METHOD FOR INSTALLING A TUBULAR METAL PILE IN ROCKY SOIL
20210292989 · 2021-09-23
Inventors
Cpc classification
E02D15/08
FIXED CONSTRUCTIONS
Y02E10/72
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
E02D27/525
FIXED CONSTRUCTIONS
E02D5/285
FIXED CONSTRUCTIONS
E02D15/10
FIXED CONSTRUCTIONS
Y02E10/727
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
International classification
E02D15/08
FIXED CONSTRUCTIONS
E02D15/10
FIXED CONSTRUCTIONS
E02D27/52
FIXED CONSTRUCTIONS
Abstract
A method for installing a tubular metal pile in a rocky ground, successively comprises the steps of drilling the rocky ground in order to form a cavity of predetermined diameter and depth, filling the cavity with a granular material, arranging the granular material present in the cavity by vibration, and installing the pile in the cavity.
Claims
1.-11. (canceled)
12. A method for installing a tubular metal pile in a rocky ground, successively comprising: drilling the rocky ground in order to form a cavity of predetermined diameter and depth; filling the cavity with a granular material; arranging the granular material present in the cavity by vibration; and installing the pile in the cavity.
13. The method according to claim 12, wherein the pile is installed at sea in a rocky seabed.
14. The method according to claim 12, wherein the pile is installed onshore in a rocky ground.
15. The method according to claim 12, wherein the arrangement of the granular material in the cavity is achieved during the installation of the pile.
16. The method according to claim 12, wherein the arrangement of the granular material in the cavity is achieved prior to the installation of the pile.
17. The method according to claim 16, wherein the arrangement of the granular material in the cavity is achieved by vibro-compaction.
18. The method according to claim 16, wherein the arrangement of the granular material in the cavity is achieved by dynamic compaction.
19. The method according to claim 12, wherein the pile is installed by vibro-sinking into the cavity filled with the granular material.
20. The method according to claim 12, wherein the pile is installed by driving into the cavity filled with the granular material.
21. The method according to claim 12, wherein installing the pile in the cavity successively comprises placing a guide, vertically inserting the pile through this guide, and placing the pile in the cavity.
22. The method according to claim 12, wherein the granular material comes from the material obtained from the drilling of the rocky ground.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Other characteristics and advantages of the present invention will emerge from the description given below, with reference to the appended drawings which illustrate an exemplary embodiment thereof without any limitation. In the figures:
[0019]
[0020]
[0021]
DETAILED DESCRIPTION OF THE INVENTION
[0022] The method according to the invention comprises three main steps, namely a main step of drilling a cavity, a main step of filling and arranging the cavity and an actual main step of installing the pile in the cavity.
[0023]
[0024] In this exemplary embodiment, the tubular metal pile is installed at sea in a rocky seabed (it may be, for example, a foundation pile of an offshore wind turbine). Of course, the steps of the method according to the invention also apply to the land installation of a tubular metal pile in a rocky ground.
[0025] During a first sequence (
[0026] The platform 2 is of the jack-up type, that is to say it comprises legs 8 that bear on the rocky seabed 6 to allow lifting the platform 2 above sea level. A derrick 10 of the drilling facility is then lowered (
[0027] A drilling head 12 is then lowered into the derrick 10 and the drilling of the rocky seabed 6 to form a cavity 14 of predetermined diameter and depth begins (step 1C).
[0028]
[0029] During the following sequence (
[0030] Finally, the derrick 10 of the drilling facility can be pulled up, the legs 8 be raised (
[0031]
[0032] This step requires placing, above the cavity 14, a ship 17 for transporting granular material 18. This granular material can be for example imported sand or come directly from the material obtained from the drilling of the rocky ground, in which case it may have undergone prior treatment.
[0033] During a first sequence (
[0034] Once the cavity is almost completely filled with the granular material, the duct 19 is pulled up onboard the ship and an arrangement of this granular material is carried out (
[0035] The vibro-compaction is a known technique for generating an arrangement of the granular material having filled the cavity. This method is a mass treatment which consists in immersing a vibrator 20 (or vibrating needle) into the cavity filled with granular material to emit vibrations in order to rearrange the grains in order to density the material having filled the cavity.
[0036] The dynamic compaction (not represented in the figures) is another known technique for generating a settlement of the granular material present in the cavity under the effect of the input of high energies. Typically, in order to create high-energy waves in the cavity, a mass of several tons is dropped several times on the granular material.
[0037] Once the arrangement operation is complete, the height of granular material present in the cavity 14 is lower than before this operation.
[0038] During the next sequence (
[0039] The gravel 24 then undergoes an arrangement operation as described above (vibro-compaction or dynamic compaction), for example by means of a vibrator 20 as represented in
[0040] It will be noted that the sequence of arrangement of the granular material in the cavity can be performed before (as described above) or during the pile installation step described below.
[0041]
[0042] This step requires placing, above the cavity 14, a ship 26 for installing the metal, tubular and hollow pile 28 (the ship for transporting granular material having been previously conveyed to another site).
[0043] A first sequence may consist in installing a guide 30 at the upper end of the cavity 14 (
[0044] The tubular and hollow metal pile 28 is then inserted into the cavity (
[0045] The insertion of the pile into the cavity filled with the arranged granular material is carried out by vibro-sinking or driving. The vibro-sinking is a technique known in the construction industry and public works for sinking piles by high-frequency and low-amplitude vibration. As for the driving, it is another known technique consisting in sinking a pile into the ground by dynamic effect of shocks or vibrations. The shocks are generally obtained by the drop of the drop hammer on a pile cap and the vibrations by a disposition called a vibrator or pile hammer.
[0046] The insertion of the pile is then stopped once the desired insertion depth is reached and the ship 26 is moved to another pile installation site (