Foundation construction device and its construction method
10954653 ยท 2021-03-23
Assignee
Inventors
Cpc classification
E02F3/146
FIXED CONSTRUCTIONS
E02D5/50
FIXED CONSTRUCTIONS
E02D15/08
FIXED CONSTRUCTIONS
E02D17/13
FIXED CONSTRUCTIONS
E02F5/06
FIXED CONSTRUCTIONS
E02D15/04
FIXED CONSTRUCTIONS
International classification
E02F3/14
FIXED CONSTRUCTIONS
E02D5/52
FIXED CONSTRUCTIONS
E02D5/50
FIXED CONSTRUCTIONS
Abstract
A foundation construction device includes a fixed guiding device and a combined device. The fixed guiding device includes a fixed rack and a guiding device. The combined device includes a chain cutter power transmission device, a spoil treatment device, and a rack.
Claims
1. A foundation construction device for the construction of a foundation, the foundation construction device comprising: a fixed guide to make the foundation in a straight state, the fixed guide comprising a fixed frame and a guide; a combined device to connect to the top of the foundation, the combined device comprising a chain blade power transmission device, a spoil treatment device, and a rack, the chain blade power transmission device and the spoil treatment device being installed on the rack; and a chain blade to excavate rock and soil at the bottom of the foundation and transport the excavated rock and soil to the top, the chain blade comprising a chain and a cutter that is fixed on the chain for rock and soil excavation, whereby during operation the fixed guide guides the foundation and/or the combined device to make the foundation in a straight state, the chain blade power transmission device drives the chain blade to run along a track of the foundation, the spoil treatment device separates the rock and soil transported from the bottom of the foundation by the chain blade from the chain blade, and the combined device and the foundation descend synchronously.
2. The foundation construction device of claim 1, wherein the chain blade power transmission device comprises a chain blade drive device, a chain blade tension device, and a chain wheel.
3. The foundation construction device of claim 1, wherein the rack is adapted to move within the guide.
4. The foundation construction device of claim 1, wherein the guide is adapted such that the foundation can move within the guide.
5. The foundation construction device of claim 1, wherein the fixed frame comprises a machinery/construction vehicle or machinery/construction ship.
6. The foundation construction device of claim 1, wherein the foundation is a slot-type foundation adapted to be equipped with a chain excavating device to excavate rock and soil at the bottom of the foundation.
7. The foundation construction device of claim 1, wherein the foundation is a combined foundation comprising a plurality of slot-type foundations, whereby during operation each slot-type foundation is equipped with a chain excavating device to excavate rock and soil at a bottom one of the foundations.
8. The foundation construction device of claim 1, wherein the rack of the combined device comprises a slurry pipeline device, the slurry pipeline device comprising a slurry pipeline connected with a slurry nozzle at the bottom of the foundation.
9. The foundation construction device of claim 1, wherein the fixed frame is a construction platform of the foundation, with a lifting device installed at the top.
10. A method of foundation construction, the method comprising: 1) pre-fabricating a foundation by sections or integrally at a factory; 2) installing and fixing a frame at a foundation-construction site; 3) transporting a first, bottom section of the foundation to the site, loading the first section into the fixed frame, and installing a chain blade at the first section; 4) connecting the bottom of a rack with the top of the first section of the foundation, connecting the chain blade with a chain blade at the top of the first section of the foundation; 5) driving the chain blade to move along a track of the foundation, excavating the rock and soil at the bottom of the first section of the foundation, transporting the excavated rock and soil to the top, and separating the rock and soil transported from the bottom of the foundation; 6) lowering the combined device and the first section of foundation (4-1) synchronously to a set position; 7) separating and removing the rack from the first section of the foundation; 8) loading the second section of the foundation into the frame; 9) connecting the bottom of the second section of the foundation with the top of the first section of the foundation, connecting the chain blade at the bottom of the second section of the foundation with the chain blade at the top of the first section of the foundation; 10) connecting the bottom of the rack with the top of the second section of the foundation, connecting the chain blade with the chain blade at the top of the second section of the foundation; 11) driving the chain blade to move along the track of the foundation, excavating the rock and soil at the bottom of the first section of the foundation and transporting the excavated rock and soil to the top, and separating the rock and soil transported from the bottom of the foundation; 12) lowering the rack, the first section of the foundation, and the second section of the foundation synchronously to a set position; 13) separating and removing the rack from the second section of the foundation; 14) repeating the above steps 7), 8), 9), 10), 11), and 12) to complete the connection of each section of the foundation and lowering to the set position, and then pulling out the chain blade for concrete pouring.
Description
BRIEF DESCRIPTION OF THE SEVERAL VIEWS OF THE DRAWINGS
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
(17)
(18)
(19)
(20)
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS
(21) The foundation construction device includes fixed guide 1 and combined device 2, which is used for the construction of foundation 4 with chain blade 3 at the bottom. Device 1 consists of fixed frame 1-1 and guide 1-2. Device 2 includes chain blade power transmission device 2-1, spoil treatment device 2-2, and rack 2-3. Device 2-1 and device 2-2 are installed on rack 2-3. Device 2-1, foundation 4 and chain blade 3 constitute chain excavating device 5. Foundation 4 is the rack of chain excavating device 5, while chain blade 3 only excavates the rock and soil at the bottom of foundation 4. Chain blade 3 is composed of chain 3-1 and cutter 3-2 fixed on chain 3-1 for rock and soil excavation. Device 1 guides foundation 4 and/or device 2 to make foundation 4 in a straight state. During construction, device 2 is connected with the top of device 2 and foundation 4, and device 2-1 drives chain blade 3 to run along the track of foundation 4. Chain blade 3 excavates the rock and soil at the bottom of foundation 4, and transports the excavated rock and soil to the top. Device 2-2 separates the rock and soil transported from the bottom of foundation 4 by chain blade 3 from chain blade 3, and device 2 and foundation 4 descend synchronously.
(22) Device 2-1 is composed of chain blade drive device 2-1-1, chain blade tension device 2-1-2, and chain wheel 2-1-3.
(23) Rack 2-3 moves within guide 1-2.
(24) Foundation 4 moves within guide 1-2.
(25) Fixed frame 1-1 is a machinery/construction vehicle or machinery/construction ship.
(26) Foundation 4 is slot-type foundation 4A. During construction, slot-type foundation 4A is equipped with chain excavating device 5A for excavating the rock and soil at the bottom of foundation 4A, that is, frame 2A-3 of device 2A is equipped with a device 2A-1.
(27) The foundation is combined foundation 4B composed of several slot-type foundations 4A. Each slot-type foundation 4A is equipped with chain excavating device 5A that excavates the rock and soil at the bottom of respective foundation 4A only, that is, the frame of device 2B is equipped with several devices 2A-1.
(28) Rack 2-3 in device 2 includes slurry pipeline device 6, and slurry pipeline 6-1 is connected with slurry nozzle 6-2 at the bottom of the foundation.
(29) Fixed frame 1-1 is the construction platform of foundation 4, with a lifting device installed at the top.
(30) The construction method can be divided into the following steps:
(31) 1) Pre-fabricate foundation 4 by sections or integrally at the factory;
(32) 2) Install and fix frame 1-1 on the spot;
(33) 3) Transport the first section (i.e. bottom section) of foundation 4-1 to the site, load it into fixed frame 1-1, and install chain blade 3;
(34) 4) Connect the bottom of rack 2-3 in device 2 with the top of the first section of foundation 4-1, connect chain blade 3 at the bottom of device 2 with the chain blade 3 at the top of the first section of foundation 4-1 to constitute chain excavating device 5, and connect slurry pipeline 6-1 at the bottom of device 2 with slurry pipeline 6-1 at the top of the first section of foundation 4-1;
(35) 5) Start device 2-1-1, so that device 2-1-1 drives chain blade 3 to move along the track of foundation 4-1, chain blade 3 excavates the rock and soil at the bottom of the first section of foundation 4-1 and transports the excavated rock and soil to the top, and device 2-2 separates the rock and soil transported by chain blade 3 from the bottom of foundation 4-1 from chain blade 3;
(36) 6) Device 2 and the first section of foundation 4-1 descend synchronously to the set position;
(37) 7) Separate and remove device 2 from the first section of foundation 4-1;
(38) 8) Load the second section of foundation 4-2 into frame 1-1;
(39) 9) Connect the bottom of the second section of foundation 4-2 with the top of the first section of foundation 4-1, connect chain blade 3 at the bottom of the second section of foundation 4-2 with chain blade 3 at the top of the first section of foundation 4-1, and connect slurry pipeline 6-1 at the bottom of the second section of foundation 4-2 with slurry pipeline 6-1 at the top of the first section of foundation 4-1;
(40) 10) Connect the bottom of rack 2-3 in device 2 with the top of the second section of foundation 4-2, connect chain blade 3 at the bottom of device 2 with chain blade 3 at the top of the second section of foundation 4-2 to constitute chain excavating device 4, and connect slurry pipeline 6-1 at the bottom of device 2 with slurry pipeline 6-1 at the top of the second section of foundation 4-2;
(41) 11) Start device 2-1-1, so that device 2-1-1 drives chain blade 3 to move along the track of foundation 4-1, chain blade 3 excavates the rock and soil at the bottom of the first section of foundation 4-1 and transports the excavated rock and soil to the top, and device 2-2 separates the rock and soil transported by chain blade 3 from the bottom of foundation 4-1 from chain blade 3;
(42) 12) Device 2, first section of foundation 4-1 and second section of foundation 4-2 descend synchronously to the set position;
(43) 13) Separate and remove device 2 from the second section of foundation 4-2;
(44) Repeat the above steps 7), 8), 9), 10), 11), and 12) to complete the connection of each section of the foundation and descend to the set position, and then pull out chain blade 3 for concrete pouring.
(45) The Present Invention is Further Described Below in Conjunction with the Drawings Attached:
(46) As shown in
(47) As shown in
(48) As shown in
(49) As shown in
(50) As shown in
(51) 1) Pre-fabricate foundation 4B by blocks at the factory;
(52) 2) Install and fix frame 1-1 on the spot;
(53) 3) Transport the first section (i.e. bottom section) of foundation 4B-1 to the site, load it into fixed frame 1-1, and install chain blade 3;
(54) 4) Connect the bottom of frame 2B-3 in device 2B with the top of the first section of foundation 4B-1, connect chain blade 3 at the bottom of device 2B with the chain blade 3 at the top of the first section of foundation 4B-1 to constitute chain excavating device 5B, and connect slurry pipeline 6-1 at the bottom of device 2B with slurry pipeline 6-1 at the top of the first section of foundation 4B-1;
(55) 5) Start device 2-1-1, so that device 2-1-1 drives chain blade 3 to move along the track of foundation 4B-1, chain blade 3 excavates the rock and soil at the bottom of the first section of foundation 4B-1 and transports the excavated rock and soil to the top, and device 2B-2 separates the rock and soil transported by chain blade 3 from the bottom of foundation 4B-1 from chain blade 3;
(56) 6) Device 2B and the first section of foundation 4B-1 descend synchronously to the set position;
(57) 7) Separate and remove device 2B from the first section of foundation 4B-1;
(58) 8) Load the second section of foundation 4B-2 into frame 1-1;
(59) 9) Connect the bottom of the second section of foundation 4B-2 with the top of the first section of foundation 4B-1, connect chain blade 3 at the bottom of the second section of foundation 4B-2 with chain blade 3 at the top of the first section of foundation 4B-1, and connect slurry pipeline 6-1 at the bottom of the second section of foundation 4B-2 with slurry pipeline 6-1 at the top of the first section of foundation 4B-1;
(60) 10) Connect the bottom of rack 2-3 in device 2B with the top of the second section of foundation 4B-2, connect chain blade 3 at the bottom of device 2 with chain blade 3 at the top of the second section of foundation 4B-2 to constitute chain excavating device 5B, and connect slurry pipeline 6-1 at the bottom of device 2B with slurry pipeline 6-1 at the top of the second section of foundation 4B-2;
(61) 11) Start device 2-1-1, so that device 2-1-1 drives chain blade 3 to move along the track of foundation 4B, chain blade 3 excavates the rock and soil at the bottom of the first section of foundation 4B-1 and transports the excavated rock and soil to the top, and device 2B-2 separates the rock and soil transported by chain blade 3 from the bottom of foundation 4B from chain blade 3;
(62) 12) Device 2B, first section of foundation 4B-1, and second section of foundation 4B-2 descend synchronously to the set position;
(63) 13) Separate and remove device 2B from the second section of foundation 4B-2;
(64) Repeat the above steps 7), 8), 9), 10), 11), and 12) to complete the connection of each section of the foundation and descend to the set position, and then pull out chain blade 3 for concrete pouring.