Supercharging system, control device for supercharging system, and method for operating supercharging system
10961903 ยท 2021-03-30
Assignee
Inventors
- Yukio Yamashita (Tokyo, JP)
- Hiroyoshi KUBO (Tokyo, JP)
- Mitsufumi GOTO (Tokyo, JP)
- Musashi Sakamoto (Tokyo, JP)
Cpc classification
G01R19/165
PHYSICS
F02B39/10
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F02B37/14
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F02B37/013
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F02B37/004
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F02B37/24
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
International classification
F02B37/24
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F02B37/013
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F02B37/00
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F02B37/14
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F02B39/10
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
Abstract
A supercharging system includes: a first supercharger including a first compressor for compressing air to be supplied to an engine and a motor for driving the first compressor; a leakage current measuring part for measuring a leakage current of the motor; and a first controller for controlling the first supercharger. The first controller includes a motor control part configured to, when a measurement result by the leakage current measuring part is not less than a first threshold, set an upper limit value of an output command value for the motor to be lower than when the measurement result is less than the first threshold, and to control an output of the motor within a range which does not exceed the upper limit value.
Claims
1. A supercharging system, comprising: a supercharger including, a compressor for compressing air to be supplied to an engine, a motor for driving the compressor, a turbine driven by exhaust gas from the engine and by the motor, and a nozzle vane configured to adjust a flow path area of the exhaust gas flowing into the turbine; a leakage sensor measuring a leakage current of the motor; and a controller and a non-transitory memory storing executable instructions that cause the controller to: if a measurement result by the leakage current measuring part is not less than a threshold, set an upper limit value of an output command value for the motor to be lower than when the measurement result is less than the threshold; control an output of the motor within a range which does not exceed the upper limit value; determine a target opening degree of the nozzle vane on the basis of a difference between a boost pressure by the supercharging system and a target boost pressure; and obtain a corrected opening degree of the nozzle by correcting the target opening degree to reduce the flow path area, corresponding to a reduction amount of the output command value for the motor by the upper limit value; and control an opening degree of the nozzle vane to the corrected opening degree.
2. The supercharging system according to claim 1, wherein the executable instructions further causes the controller to: set, if the measurement result is not less than the threshold and less than another threshold which is greater than the threshold, the upper limit value of the output command value for the motor to be greater than zero and smaller than when the measurement result is less than the threshold; and set, if the measurement result is not less than the another threshold, the upper limit value of the output command value for the motor to zero.
3. The supercharging system according to claim 1, wherein the motor includes an inverter for converting a direct current voltage from a battery to a three-phase alternating current voltage and supplying the three-phase alternating current voltage to the motor, and wherein the leakage current sensor is an ammeter collectively measuring a three-phase alternating current between the inverter and the motor.
4. The supercharging system according to claim 1, wherein the motor includes an inverter for converting direct current voltage from a battery to three-phase alternating current voltage and supplying the three-phase alternating current voltage to the motor, and wherein the leakage current sensor is an ammeter collectively measuring going and returning direct current between the battery and the inverter.
5. The supercharging system according to claim 1, wherein the leakage current sensor is an insulation resistance meter measuring an insulation resistance value of the motor.
6. A method of operating a supercharging system which comprises a supercharger including, a compressor for compressing air to be supplied to an engine, a motor for driving the compressor, a turbine driven by exhaust gas from the engine and by the motor, and a nozzle vane configured to adjust a flow path area of the exhaust gas flowing into the first turbine, the method comprising: measuring a leakage current of the motor by a leakage sensor; by a controller, setting, if a measurement result in the leakage current measuring step is not less than a first threshold, an upper limit value of an output command value for the motor to be lower than when the measurement result is less than the first threshold; controlling an output of the motor within a range which does not exceed the upper limit value having been set; controlling an opening degree of the nozzle vane on the basis of the measured on the leakage current; determining a target opening degree of the nozzle vane on the basis of a difference between a boost pressure, detected by a pressure sensor of the supercharging system and a target boost pressure; and obtaining a corrected opening degree by correcting the target opening degree as to reduce the flow path area, corresponding to a reduction amount of the output command value for the motor by the upper limit value; and controlling the opening degree of the nozzle vane to the corrected opening degree.
Description
BRIEF DESCRIPTION OF DRAWINGS
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
DETAILED DESCRIPTION
(15) Embodiments of the present invention will now be described in detail with reference to the accompanying drawings. It is intended, however, that unless particularly specified, dimensions, materials, shapes, relative positions and the like of components described in the embodiments shall be interpreted as illustrative only and not intended to limit the scope of the present invention.
(16)
(17) The first supercharger 2 depicted in
(18) The first supercharger 2 depicted in
(19) In the first supercharger 2 depicted in
(20) The first supercharger 2 depicted in
(21) With reference to
(22) The opening degree of the plurality of nozzle vanes 16 can be changed by rotating the support shafts 17 with an actuator (not depicted). In
(23) With the opening degree of the nozzle vanes 16 reduced (i.e. the flow path area of exhaust gas is reduced), the inflow velocity of exhaust gas to the first turbine 14 increases, and thus it is possible to increase the boost pressure by the supercharging system 1. Furthermore, with the opening degree of the nozzle vanes 16 expanded (i.e. the flow path area of exhaust gas increased), the inflow velocity of exhaust gas to the first turbine 14 decreases, and thus it is possible to decrease the boost pressure by the supercharging system 1. Accordingly, it is possible to adjust the boost pressure by the supercharging system 1 by adjusting the opening degree of the nozzle vanes 16.
(24) In the supercharging system 1 depicted in
(25) In the intake pipe 32, a pressure sensor 5 for measuring a pressure of air to be supplied to the engine 8 (boost pressure) may be disposed, on the further upstream side of the intake manifold 36.
(26) In the supercharging system 1 depicted in
(27) A bypass pipe 42 bypassing the first turbine 14 may be connected to the exhaust pipe 40, and a waste-gate valve 43 may be disposed in the bypass pipe 42. By adjusting the opening degree of the waste-gate valve 43, it is possible to adjust the flow rate of exhaust gas that flows into the first turbine 14 and the flow rate of exhaust gas that flows through the bypass pipe 42, and thereby it is possible to control the rotation speed of the first turbine 14 and the rotation speed of the first compressor 10 coaxially driven with the first turbine 14. The opening degree of the waste-gate valve 43 may be controlled by the control device 100.
(28)
(29) The control device 100 may be an ECU for controlling the supercharging system 1. Further, the control device 100 may be an ECU provided independently from an engine ECU for controlling the engine 8.
(30) The control device 100 may be a microcomputer comprising a central processing unit (CPU), a random access memory (RAM), a read only memory (ROM), and an I/O interface.
(31) A method for operating the supercharging system 1 using the control device 100 according to an embodiment now will be described along the flowchart of
(32) Leakage current of the motor 12 for driving the first compressor is measured (S2). Leakage current of the motor 12 is measured by using the leakage current measuring part 4 (described below).
(33) If insulation degradation of winding, which is a typical example of malfunction of the motor 12, occurs in the motor 12, leakage current increases with development of the insulation degradation. In other words, a leakage current value indicates the stage of progress of malfunction of the motor 12.
(34) A measurement value obtained by the leakage current measuring part 4 is sent to the first controller 110 as an electric signal.
(35) Next, it is determined whether the measurement result of the leakage current of the motor 12 in S2 is greater than the first threshold set in advance (S4). The first controller 110 may include a storage part (memory), and the first threshold may be stored in the storage part in advance. Further, the first controller 110 may be configured to compare the first threshold stored in the storage part and a measurement value sent from the leakage current measuring part 4.
(36) If it is determined in S4 that the measurement result of the leakage current of the motor 12 is less than the first threshold (No in S4), the flow is just ended. Alternatively, the flow may return to S2 and perform the step of measuring the leakage current.
(37) If it is determined in S4 that the measurement result of the leakage current of the motor 12 is not less than the first threshold (YES in S4), the motor control part 112 sets an upper limit value of the output command value for the motor 12 to be lower than when the measurement result of the leakage current is less than the first threshold, and controls the output of the motor 12 to be within a range that does not exceed the upper limit value (S8 or S10).
(38) As described above, if the measurement result of the leakage current of the motor 12 is not less than the first threshold, i.e., when the motor 12 is malfunctioning or is about to malfunction, the upper limit value of the output command value for the motor 12 is set to be lower than when it is otherwise, and the output of the motor 12 is controlled in the range of the upper limit value. Thus, compared to a case in which the motor 12 is stopped immediately after the motor 12 is determined to be malfunctioning, the output of the motor 12 is reduced gradually, which mitigates deterioration of drivability. Further, insulation degradation of the motor 12 occurs depending on the temperature of the wire of the motor 12 (motor winding or wire that leads to outside from the motor), and is more likely to develop when the temperature of the wire is higher. In this regard, reducing the output of the motor 12 as described above also reduces the wire temperature of the motor 12, and thereby it is possible to suppress development of insulation degradation of the motor 12.
(39) To control the output of the motor 12, the motor control part 112 may control the voltage that the inverter 28 applies to the motor 12 so as to obtain a desired output from the motor 12.
(40) As described above, if it is determined in S4 that the measurement result of the leakage current of the motor 12 is not less than the first threshold (Yes in S4), it may be further determined whether the measurement result of the leakage current exceeds a second threshold which is greater than the first threshold (S6). If it is determined in S6 that the measurement result of the leakage current of the motor 12 is less than the second threshold (No in S6), the motor control part 112 sets the upper limit value of the output command value for the motor 12 to be larger than zero and smaller than when the measurement result of the leakage current is less than the first threshold, and controls the output of the motor 12 to be within the range not exceeding the upper limit value (S8). If it is determined in S6 that the measurement result of the leakage current of the motor 12 is not less than the second threshold (Yes in S6), the motor control part 112 sets an upper limit value of the output command value for the motor 12 to zero, and controls the output of the motor 12 to become zero (S10).
(41) In this case, the upper limit value of the output command value for the motor 12 is reduced in stages with an increase in the leakage current of the motor 12. Thus, compared to a case in which the motor 12 is stopped immediately after the motor 12 is determined to be malfunctioning, the output of the motor 12 is reduced gradually, which mitigates deterioration of drivability.
(42) The second threshold may be stored in advance in the storage part of the first controller 110. Further, the first controller 110 may be configured to compare the second threshold stored in the storage part and a measurement value sent from the leakage current measuring part 4.
(43) If the first supercharger 2 has the first turbine 14 and the first nozzle vanes 16 for adjusting the flow-path area of exhaust gas that flows from the engine 8 into the first turbine 14, the first vane control part 114 may control the opening degree of the first nozzle vanes 16 (S12) to ensure a boost pressure by the supercharging system 1. More specifically, when the measurement result by the leakage current measuring part 4 is not less than the first threshold (Yes in S4), the first vane control part 114 controls the opening degree of the first nozzle vanes 16 so that the flow path area of exhaust gas flowing into the first turbine 14 is smaller than when the measurement result of the leakage current is less than the first threshold, in response to reduction of the upper limit value of the output command value for the motor 12 by the motor control part 112 in S8 and S10.
(44) Accordingly, the opening degree of the first nozzle vanes 16 is reduced to increase the boost pressure in response to a decrease in the boost pressure due to a decrease in the output command value for the motor 12, and thereby it is possible to ensure a boost pressure by the supercharging system 1 while performing a control by the motor control part 112.
(45)
(46) Accordingly, a feedback control (e.g. PI control or PID control) is performed on the first nozzle vanes 16 so as to achieve a target opening degree determined on the basis of a difference between the boost pressure by the supercharging system 1 and the target boost pressure, and thereby it is possible to bring the boost pressure closer to the target boost pressure while performing a control by the motor control part 112.
(47) Further, the boost pressure by the supercharging system 1 may be measured by the pressure sensor 5 and sent to the first controller 110 as an electric signal.
(48) In an embodiment, as depicted in
(49) Accordingly, the target opening degree of the first nozzle vanes 16 in the feedback control is corrected corresponding to the amount of reduction of the output command value for the motor 12 by the upper limit value, and thus it is possible to bring the boost pressure closer to the target boost pressure quickly compared to a case in which the target opening degree is not corrected.
(50)
(51) In the control block diagram depicted in
(52) In the motor control part 112, an upper limit value determination part 104 determines the upper limit value of the output command value for the motor 12 on the basis of the value of a leakage current I.sub.L measured by the leakage current measuring part 4. For instance, if the measurement result by the leakage current measuring part 4 is not less than the above described first threshold, the upper limit of the output command value for the motor 12 is set to be lower than when the measurement result of the leakage current is less than the first threshold. Further, a limiter 106 imposes a limit on the motor output command value P.sub.m* to be not greater than the set upper limit value of the output command value, and thereby P.sub.m is obtained. P.sub.m obtained as described above is used to control the output of the motor 12 as a motor output command value.
(53) In the first vane control part 114, a correction part 108 corrects the first target opening degree O.sub.V* of the first nozzle vane 16, and thereby the first corrected opening degree (the first nozzle vane opening degree command value) O.sub.V is obtained.
(54) The correction part 108 corrects the first target opening degree of the first nozzle vanes 16 corresponding to a reduction amount of the output command value for the motor 12, that is, a difference between the target boost pressure P.sub.B* calculated by the command value calculation part 102 and the motor output command value P.sub.m whose upper limit value is limited by the limiter 106, and thereby the first corrected opening degree (the first nozzle vane opening degree command value) O.sub.V is obtained. O.sub.V obtained as described above is used to control the opening degree of the first nozzle vanes 16 as the first corrected opening degree (the first nozzle vane opening degree command value).
(55) The supercharging system 1 according to the embodiment depicted in
(56) The second supercharger 6 is a turbocharger including a second compressor 20 for compressing air to be supplied to the engine 8, and a second turbine 24 configured to be rotary driven by exhaust gas from the engine 8 to drive the second compressor 20. The second supercharger 6 includes a second nozzle vane 26 configured to adjust the flow-path area of exhaust gas flowing into the second turbine 24.
(57) The first supercharger 2 and the second supercharger 6 are disposed in series in the supercharging system 1, and one of the first supercharger 2 or the second supercharger 6 is a low-pressure stage supercharger (90) that is disposed on the low pressure side (that is, a side closer to the inlet of intake air). The other one of the first supercharger 2 or the second supercharger 6 is a high-pressure stage supercharger (92) configured to further compress air that is compressed by the compressor (the first compressor 10 or the second compressor 20) of the low-pressure stage compressor (90) and to supply the air to the engine 8.
(58) In the supercharging system 1 depicted in
(59) In the supercharging system 1 depicted in
(60) The supercharging system 1 depicted in
(61) In the supercharging system 1 depicted in
(62) A bypass pipe 42 bypassing the second turbine 24 may be connected to the exhaust pipe 40, and a waste-gate valve 43 may be disposed in the bypass pipe 42. By adjusting the opening degree of the waste-gate valve 43, it is possible to adjust the flow rate of exhaust gas that flows into the second turbine 24 and the flow rate of exhaust gas that flows through the bypass pipe 42, and thereby it is possible to control the rotation speed of the second turbine 24 and the rotation speed of the second compressor 20 coaxially driven with the second turbine 24. The opening degree of the waste-gate valve 43 may be controlled by the control device 100.
(63) In the supercharging system 1 depicted in
(64) A bypass pipe 42 bypassing the turbine (14 or 24) of the low-pressure stage supercharger 90 may be connected to the exhaust pipe 40, and a waste-gate valve 43 may be disposed in the bypass pipe 42. By adjusting the opening degree of the waste-gate valve 43, it is possible to adjust the flow rate of exhaust gas that flows into the turbine (14 or 24) of the low-pressure stage supercharger 90 and the flow rate of exhaust gas that flows through the bypass pipe 42, and thereby it is possible to control the rotation speed of the turbine (14 or 24) of the low-pressure stage supercharger 90 and the rotation speed of the compressor (10 or 20) of the low-pressure stage supercharger 90 coaxially driven with the turbine (14 or 24). The opening degree of the waste-gate valve 43 may be controlled by the control device 100.
(65) Further, a second bypass flow passage 48 is connected to the exhaust pipe 40 and the exhaust manifold 38 so as to bypass the turbine (24 or 14) of the high-pressure stage supercharger 92. A part of exhaust gas from the engine 8 can flow into the turbine (14 or 24) of the low-pressure stage supercharger 90 without passing through the turbine (24 or 14) of the high-pressure stage supercharger 92 via a bypass valve 45 disposed in the second bypass flow passage 48. By adjusting the opening degree of the bypass valve 45, it is possible to adjust the flow rate of exhaust gas that flows into the turbine (24 or 14) of the high-pressure stage supercharger 92 and the turbine (14 or 24) of the low-pressure stage supercharger 90, and thereby it is possible to control the rotation speed of the turbine (24 or 14) of the high-pressure stage supercharger 92 and the turbine (14 or 24) of the low-pressure stage supercharger 90, as well as the rotation speed of the compressor (20 or 10) of the high-pressure stage supercharger 92 and the compressor (10 or 20) of the low-pressure stage supercharger 90 coaxially driven with the turbine (24 or 14) and the turbine (14 or 24). The opening degree of the bypass valve 45 may be controlled by the control device 100.
(66)
(67) The supercharging system 1 depicted in
(68) A method for operating the supercharging system 1 using the control device 100 including the first controller 110 and the second controller 120 will be described along the flowchart of
(69) Herein, S32, S34, S36, S38, and S40 in
(70) In S34, when it is determined that the measurement result of the leakage current of the motor 12 is not less than the first threshold (Yes in S34), the second vane control part 122 may control the opening degree of the second nozzle vanes 26 (S42) to ensure the boost pressure by the supercharging system 1. More specifically, when the measurement result by the leakage current measuring part 4 is not less than the first threshold (Yes in S34), the second vane control part 122 controls the opening degree of the second nozzle vanes 26 so that the flow path area of exhaust gas flowing into the second turbine 24 becomes smaller than when the measurement result of the leakage current is less than the first threshold, in response to reduction of the upper limit value of the output command value for the motor 12 by the motor control part 112 in S38 or S40.
(71) Accordingly, the opening degree of the second nozzle vanes 26 is reduced to increase the boost pressure in response to a decrease in the boost pressure due to a decrease in the output command value for the motor 12, and thereby it is possible to ensure a boost pressure by the supercharging system 1 while performing a control by the motor control part 112.
(72) The opening degree of the second nozzle vanes 26 in S42 can be controlled in accordance with the flowchart depicted in
(73) That is, in an embodiment, as depicted in
(74) Accordingly, a feedback control (e.g. PI control or PID control) is performed on the second nozzle vanes 26 so as to achieve a target opening degree determined on the basis of a difference between the boost pressure by the supercharging system 1 and the target boost pressure, and thereby it is possible to bring the boost pressure closer to the target boost pressure while performing a control by the motor control part 112.
(75) Further, in an embodiment, as depicted in
(76) Accordingly, the target opening degree of the second nozzle vanes 26 in the feedback control is corrected corresponding to the amount of reduction of the output command value for the motor 12 by the upper limit value, and thus it is possible to bring the boost pressure closer to the target boost pressure quickly compared to a case in which the target opening degree is not corrected.
(77) Next, the leakage current measuring part 4 according to some embodiments will be described.
(78) In an embodiment, the leakage current measuring part 4 is an ammeter capable of collectively measuring a three phase alternating current between the motor 12 and the inverter 28 for converting direct-current voltage from the battery 30 into three-phase alternating current voltage and supplying the alternating current voltage to the motor winding. Such an ammeter includes, for instance, a clamp meter.
(79) A clamp meter can be used, for instance, to measure a leakage current of the motor 12 by collectively measuring a zero-phase current of a three-phase alternating current between the inverter 28 and the motor 12. That is, if the total current obtained by collectively measuring a three-phase alternating current is zero, it means that there is no problem in insulation of the winding of the motor 12, and there is no occurrence of leakage current. In contrast, if the total current obtained by collectively measuring a three-phase alternating current is not zero, it means that there is occurrence of leakage current in the motor 12. If the total current is increasing, it means that insulation degradation of the winding is in progress.
(80) In an embodiment, the leakage current measuring part 4 is an ammeter capable of collectively measuring going and returning direct current between the battery 30 and the inverter 28. Such an ammeter includes, for instance, a clamp meter.
(81) A clamp meter can be used, for instance, to measure a leakage current of the motor 12 by collectively measuring the total of going and returning direct current between the battery 30 and the inverter 28. That is, if the total current obtained by collectively measuring going and returning direct current between the battery 30 and the inverter 28 is zero, it means that there is no problem in insulation of the winding of the motor 12, and there is no occurrence of leakage current. In contrast, if the total current obtained by collectively measuring going and returning direct current between the battery 30 and the inverter 28 is not zero, it means that there is occurrence of leakage current in the motor 12. If the total current is increasing, it means that insulation degradation of the winding is in progress.
(82) In an embodiment the leakage current measuring part 4 is an insulation-resistance meter capable of measuring an insulation resistance value of the motor 12.
(83) A decrease in the insulation resistance value of the motor 12 means an increase in leakage current of the motor 12. Thus, it is possible to detect a leakage current of the motor 12 with an insulation resistance meter for measuring an insulation resistance value of the motor 12. Further, an insulation resistance value of the motor 12 can be measured even when the motor 12 is not supplied with power from the battery 30, and thus, an insulation resistance meter can detect a leakage current of the motor 12 even when the motor 12 is not in operation.
(84) The control device 100 may perform monitoring of leakage current by the leakage current measuring part 4. Further, monitoring of leakage current by the leakage current measuring part 4 may be performed not directly by the control device 100 but by an inverter controller, and may be sent to the control device 100 through communication (e.g. CAN).
(85) As described above, before the motor 12 develops a critical insulation failure, an abnormality is detected from an increase in leakage current, which is a sign of malfunction of the motor 12, and the output of the motor 12 is controlled on the basis of the detection. Accordingly, it is possible to mitigate deterioration of drivability due to malfunction of the motor 12.
(86) Embodiments of the present invention were described in detail above, but the present invention is not limited thereto, and various amendments and modifications may be implemented.
(87) Further, in the present specification, an expression of relative or absolute arrangement such as in a direction, along a direction, parallel, orthogonal, centered, concentric and coaxial shall not be construed as indicating only the arrangement in a strict literal sense, but also includes a state where the arrangement is relatively displaced by a tolerance, or by an angle or a distance whereby it is possible to achieve the same function.
(88) For instance, an expression of an equal state such as same equal and uniform shall not be construed as indicating only the state in which the feature is strictly equal, but also includes a state in which there is a tolerance or a difference that can still achieve the same function.
(89) On the other hand, an expression such as comprise, include, have, contain and constitute are not intended to be exclusive of other components.
DESCRIPTION OF REFERENCE NUMERALS
(90) 1 Supercharging system 2 First supercharger 4 Leakage current measuring part 5 Pressure sensor 6 Second supercharger 8 Engine 10 First compressor 11 Rotational shaft 12 Motor 14 First turbine 16 First nozzle vane 17 Support shaft 20 Second compressor 24 Second turbine 26 Second nozzle vane 28 Inverter 30 Battery 32 Intake pipe 34 Intercooler 36 Intake manifold 38 Exhaust manifold 40 Exhaust pipe 42 Bypass pipe 43 Waste-gate valve 45 Bypass valve 46 Recirculation passage 47 Recirculation valve 48 Second bypass flow passage 50 Turbine casing 54 Turbine rotor 56 Rotor blade 90 Low-pressure stage supercharger 92 High-pressure stage supercharger 100 Control device 102 Command value calculation part 104 Upper limit value determination part 106 Limiter 108 Correction part 110 First controller 112 Motor control part 114 First vane control part 120 Second controller 122 Second vane control part