 2022-04-14
Inventors
Cpc classification
E01D21/00
FIXED CONSTRUCTIONS
E04G13/02
FIXED CONSTRUCTIONS
E01D19/02
FIXED CONSTRUCTIONS
International classification
Abstract
A single-use or multi-use prefabricated pier top form for topping a concrete pier comprises a hollow mold with an upper portion in the desired shape of the finished pier top, a stepped-down tapered mid portion, and a lower mating portion for mating with the pier form so that concrete can be continuously poured to fill both the pier form and the pier top form at one time. Use of the prefabricated pier top form results in substantial time and material savings because the top of the pier residing above ground can be formed at the same time as the footer and pier are formed replacing the need to form a separate pier top after the pier and footer have been filled with concrete.
Claims
1. A prefabricated pier top form for creating a desired shape for a top of a structural pier comprising: a tubular lower section configured to mate with an upper section of a prefabricated concrete form; a tapered mid-section that transitions outwardly from the lower section; and an upper section configured to form a shape of the top of the structural pier.
2. The pier top form of claim 1 wherein the tubular lower section is configured to mate with an upper section of a prefabricated tubular pier form.
3. The pier top form of claim 1 further comprising an upper section in the shape of a rectangle.
4. The pier top form of claim 2 wherein the tubular lower section further comprises a stepped mating area configured to mate several different sizes of the prefabricated tubular pier form.
5. A plastic prefabricated pier top form for creating a desired shape for a top of a structural pier comprising: a tubular lower section configured to mate with an upper section of a prefabricated concrete form; a tapered mid-section that transitions outwardly from the lower section; and an upper section configured to form a shape of the top of the structural pier.
6. The pier top form of claim 5 wherein the tubular lower section is configured to mate with an upper section of a prefabricated tubular pier form.
7. The pier top form of claim 5 further comprising an upper section in the shape of a rectangle.
8. The pier top form of claim 6 wherein the tubular lower section further comprises a stepped collar configured to mate several different sizes of the prefabricated tubular pier form.
9. A method for creating a structural pier with a rectangle shaped upper surface comprising: creating a structural form assembly by setting a prefabricated footer form in the desired location; securing a prefabricated tubular pier form to the prefabricated footer form; securing a prefabricated pier top form to the prefabricated tubular pier form, the prefabricated pier top form comprising a tubular lower section configured to mate with the upper section of the prefabricated tubular pier form, a tapered mid-section that transitions outwardly from the lower section; and an upper rectangle shaped section to form the top of the structural pier; placing rebar within the structural form assembly; and filling the structural form assembly with concrete.
10. The method of claim 9 wherein the prefabricated pier top form is constructed of plastic.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0011] Embodiments of the present invention are illustrated by way of examples and are not limited to the accompanying drawings:
[0012]
[0013]
[0014]
[0015]
[0016]
[0017]
DETAILED DESCRIPTION OF INVENTION
[0018] Referring now to the figures,
[0019] Referring to
[0020] The pier top form 20 can be fully or partially filled with concrete to achieve the desired finished height. The pier top form 20 could be partially filled to any desired level. Typically, the pier top form 20 will be filled to a resulting height of six inches above finished grade. In some applications where a shorter overall structural pier is desired, the pier top form 20 can also be directly fitted to the footer form 14 as shown in
[0021] The tapered mid-section 40 transitions between the lower section 30 that mates to the pier form 12 and the upper section 50 that forms the desired shape of the pier top. The taper section 40 in one embodiment smoothly transitions between the two other sections permitting concrete to flow through the pier top form 20 to the pier form 12. In another embodiment, the pier top form 20 transition section 40 comprises a step or other shape as required to maintain flow of concrete through the pier top form 20 as it is being filled. The transition section 40 may also have securing portions for securing rebar or other structural members inside the pier top form 30.
[0022] The upper section 50 of the pier top form 20 forms the desired shape of the top of the structural pier.
[0023] The prefabricated pier top form 20 may be made from various materials including cardboard, plastic, or metal. In an embodiment of the invention, the pier top form 20 is made from cardboard. Following pouring concrete to create the pier and the setting of the concrete, the cardboard pier top form 20 may be cut away from the concrete exposing a clean pier top.
[0024] In another embodiment of the invention, the prefabricated the pier top form 20 is divided into first and second sections couple by a hinge. The first and second sections are held shut by a closure. The hinge permits easy removal of the pier top form 20 after concrete has been poured to form a structural pier. One or more, clasps or other structures may be used to hold the pier top form 20 closed as part of the structural pier form assembly 10 prior to pouring concrete.