Method for dividing brittle-material substrate
10927031 ยท 2021-02-23
Assignee
Inventors
Cpc classification
B28D5/0011
PERFORMING OPERATIONS; TRANSPORTING
B28D1/225
PERFORMING OPERATIONS; TRANSPORTING
International classification
Abstract
A cutter edge is pressed against a brittle-material substrate so that a protruding portion of the cutter edge is positioned between a first edge of the brittle-material substrate and a side portion of the cutter edge and that a side portion of the cutter edge is positioned between the protruding portion of the cutter edge and a second edge of the brittle-material substrate. A scribe line is formed by a scratch between a first position closer to the first edge of the first and second edges and a second position closer to the second edge of the first and second edges. After the formation of the scribe line, a crack is extended in a thickness direction from the second position toward the first position along the scribe line, thus forming a crack line.
Claims
1. A method for dividing a brittle-material substrate, the method comprising: preparing a brittle-material substrate made of glass material and including a surface and having a thickness direction perpendicular to said surface, said surface being surrounded by a perimeter including first and second edges opposite to each other; pressing a cutter edge against said surface of said brittle-material substrate, said cutter edge including a protruding portion and a side portion extending from said protruding portion and having a convex shape; forming, by plastic deformation, a scribe line having a groove shape involving no vertical crack, said scribe line being formed between a first position closer to said first edge and a second position closer to said second edge on said surface of said brittle-material substrate by causing said cutter edge pressed in said pressing to slide on said surface of said brittle-material substrate; after said forming the scribe line, forming a crack line by cracking said brittle-material substrate in said thickness direction, from said second position toward said first position along said scribe line; dividing said brittle-material substrate along said crack line, wherein said forming the scribe line is performed by forming the scribe line spaced away from said perimeter, and the method further comprises forming an assist line by cracking said brittle-material substrate in said thickness direction, said assist line and said scribe line intersecting each other at said second position, wherein said step of forming the crack line is commenced at said second position.
2. The method for dividing a brittle-material substrate according to claim 1, wherein said forming the assist line is performed after said forming the scribe line.
3. The method for dividing a brittle-material substrate according to claim 1, wherein said forming the assist line is performed before said forming the scribe line.
4. The method for dividing a brittle-material substrate according to claim 1, wherein in said forming the scribe line, said cutter edge is pressed against said surface of said brittle-material substrate with a greater force at said second position than at said first position.
5. The method for dividing a brittle-material substrate according to claim 1, wherein said cutter edge includes first to third surfaces adjacent to each other, a vertex at which said first to third surfaces meet, and a ridge formed by said second and third surfaces, and said protruding portion of said cutter edge comprises said vertex, and said side portion of said cutter edge comprises said ridge.
6. The method for dividing a brittle-material substrate according to claim 1, wherein said cutter edge has a shape of a cone including a vertex and a conical surface, and said protruding portion of said cutter edge comprises said vertex, and said side portion of said cutter edge is formed along an imaginary line extending from said vertex on said conical surface.
7. The method for dividing a brittle-material substrate according to claim 1, wherein said forming the scribe line comprises displacing said cutter edge from said first position to said second position.
8. The method for dividing a brittle-material substrate according to claim 1, wherein said forming a scribe line comprises displacing said cutter edge from said second position to said first position.
9. A method for dividing a brittle-material substrate, the method comprising: preparing a brittle-material substrate made of glass material and including a surface and having a thickness direction perpendicular to said surface, said surface being surrounded by a perimeter including first and second edges opposite to each other; pressing a cutter edge against said surface of said brittle-material substrate, said cutter edge including a protruding portion and a side portion extending from said protruding portion and having a convex shape; forming, by plastic deformation, a scribe line having a groove shape involving no vertical crack, said scribe line being formed between a first position closer to said first edge and a second position closer to said second edge on said surface of said brittle-material substrate by causing said cutter edge pressed in said pressing to slide on said surface of said brittle-material substrate; said scribe line being spaced away from said perimeter, and forming an assist line on said brittle-material substrate, said assist line and said scribe line intersecting each other at said second position, and applying a first stress to said assist line to cause cracking of said brittle-material substrate in said thickness direction along said assist line, wherein forming a crack line along said scribe line is commenced by applying said first stress to said brittle-material substrate to separate said brittle-material substrate along said assist line, thereby initiating formation of said crack line from said second position for division of said brittle-material substrate along said crack line.
10. The method for dividing a brittle-material substrate according to claim 9, wherein said forming said assist line comprises forming said assist line on another surface that is located opposite to said surface of said brittle-material substrate.
11. The method for dividing a brittle-material substrate according to claim 9, wherein the division of said brittle-material substrate along said crack line is initiated by said first stress.
12. The method for dividing a brittle-material substrate according to claim 9, further comprising applying a second stress to said crack line to initiate the division of said brittle-material substrate along said crack line.
13. The method for dividing a brittle-material substrate according to claim 9, wherein said forming the assist line is performed after said forming the scribe line.
14. The method for dividing a brittle-material substrate according to claim 9, wherein said forming the assist line is performed before said forming the scribe line.
15. The method for dividing a brittle-material substrate according to claim 9, wherein in said forming the scribe line, said cutter edge is pressed against said surface of said brittle-material substrate with a greater force at said second position than at said first position.
16. The method for dividing a brittle-material substrate according to claim 9, wherein said cutter edge includes first to third surfaces adjacent to each other, a vertex at which said first to third surfaces meet, and a ridge formed by said second and third surfaces, and said protruding portion of said cutter edge comprises said vertex, and said side portion of said cutter edge comprises said ridge.
17. The method for dividing a brittle-material substrate according to claim 9, wherein said cutter edge has a shape of a cone including a vertex and a conical surface, and said protruding portion of said cutter edge comprises said vertex, and said side portion of said cutter edge is formed along an imaginary line extending from said vertex on said conical surface.
18. The method for dividing a brittle-material substrate according to claim 9, wherein said forming the scribe line comprises displacing said cutter edge from said first position to said second position.
19. The method for dividing a brittle-material substrate according to claim 9, wherein said forming a scribe line comprises displacing said cutter edge from said second position to said first position.
Description
BRIEF DESCRIPTION OF DRAWINGS
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
(17)
(18)
(19)
(20)
(21)
(22)
(23)
(24)
(25)
(26)
DESCRIPTION OF EMBODIMENTS
(27) Embodiments of the present invention will be described below with reference to the drawings. The same or corresponding portions are denoted by the same references in the drawings, and description thereof will not be repeated.
First Embodiment
(28) In the present embodiment, a glass substrate is used as a brittle-material substrate. Other examples of the brittle-material substrate include a ceramic substrate of, for example, low-temperature firing ceramic or high-temperature firing ceramic, a silicon substrate, a compound semiconductor substrate, a sapphire substrate, and a quartz substrate.
(29) With reference to
(30) The cutter edge 51 is provided with a top surface SD1 (first surface) and a plurality of surfaces surrounding the top surface SD1. The plurality of surfaces include a side surface SD2 (second surface) and a side surface SD3 (third surface). The top surface SD1 and the side surfaces SD2 and SD3 (the first to third surfaces) are oriented in different directions and are adjacent to each other. The cutter edge 51 has a vertex at which the top surface SD1 and the side surfaces SD2 and SD3 meet, and the vertex forms a protruding portion PP of the cutter edge 51. The side surfaces SD2 and SD3 form a ridge forming a side portion PS of the cutter edge 51. The side portion PS linearly extends from the protruding portion PP. The side portion PS, which is a ridge as described above, has a convex shape extending linearly.
(31) It is desirable that the cutter edge 51 be a diamond point. Specifically, the cutter edge 51 is desirably made of diamond in terms of hardness and reduced surface roughness. More desirably, the cutter edge 51 is made of single-crystal diamond. Still more desirably, in crystallography, the top surface SD1 is a {001} plane, and each of the side surfaces SD2 and SD3 is a {111} plane. In this case, the side surfaces SD2 and SD3 are crystal planes equivalent to each other in crystallography though they have different directions.
(32) Diamond other than single-crystal diamond may be used, and for example, polycrystalline diamond synthesized by chemical vapor deposition (CVD) may be used. Alternatively, sintered diamond may be used that is obtained by binding, with a binder such as iron group elements, polycrystalline diamond particles sintered from particulate graphite or non-graphitic carbon so as not to contain the binder such as iron group elements.
(33) The shank 52 extends along an axial direction AX. The cutter edge 51 is preferably attached to the shank 52 in such a manner that the direction normal to the top surface SD1 extends substantially along the axial direction AX.
(34) With reference to
(35) With further reference to
(36) With reference to
(37) With reference to
(38) In step S20 (
(39) In step S30 (
(40) In the formation of the scribe lines SL, the cutter edge 51 is displaced from the position N1 to the position N2 and is further displaced from the position N2 to the position N3 in the present embodiment. With reference to
(41) With reference to
(42) Although the method for forming the assist line AL is not particularly limited, as illustrated in
(43) The crack lines CL are less likely to be formed in the direction from the position N2 to the position N3 than in the direction from the position N2 to the position N1. In other words, ease of the extension of the crack lines CL involves direction dependency. This can result in a phenomenon in which the crack lines CL are formed between the positions N1 and the N2 and are not formed between the positions N2 and N3. The present embodiment is aimed to divide the glass substrate 4 along between the positions N1 and N2 and is not aimed to separate the glass substrate 4 along between the positions N2 and N3. Thus, while the formation of the crack line CL is necessary between the positions N1 and N2, the difficulty of forming the crack line CL between the positions N2 and N3 is not an issue.
(44) In step S50 (
(45) The glass substrate 4 is divided as described above.
(46) With reference to
(47) With reference to
(48) With reference to
Second Embodiment
(49) With reference to
(50) With reference to
(51) With reference to
(52) The other steps are substantially identical to those of the first embodiment described above.
(53) With reference to
(54) With reference to
(55) With reference to
Third Embodiment
(56) With reference to
(57) The cutter edge 51 is caused to slide from the position N1 beyond the edge ED2. When the cutter edge 51 passes through the edge ED2, the stress distortion generated inside the substrate directly below the scribe line is released, so that the crack line extends from the end of the scribe line SL located on the edge ED2 toward the position N1 (
(58) Although a constant load may be applied to the cutter edge 51 in the formation of the scribe lines SL, the load applied to the cutter edge 51 at the position N2 may be increased when the cutter edge 51 is displaced from the position N1 to the position N2. For example, the load is increased by approximately 50%. The cutter edge 51 whose load has been increased is caused to slide beyond the edge ED2. In other words, the load of the cutter edge 51 is increased at the end portion of the scribe line SL. When the cutter edge 51 reaches the edge ED2, the crack line extends from the end of the scribe line SL located on the edge ED2 via the position N2 toward the position N1 (
(59) The other steps are substantially identical to those of the first embodiment above.
Fourth Embodiment
(60) With reference to
(61) With reference to
(62) As the application of a stress, specifically, the pressed cutter edge 51 is caused to slide between the position N2 and the edge ED2 (in the figure, the area between the dashed line and the edge ED2) on the front surface SF. This sliding is performed until the cutter edge 51 reaches the edge ED2. The cutter edge 51 is caused to slide preferably to intersect the path of the scribe line SL that has been first formed, more preferably to overlap the path of the scribe line SL that has been first formed. The length of a second sliding is, for example, approximately 0.5 mm. A second sliding may be performed after each of a plurality of scribe lines SL (
(63) In a modification, to apply a stress between the position N2 and the edge ED2, laser light may be applied between the position N2 and the edge ED2 on the front surface SF, in place of causing the cutter edge 51 to slide again as described above. A resultant thermal stress can also induce the formation of crack lines.
(64) The other steps are substantially identical to those of the first embodiment described above.
Fifth Embodiment
(65) With reference to
(66) With reference to
(67) With reference to
(68) The other steps are substantially identical to those of the first embodiment described above.
Sixth Embodiment
(69) With reference to
(70) Although the first and second edges of the perimeter of the glass substrate are short sides of a rectangle in the embodiments above, the first and second edges may be long sides of the rectangle. The shape of the perimeter is not limited to a rectangle and may be, for example, a square. The first and second edges are not limited to linear edges and may be curved edges. Although the front surface of the glass substrate is flat in the embodiments above, the front surface may be curved.
(71) The embodiments according to the present invention may be arbitrarily combined, modified, and omitted as appropriate within the scope of the present invention.
EXPLANATION OF REFERENCE SIGNS
(72) N1 position (first position) N2 position (second position) ED1 edge (first edge) ED2 edge (second edge) AL assist line CL crack line SF front surface SL scribe line PP, PPv protruding portion PS, PSv side portion glass substrate 50 cutting tool 51, 51v cutter edge 52 shank