Method for bonding large modules, and bonding arrangement
11103946 ยท 2021-08-31
Assignee
Inventors
Cpc classification
B23K20/10
PERFORMING OPERATIONS; TRANSPORTING
H01L21/02
ELECTRICITY
B23K37/00
PERFORMING OPERATIONS; TRANSPORTING
B23K37/047
PERFORMING OPERATIONS; TRANSPORTING
B65G17/00
PERFORMING OPERATIONS; TRANSPORTING
B65G19/00
PERFORMING OPERATIONS; TRANSPORTING
B23K37/0235
PERFORMING OPERATIONS; TRANSPORTING
B23K2101/36
PERFORMING OPERATIONS; TRANSPORTING
B23K1/0016
PERFORMING OPERATIONS; TRANSPORTING
International classification
B23K1/00
PERFORMING OPERATIONS; TRANSPORTING
B23Q7/14
PERFORMING OPERATIONS; TRANSPORTING
B23K37/00
PERFORMING OPERATIONS; TRANSPORTING
H01L21/02
ELECTRICITY
B65G17/00
PERFORMING OPERATIONS; TRANSPORTING
B23K20/00
PERFORMING OPERATIONS; TRANSPORTING
B65G19/00
PERFORMING OPERATIONS; TRANSPORTING
B23K20/10
PERFORMING OPERATIONS; TRANSPORTING
B23K37/02
PERFORMING OPERATIONS; TRANSPORTING
B23K37/04
PERFORMING OPERATIONS; TRANSPORTING
B23K37/047
PERFORMING OPERATIONS; TRANSPORTING
Abstract
A method for bonding large modules with the following steps, a large module is fed to a bonder from behind in a loading plane by means of a feeder unit. The large module is passed from the feeder unit to a first transverse conveyor unit, and is brought by the same to a first buffer position provided in the bonder, wherein the first buffer position is provided in a loading plane of the bonder. The large module is brought from the first buffer position into a first receiving position in the loading plane via the first transverse conveyor unit and is passed there to a vertical conveyor unit.
Claims
1. A method for bonding modules, the method comprising: feeding a module to a bonder from behind in a loading plane via a feeder unit; passing the module from the feeder unit to a first transverse conveyor unit, and is brought by the same to a first buffer position provided in the bonder, wherein the first buffer position is provided in a loading plane of the bonder; positioning the module from the first buffer position into a first receiving position in the loading plane via the first transverse conveyor unit and passing the module to a vertical conveyor unit; moving the vertical conveyor unit, the module is moved vertically and brought into a bonding plane, wherein the module in the bonding plane is located at least partially in a working area of the bonder; processing the module by a first bonding head and/or by a second bonding head, wherein electrically conductive bond connections are produced on the module; moving the module vertically by the vertical conveyor unit out of the bonding plane into a second transfer position, and in the second transfer position is passed to a second transverse conveyor unit, wherein the second transfer position is provided in an unloading plane of the bonder; positioning the module by the second transverse conveyor unit into a second buffer position in the unloading plane; and passing, from the second buffer position, the module to a removal unit via the second transverse conveyor unit.
2. The method according to claim 1, wherein the vertical conveyor unit has a vertically movable support body designed to receive the module, wherein the support body is lowered below the loading plane before the module is brought from the first buffer position into the transfer position.
3. The method according to claim 1, wherein, when the module is brought from the first transfer position into the bonding plane, the second transfer position for the module is traveled through and/or the second transverse conveyor unit is provided in the second buffer position.
4. The method according to claim 1, wherein the support body is moved vertically out of the bonding plane and lowered below the loading plane, and wherein, during this lowering of the support body, the module is passed to the second transverse conveyor unit while the second transfer position is traveled through.
5. A bonding arrangement comprising: a bonder; a feeder unit for a module that is adapted to be processed by the bonder; and a removal unit for the module, wherein the bonder includes at least one bonding head via which electrically conductive bond connections are be produced on the module during the processing of the module, wherein the bonder includes a vertical conveyor unit that is designed to convey the module vertically out of a loading plane into a bonding plane and/or into an unloading plane, wherein the bonder includes a first transverse conveyor unit that is associated with the loading plane and is designed to receive the module from the feeder unit, to bring the module into a first buffer position provided in the loading plane, and to bring the module into a first transfer position in which the module is made available for transfer to the vertical conveyor unit, and wherein the bonder includes a second transverse conveyor unit that is associated with the unloading plane and is designed to receive the module from the vertical conveyor unit in a second transfer position, to bring the module into a second buffer position, wherein the second transfer position and the second buffer position are provided in the unloading plane, and to pass the module to the removal unit that is associated with the unloading plane.
6. The bonding arrangement according to claim 5, wherein the bonding plane is provided above the loading plane and/or above the unloading plane.
7. The bonding arrangement according to claim 5, wherein the unloading plane is provided above the loading plane.
8. The bonding arrangement according to claim 5, wherein the first buffer position and/or the second buffer position, with respect to its horizontal location, is provided between the feeder unit and/or the removal unit and the first transfer position and/or the second transfer position.
9. The bonding arrangement according to claim 5, wherein the first buffer position and/or the second buffer position and/or the first transfer position and/or the second transfer position is provided in a machine housing of the bonder.
10. The bonding arrangement according to claim 5, wherein the feeder unit and/or the removal unit are associated with the bonder at a rear side and/or are arranged one above the other.
11. The bonding arrangement according to claim 5, wherein the bonding arrangement is designed to carry out the method comprising: feeding a module to a bonder from behind in a loading plane via a feeder unit; passing the module from the feeder unit to a first transverse conveyor unit, and is brought by the same to a first buffer position provided in the bonder, wherein the first buffer position is provided in a loading plane of the bonder; positioning the module from the first buffer position into a first receiving position in the loading plane via the first transverse conveyor unit and passing the module to a vertical conveyor unit; moving the vertical conveyor unit, the module is moved vertically and brought into a bonding plane, wherein the module in the bonding plane is located at least partially in a working area of the bonder; processing the module by a first bonding head and/or by a second bonding head, wherein electrically conductive bond connections are produced on the module; moving the module vertically by the vertical conveyor unit out of the bonding plane into a second transfer position, and in the second transfer position is passed to a second transverse conveyor unit, wherein the second transfer position is provided in an unloading plane of the bonder; positioning the module by the second transverse conveyor unit into a second buffer position in the unloading plane; and passing, from the second buffer position, the module to a removal unit via the second transverse conveyor unit.
12. The bonding arrangement according to claim 5, wherein the vertical conveyor unit has a vertically extending guide rail and a support body that is held movably on the guide rail.
13. The bonding arrangement according to claim 5, wherein the first transverse conveyor unit and/or the second transverse conveyor unit have carriages that are held so as to be horizontally movable and can be brought from the first buffer position into the first transfer position and/or from the second buffer position into the second transfer position.
14. The bonding arrangement according to claim 5, wherein at least two bonders are provided that are placed next to one another with two transverse sides of their machine housing facing one another, and wherein a shared feeder unit and/or a shared removal unit are associated with the bonders.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
(1) The present invention will become more fully understood from the detailed description given hereinbelow and the accompanying drawings which are given by way of illustration only, and thus, are not limitive of the present invention, and wherein:
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
DETAILED DESCRIPTION
(14) A bonding arrangement according to the invention as shown in
(15) The feeder unit 6 and the removal unit 7 are designed in the present case as roller conveyors, and are arranged to extend lengthwise in a transport direction 11. The removal unit 7 is provided above the feeder unit 6. The modules fed by means of the feeder unit 6 and removed by means of the removal unit 7, which are not shown in
(16) Different types of bonders 1, 2, 3, 4, 5, for example, can be provided within the bonding arrangement according to the invention.
(17) In accordance with
(18)
(19) According to
(20)
(21) The bonder 1 includes the machine housing 12. Provided in the machine housing 12 are a vertical conveyor unit 20, a first transverse conveyor unit 21, and a second transverse conveyor unit 22. The vertical conveyor unit 20 includes a guide rail 23 that extends vertically and a support body 24 that is movably held on the vertically oriented guide rail 23. The first transverse conveyor unit 21 provides a carriage 25 that is held so as to be horizontally movable, which in the present case is located in a first buffer position below the second transverse conveyor unit 22. From the first buffer position, the carriage 25 can be moved horizontally in the direction of the vertical conveyor unit 20 and arrive in a first transfer position in which a module is passed from the first transverse conveyor unit 21 to the vertical conveyor unit 20.
(22) In analogous fashion, the second transverse conveyor unit 22 provides a carriage 26, which, like the carriage 25 of the first transverse conveyor unit 21, is provided so as to be horizontally movable. The carriage 26 is positioned in a second buffer position. From the second buffer position, this can be moved horizontally in the direction of the vertical conveyor unit 20 into a second transfer position.
(23) The feeder unit 6 defines, together with the transverse conveyor unit 21, a loading plane 27 of the bonder 1, which is provided below an unloading plane 28 and a bonding plane 29. The unloading plane 28 is provided between the loading plane 27 and the bonding plane 29, and is defined by the removal unit 7 and the second transverse conveyor unit 22. Located above the unloading plane 28 is the bonding plane 29, in which a large module to be processed is provided during the processing.
(24) The support body 24 of the vertical conveyor unit 20 can be moved along the guide rail 23 in such a manner that the large module can be positioned in the bonding plane 29. In addition, the support body 24 can be lowered to below the loading plane 27.
(25) The method according to the invention and the details of the bonding arrangement according to the invention are described below on the basis of
(26) In order to now bond the second module 31, the support body 24 is lowered, along the guide rail 23, below the loading plane 27. In this process, the first module 30, which was bonded in the preceding method step, is placed on the carriage 26 of the second transverse conveyor unit 22] while the support body 24 travels through the second transfer position, see
(27) In the next method step according to
(28) Subsequently, the second module 31 is vertically lifted by the support body 24 and brought into the bonding plane 29. There, the second module 31 is pressed against a pressure plate 32 of the bonder 1 from below, and is thus positioned in terms of height. By means of the bonding head 15, the electrically conductive bond connections are formed on the first module 30, see
(29) According to
(30) The invention is not limited to the embodiment of the bonding arrangement shown, nor to the method discussed on the basis of the figures.
(31) For example, provision can be made that the feeder unit 6 and the removal unit 7 for the modules 30, 31, 33 are implemented in an integrated manner. In this regard, a single roller conveyor or another suitable transport device can serve simultaneously as feeder unit 6 and as removal unit 7. The loading plane 27 and the unloading plane 28 then coincide.
(32) For example, the modules 30, 31, 33 can be received from the feeder unit 6 by means of the first transverse conveyor unit 21 and moved into the machine housing 12 of the bonder 1. The carriage 25 of the first transverse conveyor unit 21, for example, can serve this purpose. For example, provision can be made that suitable means for lifting the modules 30, 31, 33 are provided on the feeder unit 6. For example, the feeder unit 6 and/or the first transverse conveyor unit 21 can have a separate handler for bringing the modules 30, 31, 33 into the first buffer position. The transfer of the modules 30, 31, 33 to the removal unit 7 can be accomplished in analogous fashion. In this regard, a suitable handler can be provided as part of the removal unit 7 and/or the modules 30, 31, 33 can be passed to the removal unit 7 by the second transverse conveyor unit 22.
(33) Within the bonding arrangement according to the invention, it is possible to provide bonders 1, 2, 3, 4, 5 that are all of the same type, or bonders 1, 2, 3, 4, 5 of different design. The bonders 1, 2, 3, 4, 5 can optionally be provided such that they are spaced apart laterally from one another. The full contact of the transverse sides of the bonders 1, 2, 3, 4, 5 is chosen merely by way of example in this respect.
(34) The invention being thus described, it will be obvious that the same may be varied in many ways. Such variations are not to be regarded as a departure from the spirit and scope of the invention, and all such modifications as would be obvious to one skilled in the art are to be included within the scope of the following claims.