Installation for combating flooding associated with spates of a waterway, including a mobile barrage, an acceleration station designed to pump water through or under the mobile barrage, from upstream of the mobile barrage to downstream when this barrage is in the active configuration, so as to increase the gradient of the stream upstream of the barrage and increase the flow rate.
Claims
1. An installation- for combating flooding associated with spates of a waterway, comprising: a mobile barrage, an acceleration station designed to pump water through or under the mobile barrage, from upstream of the mobile barrage to downstream when this barrage is in the active configuration, so as to increase the gradient of the stream upstream of the barrage and increase the flow rate.
2. The installation as claimed in claim 1, the acceleration station comprising at least one pumping unit.
3. The installation as claimed in claim 1, the acceleration station comprising at least one screen rake at the inlet to the acceleration station (11).
4. The installation as claimed in claim 1, the acceleration station being embedded in the bed of the waterway and/or located under the mobile barrage.
5. The installation as claimed in claim 1, the acceleration station resting on the foundations anchored in the bed of the waterway and the mobile barrage being supported by the foundations of the acceleration station.
6. The installation as claimed in claim 1, the acceleration station having a pumping capacity of at least 105% of the capacity of the non-equipped waterway.
7. The installation as claimed in claim 1, the water intake of the acceleration station being at least at 0.5 m from the water level upstream.
8. The installation as claimed in claim 1, comprising a means for detecting the level of the waterway upstream of the mobile barrage and the pumping power being adjusted in real time according to at least the detected level.
9. The installation as claimed in claim 1, the mobile barrage being permanently present on site and able to adopt a retracted configuration and a barrage-forming active configuration.
10. The installation as claimed in claim 9, the mobile barrage having flap gates.
11. The installation as claimed in claim 1, the mobile barrage being transportable so that it can be installed at the moment at which the acceleration station needs to be used.
12. The installation as claimed in claim 11, comprising submerged foundations that do not form obstacles to navigation when the acceleration station is not being used, and which are able to hold one or more submerged pumps in place at the moment at which the acceleration station needs to be used.
13. The installation as claimed in claim 1, comprising at least one lock configured to allow the mobile barrage and/or the acceleration station to be anchored to it.
14. A method for combating a risk of flooding associated with spates of a waterway, wherein a mobile barrage is fitted across the waterway and water is pumped through or under the mobile barrage at a flow rate high enough to lower the level of the water line upstream of the mobile barrage.
15. The method as claimed in claim 14, the water being pumped using an acceleration station permanently present on site.
16. The method as claimed in claim 14, the mobile barrage being permanently present on site.
17. The method as claimed in claim 16, the mobile barrage being submerged at a depth of at least 0.5 m when not in use.
18. The method as claimed in claim 14, the water being pumped using an acceleration station that is brought onto site at the time of its use, and that comprises one or more pumps that are submerged and held in place by foundations that already exist on the site.
19. The method as claimed in claim 14, the mobile barrage being brought onto site at the time of its use.
20. The method as claimed in claim 19, the mobile barrage being anchored to preexisting lock walls.
21. The method as claimed in claim 14, wherein the level of the waterway upstream of the mobile barrage is detected, and the pumping power is adjusted in real time according to at least the detected level.
Description
BRIEF DESCRIPTION OF THE FIGURES
[0041] The invention may be better understood from reading the following detailed description of some nonlimiting exemplary embodiments thereof and from studying the attached drawing, in which:
[0042]
[0043]
[0044]
[0045]
DETAILED DESCRIPTION OF THE INVENTION
[0046]
[0047] This installation 1 comprises an acceleration station 11 which is buried in the bed of the waterway and rests, for example, on concrete foundations 13. Thus, the acceleration station causes little or no disturbance to the flow of the water outside of the phases in which it is brought into service. The installation 1 also comprises a mobile barrage 17. The depth p by which the acceleration station 11 is submerged is preferably chosen to allow the waterway to remain navigable in the absence of the mobile barrage 17 or when the latter is inactive and the installation 1 is not in use. For example, the submersion depth p is at least 3 m below the free surface of the waterway.
[0048] The acceleration station 11 may be held in place in various ways and, for example, as illustrated, using foundations 13.
[0049] The acceleration station 11 comprises at least one pumping unit which allows, when the installation is in operation, the water upstream of the barrage 17 to be pumped downstream, in order to lower the upstream water level by a height H.
[0050] The acceleration station 11 may comprise any pumping unit suited to the desired flow rate.
[0051] Such a unit comprises a propeller-type turbine 19 and a motor 21, installed inside a bulb-shaped watertight casing 23, as illustrated in
[0052] A screen rake 18 may be positioned in front of the water intake to protect the installation against the unwanted ingestion of large floating objects and/or of bulky particles that could detract from the efficiency of the pumping or turbine action.
[0053] The mobile barrage 17 may be a permanent presence on site, and designed to adopt either an inactive configuration that does not excessively impede the navigability of the waterway or the flow of the water, or may be designed to adopt an active configuration forming a barrage against flow, as illustrated in
[0054] The mobile barrage 17 may comprise at least one barrage element that can be moved between two positions, one retracted and the other deployed. In the retracted configuration, the mobile barrage is completely submerged at a sufficient depth so as not to impede the navigability of the waterway and preferably not to impede the water flow excessively.
[0055] The mobile barrage is, for example, of the “flapgate barrage” type, comprising shutters known as “flapgates” which pivot at their base and can be raised to act as an obstacle to the flow.
[0056]
[0057] By way of example, given for a simplified configuration of waterway, if i is the flow gradient upstream and S is the cross section of the flow, given that the product S.sup.3i varies only little, doubling the gradient i allows S.sup.3 to be reduced by a factor of 2, the cross section S to be reduced by 20%, and the water level to be lowered by at least 1 m, making it possible to avoid flooding or to minimize the impact thereof.
[0058] Where appropriate, operation of the acceleration station 11 is slaved to the drop in level ΔH measured at the barrage 17. A setpoint value ΔH.sub.0 or any other associated parameter, can be input automatically or by an operator and the pumping power can be adapted in order to maintain the drop in level at the setpoint value.
[0059] This operation can be performed on site using an automatic controller, or remotely, the control data for the installation 1 being transmitted from a control station by any means, wired or otherwise.
[0060] The drop in level ΔH.sub.0 is chosen for example to be between 0.5 and 3 m.
[0061] Once the risk of spate has been removed, the mobile barrage 17 is deactivated, and in the event where it comprises flapgates, these are retracted. The acceleration station 11 is switched off
[0062] In the example of
[0063] In that case, it can be anchored to preexisting foundations, present for example on the bottom of the waterway. As an alternative or in addition, it is anchored to at least one lock wall, as illustrated in
[0064] This figure depicts two lock walls 20 made on the banks of the waterway. These lock walls 20 do not excessively impede the navigability of the waterway, as illustrated in
[0065] The lock walls 20 may be independent or connected by a raft.
[0066] In the event of a risk of spate, the acceleration station 11 is brought into position by river and temporarily sunk, as illustrated in
[0067] The mobile barrage 17 is brought into position by river between the lock walls 20 and positioned preferably above the acceleration station 11, being for example anchored to the lock walls 20, as illustrated in
[0068] The operation of the installation is then similar to that described hereinabove.
[0069] Once the risk of spate has been removed, the barrage and the acceleration station can be removed by river and stored ready for a subsequent use.
[0070] Of course, the invention is not restricted to the examples which have just been described. In particular, the installation according to the invention can be used in combination with other techniques for combating flooding, notably the deepening of the bed and/or the storage of water in reservoirs.
[0071] The mobile barrage may notably be produced in some other way; for example, it may comprise inflatable tubes held in position by a membrane.
[0072] Where appropriate, the mobile barrage and the acceleration station constitute a one-piece assembly which is brought onto site, for example being towed by river, then submerged at the desired location.