Startup charge balancing circuits and methods for capacitive charge pumps that avoid large in-rush currents and resulting voltage spikes. Embodiments include a charge balance circuit coupled to a corresponding charge pump capacitor of a charge pump. The charge balance circuit includes a comparator that compares the output voltage of the charge pump to a feedback voltage derived from the voltage across the corresponding charge pump capacitor. In response, either a constant current source or a constant current sink is coupled to the charge pump capacitor. Current sourcing or sinking continues until the voltage across the corresponding charge pump capacitor approximates a target voltage, at which point the comparator output toggles, which results in uncoupling of the coupled current source or current sink from the corresponding charge pump capacitor. Embodiments only need one current sink and one current source per charge pump capacitor, and charge balancing is independent of leakage currents.
Claims
1. A charge balance circuit configured to be coupled to a corresponding charge pump capacitor within a switched-capacitor power converter, including a current charge/discharge circuit configured to selectively provide either a constant current source or a constant current sink to the corresponding charge pump capacitor as a function of a voltage across the corresponding charge pump capacitor and an output voltage of the switched-capacitor power converter until the voltage across the corresponding charge pump capacitor is approximately equal to a target voltage.
2. The invention of claim 1, further including a ground connection subcircuit configured to selectively couple the coupled charge pump capacitor to, or uncouple the coupled charge pump capacitor from, circuit ground.
3. The invention of claim 1, further including a comparator coupled to the current charge/discharge circuit, the comparator configured to output a signal indicative of the relative values of the output voltage of the switched-capacitor power converter with respect to a feedback voltage, wherein the comparator output signal enables coupling of one of the constant current source or the constant circuit sink to the coupled charge pump capacitor.
4. The invention of claim 3, wherein a change in value of the comparator output signal disables coupling of at least one of the constant current source and the constant circuit sink from the corresponding charge pump capacitor.
5. The invention of claim 3, further including a ground connection subcircuit configured to selectively couple the coupled charge pump capacitor to, or uncouple the coupled charge pump capacitor from, circuit ground, wherein the ground connection subcircuit is configured to uncouple the coupled charge pump capacitor from circuit ground after the comparator output signal changes value.
6. The invention of claim 3, further including a scaling circuit configured to generate the feedback voltage as a scaled version of the voltage across the coupled charge pump capacitor.
7. The invention of claim 6, wherein the scaling circuit includes a resistive voltage divider.
8. The invention of claim 1, further including a comparator coupled to the current charge/discharge circuit, the comparator including a first input coupled to the output voltage of the switched-capacitor power converter and a second input coupled to a feedback voltage derived from the voltage across the coupled charge pump capacitor, the comparator configured to output a signal indicative of the relative values of the output voltage of the switched-capacitor power converter with respect to the feedback voltage.
9. A charge balance circuit configured to be coupled to a corresponding charge pump capacitor within a switched-capacitor power converter, including: (a) a comparator having a first input coupled to an output voltage of the switched-capacitor power converter, a second input coupled to a feedback voltage derived from a voltage across the corresponding charge pump capacitor, and a comparator output signal that provides a signal indicative of the relative values of the output voltage of the switched-capacitor power converter with respect to the feedback voltage; (b) a ground connection subcircuit configured to selectively couple the corresponding charge pump capacitor to, or uncouple the corresponding charge pump capacitor from, circuit ground; (c) a constant current charge circuit coupled to the comparator and selectively couplable to the corresponding charge pump capacitor in response to a first value of the comparator output signal; (d) a constant current discharge circuit coupled to the comparator and selectively couplable to the corresponding charge pump capacitor in response to a second value of the comparator output signal; and (e) a digital controller coupled to the comparator output, the digital controller configured to disable at least one of the constant current charge circuit and the constant current discharge circuit after the comparator output changes state.
10. The invention of claim 9, wherein the ground connection subcircuit is configured to uncouple the corresponding charge pump capacitor from circuit ground after the comparator output changes value.
11. The invention of claim 9, further including a scaling circuit configured to generate the feedback voltage as a scaled version of the voltage across the corresponding charge pump capacitor.
12. The invention of claim 11, wherein the scaling circuit includes a resistive voltage divider.
13. A switched-capacitor power converter, including: (a) at least one charge pump capacitor; and (b) at least one charge balance circuit coupled to a corresponding one of the at least one charge pump capacitor, each charge balance circuit including a current charge/discharge circuit configured to provide either a constant current source or a constant current sink to the corresponding charge pump capacitor as a function of both a voltage across the corresponding charge pump capacitor and an output voltage of the switched-capacitor power converter until the voltage across the corresponding charge pump capacitor is approximately equal to a target voltage.
14. The invention of claim 13, further including a ground connection subcircuit coupled to the corresponding charge pump capacitor, the ground connecting subcircuit configured to selectively couple the corresponding charge pump capacitor to, or uncouple the corresponding charge pump capacitor from, circuit ground.
15. The invention of claim 13, further including a comparator coupled to the current charge/discharge circuit, the comparator configured to output a signal indicative of the relative values of the output voltage of the coupled switched-capacitor power converter with respect to the feedback voltage, wherein the comparator output signal enables coupling of one of the constant current source or the constant circuit sink to the corresponding charge pump capacitor.
16. The invention of claim 15, wherein a change in a value of the comparator output signal disables coupling of at least one of the constant current source and the constant circuit sink from the corresponding charge pump capacitor.
17. The invention of claim 15, further including a ground connection subcircuit coupled to the corresponding charge pump capacitor, the ground connecting subcircuit configured to selectively couple the corresponding charge pump capacitor to, or uncouple the corresponding charge pump capacitor from, circuit ground, wherein the ground connection subcircuit is configured to uncouple the corresponding charge pump capacitor from circuit ground after the change in value of the comparator output signal.
18. The invention of claim 15, further including a scaling circuit configured to generate the feedback voltage as a scaled version of the voltage across the corresponding charge pump capacitor.
19. The invention of claim 18, wherein the scaling circuit includes a resistive voltage divider.
20. The invention of claim 13, further including a comparator coupled to the current charge/discharge circuit, the comparator including a first input coupled to the output voltage of the switched-capacitor power converter and a second input coupled to a feedback voltage derived from the voltage across the corresponding charge pump capacitor, the comparator configured to a output a signal indicative of the relative values of the output voltage of the coupled switched-capacitor power converter with respect to the feedback voltage, wherein the comparator output signal enables coupling of one of the constant current source or the constant circuit sink to the corresponding charge pump capacitor.
21. A method for balancing charge across a charge pump capacitor within a switched-capacitor power converter, including: (a) coupling one of a constant current source or a constant current sink to the charge pump capacitor in response to comparing an output voltage of the switched-capacitor power converter to a feedback voltage derived from a voltage across the charge pump capacitor; and (b) de-coupling the constant current source and the constant current sink from the charge pump capacitor after the voltage across the charge pump capacitor is approximately equal to a target voltage.
Description
DESCRIPTION OF THE DRAWINGS
(1)
(2)
(3)
(4)
(5)
(6)
(7) Like reference numbers and designations in the various drawings indicate like elements.
DETAILED DESCRIPTION
(8) The invention encompasses startup charge balancing circuits and methods for switched-capacitor power converters that avoid large in-rush currents and resulting large voltage spikes. The charge balancing circuits are readily integrated with integrated circuit embodiments of a power converter, provide fast balancing times, and provide charge balancing rates that are independent of leakage currents.
(9) Charge Pump States
(10) In general, a switched-capacitor power converter/charge pump will operate in at least one of three distinct states: a steady-state, a shutdown state, and a startup state. During the steady-state or “normal” operation state in which a charge pump is ready to support and does support load currents, the charge pump receives an input voltage V.sub.IN and transforms it, by switching connections to the pump capacitors Cx, into an output voltage V.sub.OUT that is a fraction or multiple of V.sub.IN. In the shutdown state, there is no charge pump switching activity. In the startup state, a voltage difference is presented across the input terminals of the charge pump and some internal circuit activity may be enabled to eventually cause the charge pump to begin switching in order to transfer charge from the voltage source at the input to the output voltage using the pump capacitors Cx—that is, to transition from the shutdown state to steady-state operation. In some embodiments, the startup state may include (1) a pre-switching period in which some circuitry in the charge pump is active (e.g., to rebalance capacitor nodes) but charge pump switching is disabled (where charge pump switching is defined as applying clock signals P1 and P2 as generated by controller 104 to control the charge pump switches, such as charge pump switches 206x in
(11) The voltage across any one pump capacitor Cx relative to the voltage across other pump capacitors Cx, as well as relative to the voltage across the output capacitor C.sub.OUT, may be such that in the first few switching cycles, without mitigating circuitry, the charge pump switches may experience voltage stress and/or the in-rush current at the charge pump input and output terminals may be excessive. Accordingly, as noted above, during the startup phase it may be necessary to first rebalance the voltage on the pump capacitors with respect to the voltage on the output capacitor (noting that the output capacitor may comprise multiple individual capacitors).
(12) In particular, there is a problem of possible transient voltage stress across the charge pump switches during start-up, when the pump capacitors Cx and the output capacitor C.sub.OUT are unbalanced relative to each other, meaning that they have non-zero voltages that deviate significantly from their steady-state values for particular V.sub.IN or V.sub.OUT values. Further, embodiments of switched-capacitor power converters may be subjected to a variety of capacitor charge states at startup resulting, for example, from startup of the power converter after a long shutdown duration and/or restart of the power converter after a fault condition (e.g., short circuit fault). For example, at startup of such a power converter after a long shutdown duration, none of the capacitors or capacitances C.sub.OUT or Cx may be initially precharged (Scenario 1). In other conditions before startup, the pump capacitors Cx may have little or no charge (e.g., due to leakage) while the much larger capacitance C.sub.OUT remains precharged (Scenario 2). In still other conditions, such as a startup after a short across the converter load, the pump capacitors Cx may be precharged but C.sub.OUT may have partially or fully discharged (Scenario 3). Intermediate conditions may also occur where C.sub.OUT and/or the pump capacitors Cx are at varying precharged and/or discharged degrees. A good converter design should be able to deal with all of these startup conditions or any of the possible precharged conditions that may arise.
(13) A possible solution to dealing with an unknown startup charge state for a switched-capacitor power converter would be to discharge all capacitors before startup commences so as to result in a known charge state, or to use high-voltage rated FETs for the charge pump switches so as to mitigate FET over-voltage stress. However, these solutions are inefficient, waste charge (which may be highly undesirable for battery-powered applications), and/or require relatively long startup times to settle into steady-state power converter operation. Furthermore, a particular application, such as a cellular phone, may not tolerate or allow a power converter component to discharge the relatively large output capacitor C.sub.OUT without careful controls in place.
(14) A better solution is to utilize a charge balancing circuit to source current to or sink current from the capacitor nodes within a charge pump to achieve a desired respective voltage at such nodes. One such solution is taught in U.S. Patent Application No. 62/971,094, filed Feb. 14, 2020, entitled “Startup of Switched Capacitor Step-Down Power Converter”, assigned to the assignee of the present invention, the contents of which are hereby incorporated by reference. In the referenced solution, the output voltage V.sub.OUT of a charge pump is sensed and a current proportional to V.sub.OUT is generated with a current mirror circuit. If the voltage across any of the charge pump capacitors Cx is lower than a target voltage level, the generated current is injected into those capacitors until they reach the target level (which depends on the division ratio configured in the charge pump). If the voltage across any of the charge pump capacitors Cx is higher than a target voltage level, a current is sunk from those capacitors until they reach the target level. The process is stopped when one or more auxiliary comparators detect that each of the charge pump capacitors Cx is charged to within a desired range (e.g., 80-120%) of the target voltage. However, embodiments may be slow to charge/discharge a charge pump capacitor Cx owing to a relatively large RC time constant, run continuously (and thus may be inefficient), may be sensitive to leakage currents through the current mirror circuit, and force a current source through a resistor to ground (and thus wastes energy).
(15) Improved Solution Overview
(16) The present invention provides an even better solution that includes embodiments that, compared to prior solutions, are simplified and provide a more robust way of balancing the charge of pump capacitors Cx in a charge pump. For example,
(17) As an overview, each charge balance circuit CBx includes a comparator that compares the output voltage V.sub.OUT to a feedback voltage V.sub.FB derived from the voltage V.sub.Cx across a coupled charge pump capacitor Cx. The feedback voltage V.sub.FB may be scaled in value for each charge pump capacitor Cx. A digital controller receives the result of the comparison (either a 1 or a 0) and enables coupling of either a constant current source or a constant current sink to the charge pump capacitor Cx. Current sourcing to or sinking from the coupled charge pump capacitor Cx continues until the voltage V.sub.Cx across the coupled charge pump capacitor Cx is approximately equal to a target voltage, at which point the comparator output will toggle, from 0 to 1 or from 1 to 0 (note: the target voltage for each charge pump capacitor Cx generally will be different depending on the charge pump capacitor Cx and the configuration of the charge pump, and is determined by the feedback voltage V.sub.FB). The digital controller will uncouple both the current source and current sink from the corresponding charge pump capacitor Cx once the comparator toggles in either direction. Thereafter, any remaining steps of the start-up process may be completed and the charge pump may transition to steady-state operation.
(18) Embodiments of the present invention only need one current sink and one current source per charge pump capacitor, and while constant current sourcing/sinking is triggered in part by the output voltage V.sub.OUT, V.sub.OUT is not used to directly generate that constant current to achieve the target voltage. Accordingly, while each charge balance circuit operates until a balanced condition is reached for a coupled charge capacitor, charge balancing is independent of leakage currents (a problem for some prior solutions).
Example Charge Balance Circuit Embodiment
(19)
(20) We now discuss operation of the exemplary charge balance circuit CBx of
(21) The current charge/discharge circuit 402 is configured to provide either a constant current source or a constant current sink to the charge pump capacitor Cx until the voltage V.sub.Cx across the coupled charge pump capacitor Cx is approximately equal to a target voltage. In the example illustrated in
(22) The current sources/sinks Ichg, Idischg may be implemented in a number of known ways, such as a current mirror, particularly a MOSFET current mirror. The principal desired characteristic of the current sources/sinks Ichg, Idischg is that they provide an essentially constant current to or from node X in order to charge or discharge the associated charge pump capacitor Cx without incurring excessive current in-rush or out-rush (which is a major aspect of the more general charge pump problem being solved by the charge balance circuit CBx). Accordingly, any current source/sink that regulates the flow of current to approximately a desired level may be used for the current sources/sinks Ichg, Idischg. One of the current sources/sinks, Ichg or Idischg, is selectively coupled to node X during a charge balancing event by an associated switch Sw.sub.CHG, Sw.sub.DISCHG which are ultimately responsive to the relative voltage at the charge pump output, V.sub.OUT, with respect to the voltage V.sub.Cx across the associated charge pump capacitor Cx, as controlled by the exemplary binary-output comparator 404 and logic circuit 405 described below.
(23) In the illustrated detailed example of
(24) In the illustrated example, if V.sub.OUT≥V.sub.FB, then the output comp_out of the comparator 404 is a binary “1”. Conversely, if V.sub.OUT<V.sub.FB, then the output comp_out of the comparator 404 is a binary “0”. The output comp_out of the comparator 404 is coupled to a digital controller 408, which may be included as part of the general charge pump controller 104 shown in
(25) One output of the digital controller 408 is an enable signal that enables or disables the first and second AND gates 410, 414. When the enable signal is “0”, both of the AND gates 410, 414 are disabled, switch Sw.sub.GND1 is set to OPEN, and the switches Sw.sub.CHG, Sw.sub.DISCHG are set to OPEN, thus disconnecting the current sources/sinks Ichg, Idischg from node X. Accordingly, the charge balance circuit CBx is effectively disconnected from the associated charge pump capacitor Cx.
(26) Conversely, when the enable signal is “1”, and since the outputs of the first AND gate 410 and the second AND gate 414 are complementary, then (1) one (and only one) of the AND gates 410, 414 outputs a logic “1”, and the corresponding switch Sw.sub.CHG, Sw.sub.DISCHG is set to CLOSED, thus coupling the respective current source/sink Ichg, Idischg to node X, (2) the other switch Sw.sub.DISCHG, Sw.sub.CHG is set to OPEN, thus disconnecting the respective current source/sink Idischg, Ichg from node X, and (3) switch Sw.sub.GND1 is set to CLOSED, completing the circuit to the corresponding capacitor Cx. Accordingly, the charge balance circuit CBx is coupled across the associated charge pump capacitor Cx.
(27) In operation, during a charge balancing event (typically during a pre-switching period of start-up), the digital controller 408 sets the enable signal to “1”, thereby enabling the first and second AND gates 410, 414 to respond to the output of the comparator 404. Depending on the relative values of the output voltage V.sub.OUT of the switched-capacitor power converter with respect to the feedback voltage V.sub.FB (i.e., whether V.sub.OUT≥V.sub.FB or if V.sub.OUT<V.sub.FB), charging or discharging of the associated charge pump capacitor Cx commences. Charging or discharging continues until the voltage V.sub.Cx across the associated charge pump capacitor Cx reaches a desired target level with respect to the charge pump output voltage V.sub.OUT, at which point the comparator 404 output, comp_out, toggles state. Any change in comp_out (from 0 to 1 or from 1 to 0) will cause the digital controller 408 to reset the enable signal to “0”, thereby disabling charging or discharging of the associated charge pump capacitor Cx. For example, a change in comp_out may be detected within the digital controller 408 by means of a parallel pair of edge-triggered flip-flops, one set to output a “1” on a positive edge transition, and the other set to output a “1” on a negative edge transition.
(28) More specifically, for the illustrated example, if the enable signal is “1” and V.sub.OUT≥V.sub.FB, then the output of the comparator 404 will be a “1”, the first AND gate 410 will set switch Sw.sub.CHG to CLOSED, and the second AND gate 414 will set switch Sw.sub.DISCHG to OPEN. Current source Ichg will thus be connected to node X and provide an essentially constant current to charge the associated charge pump capacitor Cx, while current sink Idischg is disconnected from node X. When V.sub.Cx reaches a desired target level with respect to V.sub.OUT (i.e., V.sub.OUT<V.sub.FB), the output of the comparator 404 will toggle to “0”, thereby causing the digital controller 408 to reset the enable signal to “0”, thereby disabling both the first and second AND gates 410, 414 and opening switches Sw.sub.CHG, Sw.sub.DISCHG, and Sw.sub.GND1. Both current sources/sinks, Ichg, Idischg will thus be disconnected from the associated charge pump capacitor Cx.
(29) Conversely, if the enable signal is “1” and V.sub.OUT<V.sub.FB, then the output of the comparator 404 will be a “0”, the first AND gate 410 will set switch Sw.sub.CHG to OPEN, and the second AND gate 414 will set switch Sw.sub.DISCHG to CLOSED. Current sink Idischg will thus be connected to node X and provide an essentially constant current to discharge the associated charge pump capacitor Cx, while current source Ichg is disconnected from node X. When V.sub.Cx reaches a desired target level with respect to V.sub.OUT (i.e., V.sub.OUT≥V.sub.FB), the output of the comparator 404 will toggle to “1”, thereby causing the digital controller 408 to reset the enable signal to “0”, thereby disabling both the first and second AND gates 410, 414 and opening switches Sw.sub.CHG, Sw.sub.DISCHG, and Sw.sub.GND1. Both current sources/sinks Ichg, Idischg will thus be disconnected from the associated charge pump capacitor Cx.
(30) As should be clear, other circuits may be used to perform the function of coupling only one current source/sink, Ichg or Idischg, to an associated charge pump capacitor Cx during a charge balancing event until V.sub.Cx reaches a desired target level, and thereafter disconnecting the current sources/sinks from the associated charge pump capacitor Cx.
(31) In embodiments in which a charge pump may be configured between one of two conversion ratios, such as divide-by-2 or divide-by-3, it may be useful to reconfigure the scaling circuit 406 between different levels of scaling. Accordingly, the digital controller 408 may output a configuration mode signal, conf_sel that is coupled to an AND gate 416 that controls the switch Sw.sub.GND2 in the example scaling circuit 406. With conf_sel set to “1”, the switch Sw.sub.GND2 is controlled by the enable signal from the digital controller 408. When switch Sw.sub.GND2 is CLOSED, the scaling circuit 406 outputs V.sub.FB, which is a scaled version of V.sub.Cx that depends on the ratio of R1 and R2. When switch Sw.sub.GND2 is OPEN, V.sub.FB will equal V.sub.Cx. In a different mode in which conf_sel is set to “0”, the switch Sw.sub.GND2 is OPEN regardless of the value of the enable signal from the digital controller 408 and hence V.sub.FB will equal V.sub.Cx.
(32) Embodiments of the present invention provide a number of advantages over prior solutions. For example, compared to a number of prior solutions, embodiments of the present invention may be implemented with fewer components, thus taking up less area (a valuable commodity) in an integrated circuit implementation.
(33) Another significant advantage is that some embodiments of the present invention may provide balancing times that are about one-third the balancing times of prior art embodiments, or better, thus allowing a charge pump to more rapidly achieve steady-state operation.
(34) Another advantage of embodiments of the present invention is that charge balancing is independent of leakage currents. In some prior solutions, the current injected into or sunk from the charge pump capacitors Cx and the output capacitor C.sub.OUT depends on a measurement of the output voltage V.sub.OUT. Any kind of leakage in any of these capacitive nodes, their associated switches, or the prior charge balance circuit (very typical in high power charge pumps that require massive switches), can jeopardize the target voltage to which the capacitors will end up being charged—that is, the target voltage may not be met at all. In contrast, embodiments of the present invention inject or sink an essentially constant current and stop current injection/sinking when charge balancing is achieved, even in the presence of leakage (as long as the source/sink current is larger than the leakage).
(35) While the examples of usage of the present invention involve a Dickson charge pump, the charge balance circuit CBx may be used in conjunction with many other types of switched-capacitor circuits, including cascade multiplier, ladder, series-parallel, Fibonacci, and doubler switched-capacitor circuits, all of which may be configured as a multi-phase or a single-phase circuit. Charge balancing circuits in accordance with the present invention may be readily integrated with integrated circuit embodiments of such power converters.
(36) Methods
(37) Another aspect of the invention includes methods for balancing charge across a charge pump capacitor within a switched-capacitor power converter.
(38) For example,
(39) Fabrication Technologies & Options
(40) The term “MOSFET”, as used in this disclosure, includes any field effect transistor (FET) having an insulated gate whose voltage determines the conductivity of the transistor, and encompasses insulated gates having a metal or metal-like, insulator, and/or semiconductor structure. The terms “metal” or “metal-like” include at least one electrically conductive material (such as aluminum, copper, or other metal, or highly doped polysilicon, graphene, or other electrical conductor), “insulator” includes at least one insulating material (such as silicon oxide or other dielectric material), and “semiconductor” includes at least one semiconductor material.
(41) Various embodiments of the invention can be implemented to meet a wide variety of specifications. Unless otherwise noted above, selection of suitable component values is a matter of design choice. Various embodiments of the invention may be implemented in any suitable integrated circuit (IC) technology (including but not limited to MOSFET structures), or in hybrid or discrete circuit forms. Integrated circuit embodiments may be fabricated using any suitable substrates and processes, including but not limited to standard bulk silicon, silicon-on-insulator (SOI), and silicon-on-sapphire (SOS). Unless otherwise noted above, embodiments of the invention may be implemented in other transistor technologies such as bipolar, LDMOS, BCD, GaAs HBT, GaN HEMT, GaAs pHEMT, and MESFET technologies. However, embodiments of the invention are particularly useful when fabricated using an SOI or SOS based process, or when fabricated with processes having similar characteristics. Fabrication in CMOS using SOI or SOS processes enables circuits with low power consumption, the ability to withstand high power signals during operation due to FET stacking, good linearity, and high frequency operation (i.e., radio frequencies up to and exceeding 50 GHz). Monolithic IC implementation is particularly useful since parasitic capacitances generally can be kept low (or at a minimum, kept uniform across all units, permitting them to be compensated) by careful design.
(42) Voltage levels may be adjusted, and/or voltage and/or logic signal polarities reversed, depending on a particular specification and/or implementing technology (e.g., NMOS, PMOS, or CMOS, and enhancement mode or depletion mode transistor devices). Component voltage, current, and power handling capabilities may be adapted as needed, for example, by adjusting device sizes, serially “stacking” components (particularly FETs) to withstand greater voltages, and/or using multiple components in parallel to handle greater currents. Additional circuit components may be added to enhance the capabilities of the disclosed circuits and/or to provide additional functionality without significantly altering the functionality of the disclosed circuits.
(43) Circuits and devices in accordance with the present invention may be used alone or in combination with other components, circuits, and devices. Embodiments of the present invention may be fabricated as integrated circuits (ICs), which may be encased in IC packages and/or modules for ease of handling, manufacture, and/or improved performance. In particular, IC embodiments of this invention are often used in modules in which one or more of such ICs are combined with other circuit blocks (e.g., filters, passive components, and possibly additional ICs) into one package. The ICs and/or modules are then typically combined with other components, often on a printed circuit board, to form an end product such as a cellular telephone, laptop computer, or electronic tablet, or to form a higher level module which may be used in a wide variety of products, such as vehicles, test equipment, medical devices, etc. Through various configurations of modules and assemblies, such ICs typically enable a mode of communication, often wireless communication.
CONCLUSION
(44) A number of embodiments of the invention have been described. It is to be understood that various modifications may be made without departing from the spirit and scope of the invention. For example, some of the steps described above may be order independent, and thus can be performed in an order different from that described. Further, some of the steps described above may be optional. Various activities described with respect to the methods identified above can be executed in repetitive, serial, or parallel fashion.
(45) It is to be understood that the foregoing description is intended to illustrate and not to limit the scope of the invention, which is defined by the scope of the following claims, and that other embodiments are within the scope of the claims. In particular, the scope of the invention includes any and all feasible combinations of one or more of the processes, machines, manufactures, or compositions of matter set forth in the claims below. (Note that the parenthetical labels for claim elements are for ease of referring to such elements, and do not in themselves indicate a particular required ordering or enumeration of elements; further, such labels may be reused in dependent claims as references to additional elements without being regarded as starting a conflicting labeling sequence).