A method for in-line leak testing of blow moulded containers wherein a conveyor line is fed with a continuous stream of blow moulded containers from a blow moulding machine, at least one measuring head is temporarily connected to a first blow moulded container. The measuring head is moved in order to follow the movement of said first blow moulded container which is pressurized by a source of pressurized gas, the source of pressurized gas is disconnected, said at least one measuring head is used to measure the pressure decay therein. The pressure decay is compared with stored data for the pressure decay of acceptable containers and an accept or non-accept signal is generated which implies proceeding or disposal of said first blow moulded container. The measuring head is moved against the moving direction of the conveyor line to a subsequent blow moulded container, and the process is repeated.
Claims
1. A method for the in-line leak testing of blow moulded containers comprising: feeding a conveyor line with a continuous stream of blow moulded containers from a blow moulding machine, wherein at least one measuring head is temporarily tightly connected to a first blow moulded container, said at least one measuring head is moved in order to follow the movement of said first blow moulded container; pressurizing said first blow moulded container by a source of pressurized gas whereafter the source of pressurized gas is disconnected; measuring, with said at least one measuring head, the pressure decay in said first blow moulded container while following the movement of said first blow moulded container; comparing said measured pressure decay with stored data for the pressure decay of acceptable containers and an accept or non-accept signal is generated which implies proceeding or disposal of said first blow moulded container such that the at least one measuring head thereafter is moved against the moving direction of the conveyor line to a subsequent blow moulded container, is tightly connected to said subsequent blow moulded container, is moved in order to follow the movement of said subsequent blow moulded container and is used to perform in-line leak testing of said subsequent blow moulded container and to generate an accept or non-accept signal for said subsequent blow moulded container.
2. The method according to claim 1, wherein the measuring head is moved to an idle position before it is moved and tightly connected to the subsequent blow moulded container.
3. The method according to claim 1, wherein the idle position is located close to the entry point of the fed containers.
4. The method according to claim 1, wherein measuring heads are arranged in a group comprising two or more measuring heads, moving in unison to test two or more blow moulded containers simultaneously.
5. The method according to claim 1, wherein the blow moulded container has a volume of at least 0.5 L.
6. The method according to claim 1, wherein the measuring head is tightly connected to the blow moulded container for less than 3 seconds.
7. The method according to claim 1, wherein the rate of leak tested bottles is at least 100 per minute.
8. The method according to claim 1, wherein the blow moulded containers are not fed in a tight sequence on the conveyor line due to deviations in the blow moulding machine and the distance between two or more measuring heads is adapted to random gaps between the containers.
9. The method according to claim 4, wherein the position of the group of measuring heads is adapted to block gaps occurring in the sequence of containers on the conveyor line due to batch wise production of the containers.
10. The method according to claim 1, wherein the block gaps occurring in the sequence of containers on the conveyor line are used to move the group of measuring heads against the moving direction of the conveyor line, or to move the group of measuring heads close to the idle position, or to move the group of measuring heads to the idle position.
11. The method according to claim 1, wherein the speed of the conveyer belt is automatically reduced to allow sufficient time for measurement, if the point at which the measurement can be initiated, is so far from the entry point and so close to the discharge point from the leak-testing station that the time for measurement becomes critically small.
12. The method according to claim 1, wherein after the accept or non-accept signal is generated at least one measuring head is moved to and hold at an idle position and the remaining heads are tightly connected to subsequent blow moulded containers which are measured with higher sensitivity compared to when all measuring heads are tightly connected to blow moulded containers.
13. The method according to claim 1, wherein all measuring heads are tightly connected for a prolonged time period to subsequent blow moulded containers on the conveyor line in order to perform a leak testing with higher accuracy compared to when the blow moulded containers are fed in a tight sequence on the conveyor line.
14. The method according to claim 13, wherein said leak testing with higher accuracy reduces the number of false generated non-accept signals.
15. A device (10) for in-line leak testing of blow moulded containers comprising: a conveyor line fed with a continuous stream of blow moulded containers from a blow moulding machine; at least one measuring head arranged to move in parallel with the blow moulded containers and to temporarily tightly connect with a first blow moulded container and movable in order to follow the movement of said first blow moulded container, wherein the measuring head is equipped to pressurize the first blow moulded container and to measure the pressure decay in said first blow moulded container while following the movement of said first blow moulded container; a control unit equipped to compare the measured pressure decay with stored data for the pressure decay of acceptable containers and to generate an accept or non-accept signal which implies proceeding or disposal of said first blow moulded container wherein the at least one measuring head is equipped to be moved against the moving direction of the conveyor line to a subsequent blow moulded container, tightly connected to the subsequent blow moulded container, moved in order to follow the movement of said subsequent blow moulded container, used to perform in-line leak testing of said subsequent blow moulded container and to generate an accept or non-accept signal said for the subsequent blow moulded container.
16. The device for in-line leak testing of blow moulded containers according to claim 15, wherein the measuring head is connected to a source of pressurized gas wherein the connection can be opened and closed by an automatic valve.
17. The method according to claim 1, wherein measuring heads are arranged in a group comprising three or more measuring heads, moving in unison to test three or more blow moulded containers simultaneously.
18. The method according to claim 1, wherein the blow moulded container has a volume of at least 2 L.
19. The method according to claim 1, wherein the measuring head is tightly connected to the blow moulded container for less than 2 seconds.
20. The method according to claim 1, wherein the rate of leak tested bottles is at least 600 per minute.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Below, the present invention is described in form of a few non-limiting embodiments illustrated by figures, in which:
[0029]
[0030]
[0031]
[0032]
DETAILED DESCRIPTION
[0033] The terms “right”, “left”, “right-most” and “left-most” as used herein, are only in relation to the drawings, not intended to be general statements.
[0034]
[0035] As shown in
[0036] While not shown, the far right point of the conveyer belt is in communication with an upstream conveyer belt or the like feeding containers to the test station 10.
[0037] In
[0038] In
[0039] In
[0040]
[0041]
[0042]
[0043]
[0044] In
[0045] In
[0046] As shown by
[0047]
[0048] If even additional containers arrive without interruption, a situation may occur in which the point at which the measurement can be initiated, is so far from the entry point and so close to the discharge point from the leak-testing station 10 that the time for measurement becomes critically small. If or when that occurs, the speed of the conveyer belt 12 may be automatically reduced to allow sufficient time for measurement. When an interruption occurs, and the measuring heads again have the time to move back to the entry point, the speed can again be raised to normal.
[0049] Now referring to
[0050]
[0051] While embodiments of one and three measuring heads are mentioned above, other embodiments are feasible, such as four and even more measuring heads within the same leak-testing station.
[0052] In some embodiments, the blow moulded containers have a volume of at least 0.5 L, or at least 2 L or at least 10 L.
[0053] In some embodiments, the measuring head is tightly connected to the blow moulded container for less than 3 seconds, or less than 2 seconds or even less than 1 second.
[0054] In certain embodiments the rate of leak tested bottles is at least 100 per minute, or at least 600 per minute or at least 1200 per minute.
[0055] In some embodiments, the blow moulded containers are fed in a variable sequence on the conveyor line, e.g. due to deviations in the blow moulding machine, in which case the distances between two or more measuring heads are adapted to the actual (random) gaps between the containers.
[0056] In some embodiments the position of the group of measuring heads is adapted to block gaps occurring in the sequence of containers on the conveyor line due to batch wise production of the containers. Modern blow moulding machines operate frequently with several blow moulding heads in parallel and feed more or less tight blocks of containers onto the conveyor belt. After such a block of containers there is frequently a gap until the next block of containers is fed onto the conveyor belt.
[0057] In particular embodiments, the block gaps occurring in the sequence of containers on the conveyor line are used to move the group of measuring heads against the moving direction of the conveyor line and to move the group of measuring heads close to the idle position or to move the group of measuring heads to the idle position.
[0058] In some embodiments, after the accept or non-accept signal is generated, at least one measuring head is moved to and hold at an idle position and the remaining heads are tightly connected to subsequent blow moulded containers. Such a set-up allows a measurement with higher sensitivity compared to the set-up when all measuring heads are tightly connected to blow moulded containers.
[0059] In a particular embodiment all measuring heads are tightly connected for a prolonged time period to subsequent blow moulded containers on the conveyor line. This set-up allows to perform a leak testing with higher accuracy compared to when the blow moulded containers are fed in a tight sequence on the conveyor line. Leak testing with higher accuracy reduces the number of false generated non-accept signals.