SYSTEMS AND METHODS FOR ASSESSING RELIABILITY OF ELECTRICAL POWER TRANSMISSION SYSTEMS
20210126452 ยท 2021-04-29
Assignee
Inventors
Cpc classification
Y04S40/20
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
H02J3/0012
ELECTRICITY
H02J2203/20
ELECTRICITY
H02J3/00125
ELECTRICITY
Y02E60/00
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
International classification
Abstract
Systems and methods for assessing reliability of electrical power transmission systems are provided. Embodiments disclosed herein use Outage Impact Index (OII), a new reliability indicator, to identify periodic (e.g., annual) system risks in transmission systems of a bulk power system (BPS) for a given voltage class. OII provides key performance indices which can be used by power utilities to quantify and assess transmission system performance, establish baselines from chronological trends, and minimize system risks by developing corrective measures to address any identified system issues.
Claims
1. A method for assessing reliability of an electrical power transmission system, the method comprising: obtaining information about a number of outages in a specific outage category and power system voltage level during an assessment period; obtaining information about an outage duration associated with each of the number of outages during the assessment period; and determining outage impact for the assessment period as a function of the number of outages and the outage duration for the specific outage category and power system voltage level independent of total outages and total outage duration for the electrical power transmission system.
2. The method of claim 1, wherein the outage impact is further a function of the number of outages over a number of power system assets.
3. The method of claim 1, wherein the outage impact is further a function of the outage duration over the assessment period.
4. The method of claim 1, wherein determining the outage impact is performed according to a formula given by:
5. The method of claim 4, wherein the outage impact index provides a measure of equipment health in the electrical power transmission system.
6. The method of claim 4, wherein the assessment period comprises at least one year.
7. The method of claim 1, wherein each of the number of outages represents a failure of one or more power system assets in the electrical power transmission system.
8. The method of claim 7, wherein the failure of the one or more power system assets is considered an outage irrespective of a loss of power to a customer of the electrical power transmission system.
9. A method for assessing reliability of an electrical power transmission system, the method comprising: obtaining a first number of outages in a first set of power system assets during an assessment period, wherein an outage is defined as a failure of at least one of the first set of power system assets; obtaining a first outage duration associated with the first number of outages; and determining a first outage effect for the assessment period as a function of the first number of outages for the first set of power system assets and the first outage duration for the assessment period.
10. The method of claim 9, wherein determining the first outage effect for the assessment period is performed according to a formula given by:
11. The method of claim 9, wherein the first set of power system assets comprises power system assets in the electrical power transmission system having a first voltage level and a first outage category.
12. The method of claim 11, wherein the first outage duration is a total outage duration for the first number of outages of the first set of power system assets in the electrical power transmission system having the first voltage level and the first outage category.
13. The method of claim 11, further comprising, for each of a plurality of voltage levels and each of a plurality of outage categories: obtaining a respective number of outages in a respective set of power system assets having a given voltage level of the plurality of voltage levels and a given outage category of the plurality of outage categories during the assessment period; obtaining a respective outage duration associated with the respective number of outages; and determining a respective outage effect for the assessment period as a function of the respective number of outages for the respective set of power system assets and the respective outage duration for the assessment period.
14. The method of claim 13, further comprising determining an outage impact index, comprising the first outage effect and each of the respective outage effects for each of the plurality of voltage levels and each of the plurality of outage categories.
15. The method of claim 14, wherein determining the outage impact index is performed according to a formula given by:
16. The method of claim 10, wherein the assessment period is one year.
17. The method of claim 10, wherein the assessment period is one month.
18. The method of claim 10, wherein the assessment period is user-definable.
19. A reliability assessment system, comprising: a database comprising outage information for an electrical power transmission system; and a processing device coupled to the database and configured to: obtain a number of outages in a set of power system assets of the electrical power transmission system during an assessment period, wherein each outage represents a failure of a power system asset irrespective of a loss of power to a customer; obtain an outage duration for the number of outages during the assessment period; and determine an outage impact for the assessment period as a function of the number of outages for the set of power system assets and the outage duration for the assessment period.
20. The reliability assessment system of claim 19, wherein the outage impact is further a function of the number of outages over the number of power system assets and the outage duration over the assessment period.
Description
BRIEF DESCRIPTION OF THE DRAWING FIGURES
[0016] The accompanying drawing figures incorporated in and forming a part of this specification illustrate several aspects of the disclosure, and together with the description serve to explain the principles of the disclosure.
[0017]
[0018]
[0019]
[0020]
[0021]
[0022]
[0023]
[0024]
[0025]
[0026]
[0027]
[0028]
[0029]
[0030]
[0031]
[0032]
[0033]
[0034]
[0035]
[0036]
[0037]
[0038]
[0039]
[0040]
[0041]
[0042]
[0043]
[0044]
DETAILED DESCRIPTION
[0045] The embodiments set forth below represent the necessary information to enable those skilled in the art to practice the embodiments and illustrate the best mode of practicing the embodiments. Upon reading the following description in light of the accompanying drawing figures, those skilled in the art will understand the concepts of the disclosure and will recognize applications of these concepts not particularly addressed herein. It should be understood that these concepts and applications fall within the scope of the disclosure and the accompanying claims.
[0046] It will be understood that, although the terms first, second, etc. may be used herein to describe various elements, these elements should not be limited by these terms. These terms are only used to distinguish one element from another. For example, a first element could be termed a second element, and, similarly, a second element could be termed a first element, without departing from the scope of the present disclosure. As used herein, the term and/or includes any and all combinations of one or more of the associated listed items.
[0047] It will be understood that when an element such as a layer, region, or substrate is referred to as being on or extending onto another element, it can be directly on or extend directly onto the other element or intervening elements may also be present. In contrast, when an element is referred to as being directly on or extending directly onto another element, there are no intervening elements present. Likewise, it will be understood that when an element such as a layer, region, or substrate is referred to as being over or extending over another element, it can be directly over or extend directly over the other element or intervening elements may also be present. In contrast, when an element is referred to as being directly over or extending directly over another element, there are no intervening elements present. It will also be understood that when an element is referred to as being connected or coupled to another element, it can be directly connected or coupled to the other element or intervening elements may be present. In contrast, when an element is referred to as being directly connected or directly coupled to another element, there are no intervening elements present.
[0048] Relative terms such as below or above or upper or lower or horizontal or vertical may be used herein to describe a relationship of one element, layer, or region to another element, layer, or region as illustrated in the Figures. It will be understood that these terms and those discussed above are intended to encompass different orientations of the device in addition to the orientation depicted in the Figures.
[0049] The terminology used herein is for the purpose of describing particular embodiments only and is not intended to be limiting of the disclosure. As used herein, the singular forms a, an, and the are intended to include the plural forms as well, unless the context clearly indicates otherwise. It will be further understood that the terms comprises, comprising, includes, and/or including when used herein specify the presence of stated features, integers, steps, operations, elements, and/or components, but do not preclude the presence or addition of one or more other features, integers, steps, operations, elements, components, and/or groups thereof.
[0050] Unless otherwise defined, all terms (including technical and scientific terms) used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this disclosure belongs. It will be further understood that terms used herein should be interpreted as having a meaning that is consistent with their meaning in the context of this specification and the relevant art and will not be interpreted in an idealized or overly formal sense unless expressly so defined herein.
[0051] Systems and methods for assessing reliability of electrical power transmission systems are provided. Embodiments disclosed herein use Outage Impact Index (OII), a new reliability indicator, to identify periodic (e.g., annual) system risks in transmission systems of a bulk power system (BPS) for a given voltage class. OII provides key performance indices which can be used by power utilities to quantify and assess transmission system performance, establish baselines from chronological trends, and minimize system risks by developing corrective measures to address any identified system issues.
[0052] I. Transmission System Reliability
[0053]
[0054] Voltage levels are stepped up from the power generation level 14 to the transmission level 16. A transmission substation 22 can receive power from one or multiple generating sources 24 in the power generation level 14, and step down or transfer the received power as appropriate. In some embodiments, voltage levels are stepped down from the transmission level 16 to the distribution level 18, and from the distribution level 18 to the load center level 20. This voltage step down is provided through one or more subtransmission substations 26 and/or distribution substations 28. However, voltage levels may vary between different branches of the power system 10. In addition, different load centers 30 may receive different voltage needs, including multiple voltage levels, according to consumption needs.
[0055] The ability of the power system 10 to perform its required function within a specified time frame and meet the expected performance criteria is termed as reliability. According to the North American Electric Reliability Corporation (NERC), the definition of reliability of a BPS (e.g., the power system 10) is the ability of the system to withstand disturbances and meet consumer demands consistently. Reliability of the power system 10 ensures secure transfer of uninterrupted power from the generating sources 24 to the load centers 30 and is thus of utmost importance to both utilities and consumers. Unreliability of the power system 10 may lead to cascading failures resulting in brownouts or blackouts.
[0056] Reliability of the power system 10 can be measured in terms of frequency, duration, and magnitude of damage caused by transmission line 12 outages. Quantitative evaluation of reliability is a crucial component during planning, design, operation, and maintenance phases of the power system 10. Furthermore, detailed analysis of system reliability may reveal vulnerable areas in the transmission network and establish a chronological system performance that would serve as a guideline for future reliability assessment.
[0057] Embodiments described herein introduce OII as a new metric which measures reliability of the transmission network on an annual basis using both outage frequency and duration. This metric can further evaluate severity of transmission line outages on the basis of outage category using historical transmission outage data.
[0058] II. Transmission Network Outages
[0059] A. State of a Transmission Line
[0060]
[0061] Forced outages can be further classified based on duration as: [0062] Momentary Outage: Outage duration of less than 1 minute (usually restored by an auto reclosing/re-energizing of the asset post-fault). [0063] Sustained Outage: Outage duration of 1 minute or longer.
Both types of forced outages, that is, momentary and sustained, are considered in the analysis which follows.
[0064] B. Outage Categories
[0065] Power system asset (e.g., transmission line) performance depends on a variety of factors ranging from malfunctioning of power system components to environmental conditions, such as storms. The power industry broadly categorizes transmission outages as: 1) equipment; 2) system protection; 3) lines; 4) weather; 5) lightning; 6) unknown; 7) external; 8) other; and 9) human factors. These categories are further coded into outage subcategories as described in Table 1, and the abbreviations are expanded in Table 2 below.
TABLE-US-00001 TABLE 1 Coding of outage categories into outage cause codes SI. No. Outage Category Outage Cause 1 Equipment AC, BK, SU, VA 2 System Protection CO 3 Lines PO, XF 4 Weather WI, ST 5 Lightning LI 6 Unknown UN, KV, FT 7 External PC, FS, KV 8 Other HU, AN, AU, BI, CN, DE, FI 9 Human Factors IP, SP
TABLE-US-00002 TABLE 2 Expansion of outage cause code abbreviations Abb. Description AC AC Circuit Equipment AN Animals AU Vehicle Caused BI Bird Contact BK Breaker Failure CN Contamination CO Communications, Control, Relay DE Debris in Equipment FI Fire FS Foreign System FT Fault HU Inadvertent By Public IP Inadequate Procedures KV Underbuilt Line LC Shunt Capacitor or Reactor Failure LI Lightning PC Power System Condition PO Pole Failure SP Inadvertent By Utility ST Storm SU AC Substation Equipment Failure UN Unknown VA Vandalism XF Transformer Failure WI Wind
[0066] III. Outage and Reliability Analysis
[0067] A. Historical Transmission Outage Data
[0068] Before discussing specifics of systems and methods providing the novel reliability metric OII, an analysis to compare other approaches to assessing reliability of the exemplary power system 10 of
[0069] In this analysis, the transmission system performance and reliability are evaluated based on the historical forced outage data for the 69-500 kilovolt (kV) voltage levels for the time-period 2009-2016. An inventory of transmission lines (e.g., power system assets) for the utility network is given in Table 3. It is observed that the 69 kV network has the highest number of assets, followed by 230 kV, 115 kV and 500 kV. In terms of mileage, 69 kV lines also have the highest mileage individually.
TABLE-US-00003 TABLE 3 Utility transmission inventory Transmission line inventory 69 kV 115 kV 230 kV 500 kV Total Line Mileage 1025 264 1125 2414 No. of Assets 296 21 39 18 374
[0070] B. Traditional Approaches to Assessing Reliability
[0071] Table 4 lists forced outage per hundred miles per year (FOHMY) trends for the years 2009-2016. It can be observed that, although the FOHMY value for 69 kV lines for 2009 is higher than that of 69 kV lines for 2016, the frequency of outages is identical for the corresponding years. This is due to an increase in line mileage in the year 2016. In this case however, a lower FOHMY value does not indicate that reliability of the 69 kV lines improved in the year 2016. Similarly, for the 115 kV lines, in the year 2015, the FOHMY value is comparable to that of 69 kV lines for the years 2009 and 2016. However, the outage percentage with respect to the total number of lines for 115 kV lines in 2015 was around 71% compared to 20% of 69 kV lines in the corresponding years. Thus, FOHMY alone cannot be used to comprehensively evaluate reliability of the transmission lines.
TABLE-US-00004 TABLE 4 FOHMY trends for the years 2009-2016 FOHMY 2009 2010 2011 2012 2013 2014 2015 2016 Mileage 910.6 914.9 916.9 916.2 992.6 992.6 1024.3 1024.3 Frequency 59 60 63 48 32 55 61 59 69 kV 6.479 6.558 6.871 5.239 3.224 5.541 5.955 5.76 Mileage 264 264 264 264 264 264 264 264.3 Frequency 19 22 14 14 19 8 15 10 115 kV 7.197 8.333 5.303 5.303 7.197 3.03 5.682 3.784 Mileage 1015 979.6 958.1 1001.1 953.7 1004.1 1020.1 1124.7 Frequency 4 14 8 9 5 9 7 5 230-500 kV 0.394 1.429 0.835 0.899 0.524 0.896 0.686 0.445
[0072]
[0073]
[0074]
[0075]
[0076]
[0077]
[0078]
[0079]
[0080] With reference to
[0081] In 2008, NERC approved implementation of TADS Phase I which required U.S. transmission owners to report automatic outages beginning in 2008 for AC circuits with voltage levels at or above 200 kV. Some of the reliability metrics developed for reporting transmission outages were:
[0082] Outage frequency per 100 Circuit Miles (FOHMY)
[0083] Total Element Outage Frequency (TOF)
[0084] Total Element Outage Duration (TOD)
[0085] Mean Time Between Failure (MTBF)
[0086] Mean Time To Repair (MTTR)
[0087] Availability
[0088]
[0089] Thus, it can be concluded that FOHMY cannot capture the impact of the outage duration and would therefore not give an accurate representation of transmission line outage severity or reliability in its entirety. This is due to the fact that FOHMY definition is not inclusive of the outage duration. The definitions of TOF and TOD are given below:
[0090] TOF is a representation of the outage frequency per transmission element per year and is mathematically defined by:
[0091] TOD is a representation of the outage hours per transmission element per year and is mathematically defined by:
[0092] The remaining TADS metrics such as MTBF, MTTR and Availability are described below with respect to
[0093] With reference to
[0094]
[0095]
[0096] Exposure time is considered to be 1 year. From
[0097]
[0098] With reference to
[0099] Exposure time is assumed to be 1 year. It is observed that AOD for 69 kV is the highest followed by 115 kV, 230 kV, and 500 kV, respectively. The AOD of 69 kV is also observed to follow a decreasing trend in general except between 2013-2015. For higher voltage levels, the trend is observed to be decreasing in general except for peaks in 2012 (500 kV), 2013 (115 kV) and 2016 (230 kV). In general, over the study period of the historical data, the AOD for the entire 69 kV network is observed to be above 100 hours per year while that for 115 kV is observed to be at an average of 50 hours per year. AOD for 230 kV and 500 kV is observed to be insignificant as compared to 69 kV and 115 kV; however, a peak in AOD is observed for 500 kV lines in the year 2012.
[0100]
[0101] With reference to
[0102]
[0103] It is observed that MTBF is highest for 500 kV followed by the lower operating voltage lines. Higher values of MTBF are desirable as they indicate a lower number of failures within a specified period. Exposure time is 8760 hours (=1 year).
[0104]
[0105] It is observed that MTTR for 69 kV is the highest and it is lower for higher voltages which is desirable as it indicates better maintainability. However, a peak in MTTR was observed for 500 kV in 2012 and for 230 kV in 2016. Low values of MTTR are desired because it indicates efficient repair works.
[0106]
[0107] It is observed that availability of the transmission lines rated higher than 69 kV is more than 97% throughout the study period. For 69 kV, the availability was observed to be above 97% except for the years 2010 and 2015. Thus, the overall availability of the transmission network under study is very high. Based on the outage analysis and reliability evaluation done above, a chronological trend in outage duration and frequency can be established. This can then become the basis for future reliability assessments.
[0108] Table 5 below lists outage categories based on the longest outage duration as well as the maximum/minimum frequency of occurrence. It is observed from Table 5 that the longest outage duration category may not correspond to the most frequently occurring outage category. Hence, focusing only on the number of outages (which is what FOHMY does) would provide information regarding the outage frequency and not the outage duration. As such, it may not be possible to distinguish between two contrasting situations where frequent outages are characterized by lower interrupted durations, as is observed in Table 5 for 69-230 kV lines. To cite an example, for 69 kV lines, it is observed that wind-related outages (WI) are of the longest duration while Debris in Equipment (DE) outages occur most frequently. Therefore, as the most frequent outage type is not necessarily the one that has the longest duration, both frequency and duration should be considered as independent indicators of transmission reliability. This inference becomes the basis of the formulations for Susceptibility Index (SI) and Outage Impact Index (OII), described below with respect to Tables 6-8 and
TABLE-US-00005 TABLE 5 Outage classification on maximum duration and frequency Circuit Longest Most Least Voltage Duration Frequent Frequent 69 kV WI DE IP, LC, VA* 115 kV ST LI XF, AU, KV* 230 kV AC SP, BI* XF, FT, SU* 500 kV FS FS XF, BK, FT* *Multiple entries indicate equal frequency of occurrence
[0109] C. Susceptibility Index (SI)
[0110] SI, derived from Severity Factor by dropping the term corresponding to loss of load (as this data is not usually recorded for every outage), for an outage category and voltage level v (e.g., 69, 115, 230 or 500 kV) is given by:
[0111] where N.sub.,v is the number of outages for category and voltage level v, N.sub.v is the total number of outages for voltage level v, IT.sub.,v is the outage duration for category a and voltage level v. This comprehensive index identifies the most severe outage category by comparing the outage category's () frequency and duration to the total outage frequency and duration for the voltage class v.
[0112] Table 6 below lists SI values for each outage category and voltage level, where higher values indicate more severe outages. It is observed that 69 kV is most susceptible to the outage category Other, followed by Weather and Equipment. For 115 kV, Weather is the most significant category followed by Other and Equipment. For 230 kV, Equipment is the most significant category followed by Other and Human Factors. For 500 kV, the most significant category is External, followed by Other and System Protection.
TABLE-US-00006 TABLE 6 Outage classification based on Susceptibility Index (SI) Outage Outage Category Cause 69 kV 115 kV 230 kV 500 kV 1-Equipment AC, BK, 0.0080 0.0097 0.0764 2.21E05 SU, VA 2-System CO 0.0003 0.0033 0.0030 0.0050 Protection 3-Lines PO, XF 0.0034 0.0030 0 0 4-Weather WI, ST 0.0221 0.0542 0.0001 0 5-Lightning LI 0.0002 0.0025 0 0.0003 6-Unknown UN, KV, 0.0010 0.0007 2.61E05 2.76E05 FT 8-External PC, FS, 7.11E05 0.0047 0.0022 0.2359 KV 9-Other HU, AN, 0.0963 0.0364 0.0603 0.0085 AU, BI, CN, DE, FI 12-Human IP, SP 3.40E05 3.45E05 0.0041 0.0008 Factors
[0113] Table 7 provides a comparison of annual SI for 500 kV lines for the years 2009 and 2012 for outage category External (8). While SI is useful in identifying the severity of outage categories specific to a voltage class, it is not useful for comparing outage severity across different years. For example, in Table 7 it is observed that although the frequency and duration of outages for the year 2009 was lower than that in 2012, the respective SI values for 2009 (1) and 2012 (0.3929) are not indicative of the severity of the outages in terms of outage duration or frequency. This is because SI is a relative frequency and duration product, and it calculates the severity specific to a year, outage category and voltage level v. It cannot be used for comparing the severity of outages across different years because the severity is not compared with a common base. The base depends on N.sub.v and IT.sub.,v, which vary according to the year of study and the outage category. Thus, SI values, and by extension, Severity Factor, for an outage category are not comparable when calculated annually.
TABLE-US-00007 TABLE 7 Comparison of Annual Susceptibility Index (SI) for 2009 and 2012 2009 2012 2009 2012 2009 2012 500 kV Frequency (#) Duration (mins) SI 1-Equipment 0 0 0 0 0 0 2-System 0 1 0 8 0 0.0002 Protection 3-Lines 0 0 0 0 0 0 4-Weather 0 0 0 0 0 0 5-Lightning 0 0 0 0 0 0 6-Unknown 0 0 0 0 0 0 8-External 2 3 214 5778 1 0.3929 9-Other 0 1 0 1543 0 0.0349 12-Human 0 1 0 24 0 0.0005 Factors Total 2 6 214 7353
[0114] D. Outage Impact Index (OII)
[0115] With reference to Table 8 and
[0116] The proposed index, OII, is mathematically defined by
OII.sub.,v is the outage impact index for category and voltage level v. N.sub.,v is the number of outages for category and voltage level v. T.sub.v is the total number of power system assets having voltage level v. IT.sub.,v is the outage duration for category and voltage level v. ET.sub.v is the exposure time for an assessment period (e.g., one year=8,760 hours, one month, or another period of time as appropriate, such as a user-definable assessment period).
[0117] It should be understood that OII is used to measure outages of any one or more assets of an electrical power transmission system, such as a transmission line, circuit breaker, transformer, reactor, or other circuit or structure. It should be further understood that an outage as measured by OII is defined as a failure of any one or more of these assets, irrespective of any loss of failure to a customer (e.g., a load center 30 in
[0118] Table 8 presents corresponding OII values for the example described in Table 7. It is observed from Table 8 that OII gives an accurate representation of outage severity for years 2009 (4.52E-05) and 2012 (0.0018) in contrast to SI values of 1 and 0.39 for the same years (obtained in Table 7). Accordingly, outage severity for the outage category External (8) is higher for the year 2012 as compared to the year 2009. This index makes it possible to compare severity for each category on an annual basis, unlike SI or Severity Factor.
TABLE-US-00008 TABLE 8 Outage classification on maximum duration and frequency 2009 2012 2009 2012 2009 2012 500 kV Frequency (#) Duration (mins) OII 1-Equipment 0 0 0 0 0 0 2-System 0 1 0 8 0 8.45E07 Protection 3-Lines 0 0 0 0 0 0 4-Weather 0 0 0 0 0 0 5-Lightning 0 0 0 0 0 0 6-Unknown 0 0 0 0 0 0 8-External 2 3 214 5778 4.52E05 0.0018 9-Other 0 1 0 1543 0 0.0002 12-Human 0 1 0 24 0 2.52E06 Factors Total 2 6 214 7353
[0119] E. Analysis of OII
[0120]
[0121]
[0122]
[0123]
[0124]
[0125] Finally, corrective action such as operation practices, maintenance strategies, and spare management can be developed based on the analysis results. It is important to mention here that identification and prioritization of outages based on frequency and duration as has been done above is not possible with FOHMY.
[0126] The impact of transmission line outages in terms of load lost (in megawatts (MW)) can also be incorporated in the definition of OII, if that information is available. This can be included in the form of a ratio in terms of the total rated capacity of the line. Based on the severity of outages categories identified by OII, further reliability and root-cause analysis may need to be carried out to identify potential system risks and take corrective action.
[0127] IV. Process for Assessing Reliability (Using OII)
[0128]
[0129]
[0130] In an exemplary aspect, the outage effect of
[0131] The outage effect may be mathematically defined by
OE is the outage effect (which may be for one or multiple outage categories and one or more voltage levels). N is the number of outages. T is the number of power system assets being measured. IT is the outage duration for the assets being measured. ET is the exposure time for an assessment period (e.g., one year=8,760 hours, one month, or another period of time as appropriate, such as a user-definable assessment period). In some examples, multiple outage effects may be amalgamated to provide the OII as defined in Equation 10.
[0132] Although the operations of
[0133] V. Computer System
[0134]
[0135] The exemplary computer system 1500 in this embodiment includes a processing device 1502 or processor, a main memory 1504 (e.g., read-only memory (ROM), flash memory, dynamic random access memory (DRAM), such as synchronous DRAM (SDRAM), etc.), and a static memory 1506 (e.g., flash memory, static random access memory (SRAM), etc.), which may communicate with each other via a data bus 1508. Alternatively, the processing device 1502 may be connected to the main memory 1504 and/or static memory 1506 directly or via some other connectivity means. In an exemplary aspect, the processing device 1502 could be used to perform any of the methods or functions described above.
[0136] The processing device 1502 represents one or more general-purpose processing devices, such as a microprocessor, central processing unit (CPU), or the like. More particularly, the processing device 1502 may be a complex instruction set computing (CISC) microprocessor, a reduced instruction set computing (RISC) microprocessor, a very long instruction word (VLIW) microprocessor, a processor implementing other instruction sets, or other processors implementing a combination of instruction sets. The processing device 1502 is configured to execute processing logic in instructions for performing the operations and steps discussed herein.
[0137] The various illustrative logical blocks, modules, and circuits described in connection with the embodiments disclosed herein may be implemented or performed with the processing device 1502, which may be a microprocessor, field programmable gate array (FPGA), a digital signal processor (DSP), an application-specific integrated circuit (ASIC), or other programmable logic device, a discrete gate or transistor logic, discrete hardware components, or any combination thereof designed to perform the functions described herein. Furthermore, the processing device 1502 may be a microprocessor, or may be any conventional processor, controller, microcontroller, or state machine. The processing device 1502 may also be implemented as a combination of computing devices (e.g., a combination of a DSP and a microprocessor, a plurality of microprocessors, one or more microprocessors in conjunction with a DSP core, or any other such configuration).
[0138] The computer system 1500 may further include a network interface device 1510. The computer system 1500 also may or may not include an input 1512, configured to receive input and selections to be communicated to the computer system 1500 when executing instructions. The input 1512 may include, but not be limited to, a touch sensor (e.g., a touch display), an alphanumeric input device (e.g., a keyboard), and/or a cursor control device (e.g., a mouse). The computer system 1500 also may or may not include an output 1514, including but not limited to a display, a video display unit (e.g., a liquid crystal display (LCD) or a cathode ray tube (CRT)), or a printer. In some examples, some or all inputs 1512 and outputs 1514 may be combination input/output devices.
[0139] The computer system 1500 may or may not include a data storage device that includes instructions 1516 stored in a computer-readable medium 1518. The instructions 1516 may also reside, completely or at least partially, within the main memory 1504 and/or within the processing device 1502 during execution thereof by the computer system 1500, the main memory 1504, and the processing device 1502 also constituting computer-readable medium. The instructions 1516 may further be transmitted or received via the network interface device 1510.
[0140] While the computer-readable medium 1518 is shown in an exemplary embodiment to be a single medium, the term computer-readable medium should be taken to include a single medium or multiple media (e.g., a centralized or distributed database, and/or associated caches and servers) that store the one or more sets of instructions 1516. The term computer-readable medium shall also be taken to include any medium that is capable of storing, encoding, or carrying a set of instructions for execution by the processing device 1502 and that causes the processing device 1502 to perform any one or more of the methodologies of the embodiments disclosed herein. The term computer-readable medium shall accordingly be taken to include, but not be limited to, solid-state memories, optical medium, and magnetic medium.
[0141] The operational steps described in any of the exemplary embodiments herein are described to provide examples and discussion. The operations described may be performed in numerous different sequences other than the illustrated sequences. Furthermore, operations described in a single operational step may actually be performed in a number of different steps. Additionally, one or more operational steps discussed in the exemplary embodiments may be combined.
[0142] Those skilled in the art will recognize improvements and modifications to the preferred embodiments of the present disclosure. All such improvements and modifications are considered within the scope of the concepts disclosed herein and the claims that follow.