Structures for Use in Erecting Multistory Buildings and Methods for Making Such Structures
20210332585 ยท 2021-10-28
Inventors
Cpc classification
B28B7/22
PERFORMING OPERATIONS; TRANSPORTING
E04B1/34823
FIXED CONSTRUCTIONS
International classification
E04B1/348
FIXED CONSTRUCTIONS
B28B7/22
PERFORMING OPERATIONS; TRANSPORTING
Abstract
Disclosed are various construction techniques for erecting a multistory building with an elevator shaft. In accordance with the method, upper and lower shaft components are formed at an offsite facility. These shaft components are then joined together to form a segment of the larger elevator shaft. Once constructed, the segment is transported to a jobsite and erected. Once an individual segment is installed, a floor slab can be formed about the segment. Using pre-cast elevator segments simplifies and expedites the construction process. In one embodiment, each segment includes a serrated edge that facilitates a connection between the floor slab and the shaft segment. Rebar and reinforcing dowels can also be used to improve the connection. Associated shaft constructions are also disclosed.
Claims
1. A modular, pre-cast elevator shaft for use in constructing a multi-story building, the modular, pre-cast elevator shaft comprising: a lower, rectangular shaft component including four walls, an upper edge, and a lower edge, an opening formed within one of the walls, a series of pockets formed adjacent the upper edge, each pocket including a recessed surface and adjacent exposed surfaces, the lower, rectangular shaft component being pre-formed from reinforced concrete; a series of hooked rebar segments, each hooked rebar segment including first and second ends, with the first end formed within the lower shaft component and the second end extending from one of the series of pockets; an upper, rectangular shaft component including four walls, an upper edge, and a lower edge, an opening formed within one of the walls, the upper, rectangular shaft component being pre-formed from reinforced concrete; an elevator shaft segment formed by joining the upper edge of the lower shaft component to the lower edge of the upper shaft component, reinforcing dowels extending between the upper and lower shaft components; a series of stitch plates, each stitch plate having an upper extent connected to one of the walls of the upper shaft component and a lower extent connected to one of the exposed surfaces of the lower shaft component, the series of stitch plates functioning to securely connect the upper and lower shaft components; a slab floor formed about the elevator shaft segment with the slab floor extending into the pockets of the lower shaft component and with the second ends of the hooked rebar segments extending into the slab floor.
2. An elevator shaft for use in constructing a multi-story building, the elevator shaft being formed from a series of elevator shaft segments, the elevator shaft comprising: a lower shaft component including walls, an upper edge, a lower edge, and a series of pockets formed along each of the walls, each pocket including a recessed surface and adjacent exposed surfaces; an upper shaft component including walls, an upper edge, and a lower edge, the lower edge of the upper shaft component being joined to the upper edge of the lower shaft component to form one of the series of elevator shaft segments; a slab floor formed about the elevator shaft segment with the slab floor extending into the pockets of the lower shaft component; a series of hooked rebar segments, each hooked rebar segment including first and second ends, with the first end formed within the lower shaft component and the second end extending from one of the series of pockets and into the slab floor.
3. The elevator shaft as described in claim 2 further comprising the upper and lower shaft components are pre-formed from reinforced concrete.
4. The elevator shaft as described in claim 2 further comprising reinforcing dowels extend between the upper and lower shaft components.
5. (canceled)
6. The elevator shaft as described in claim 2 further comprising a series of stitch plates, each stitch plate having an upper extent connected to one of the walls of the upper shaft component and a lower extent connected to one of the exposed surfaces of the lower shaft component, the series of stitch plates functioning to securely connect the upper and lower shaft components.
7. A method of constructing a multi-story building about an elevator shaft at a jobsite, the elevator shaft being formed from a series of shaft segments, with each shaft segment being formed at an offsite facility, the method comprising the following steps: forming a lower shaft component at the offsite facility from reinforced concrete, the lower shaft component including walls, an upper edge, a lower edge, and a series of pockets, with each pocket including recessed and exposed surfaces; forming an upper shaft component at the offsite facility from reinforced concrete, the upper shaft component including walls, an upper edge and a lower edge; joining the lower edge of the upper shaft component to the upper edge of the lower shat component, the joined shaft components constituting a shaft segment; securing the shaft segment with a series of stitch plates, with each stitch plate secured between a wall of the upper shaft component and one of the exposed surfaces of the lower shaft component; transporting the shaft segment to the jobsite and installing it as one of the series of segments forming the elevator shaft; pouring a concrete floor slab about the shaft segment, with the poured concrete extending into and bonding with the series of pockets within the lower shaft component.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0013] For a fuller understanding of the nature and objects of the invention, reference should be had to the following detailed description taken in connection with the accompanying drawings in which:
[0014]
[0015]
[0016]
[0017]
[0018]
[0019]
[0020]
[0021]
[0022] Similar reference characters refer to similar parts throughout the several views of the drawings.
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENT
[0023] The present disclosure relates to a construction method for erecting an elevator shaft for a multistory building. In accordance with the method, upper and lower shaft components are formed at an offsite facility. These shaft components are then joined together to form a segment of the larger elevator shaft. Once constructed, the segment is transported to a jobsite and erected. Once an individual segment is installed, a floor slab can be formed about the segment. Using pre-cast elevator segments simplifies and expedites the construction process. In one embodiment, each segment includes a serrated edge that facilitates a connection between the floor slab and the shaft segment. Rebar and reinforcing dowels can also be used to improve the connection. Associated shaft constructions are also disclosed. The various components of the present disclosure, and the manner in which they interrelate, are described in greater detail hereinafter.
[0024] With reference now to
[0025] Each segment 22 is formed from interconnected upper and lower components (24 and 26). In particular, and as better illustrated in
[0026] The lower shaft component 26, depicted in
[0027] With continuing reference to
[0028] Each upper shaft component 24 is formed to match the dimensions of the lower shaft component 26. As such, the depicted upper shaft component 24 includes four walls 62 and upper and lower edges (64 and 66). An opening 68 is also formed within one of the walls 62 and is designed to compliment the corresponding opening 38 in the lower shaft component 26. Together, these openings (38 and 68) form a larger opening for doors of the elevator shaft. The upper, rectangular shaft component 24 is similarly pre-formed from a reinforced concrete with interior rebar 48 (
[0029] Each elevator shaft segment 22 is formed by joining the upper edge 34 of the lower shaft component 26 to the lower edge 66 of the upper shaft component 24. Reinforcing dowels 72 can extend between the upper and lower shaft components (24 and 26) to improve the bonding. The connection is further strengthened via a series of stitch plates 74. Each stitch plate 74 includes an upper extent that is connected to one of the walls 62 of the upper shaft component 24 and a lower extent connected to one of the exposed surfaces 46 of the lower shaft component 26.
[0030] Once an elevator shaft segment 22 is completed it is transported to a jobsite to be erected as part of the larger elevator shaft 20. Thereafter, a slab floor 28 is formed about the shaft segment 22. As the floor slab 28 is poured, the concrete extends into and bonds with the pockets 42 of the lower shaft component 26, with the second ends 56 of the hooked rebar segments 52 extending into the slab floor 28 (
[0031] The floor slab 28 can be constructed via any number of construction methods. For example, in order to provide proper reinforcement, slab 28 can be poured about rebar or rebar cages.
[0032] The anchorage assembly 96 used for tendon 92 is illustrated in
[0033] The associated method of the present disclosure is next described. In the first step, a lower shaft component is formed from reinforced concrete at an offsite facility. As noted, this lower shaft component includes walls, upper and lower edges, and a series of pockets. Each pocket includes recessed and exposed surfaces. An upper shaft component is likewise formed from reinforced concrete at the offsite facility. This upper shaft component is similarly defined by walls, and upper and lower edges. In the next step, the lower edge of the upper shaft component is joined to the upper edge of the lower shaft component. The joined shaft components together constitute a shaft segment. Next, the shaft segment is further secured with a series of stitch plates, with each stitch plate connecting the wall of the upper shaft component to one of the exposed surfaces of the lower shaft component. The assembled shaft segment is then transported to the jobsite and installed. This process is repeated as needed to complete the entire elevator shaft. Thereafter, the floors can be constructed by pouring concrete about each shaft segment. As each floor is poured, the concrete extends into and bonds with the series of pockets within the lower shaft component. The floors can be poured following the completion of the entire elevator shaft. Alternatively, each floor can be poured after each individual shaft segment is installed. Furthermore, the shaft segments can be transported to the jobsite individually or in larger quantities.
[0034] Although this disclosure has been described in terms of certain embodiments and generally associated methods, alterations and permutations of these embodiments and methods will be apparent to those skilled in the art. Accordingly, the above description of example embodiments does not define or constrain this disclosure. Other changes, substitutions, and alterations are also possible without departing from the spirit and scope of this disclosure.