PIPELINE ASSEMBLY AND METHOD OF INSTALLATION
20210041040 ยท 2021-02-11
Assignee
Inventors
Cpc classification
F16L1/205
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F16L1/16
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F16L1/123
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F16L1/207
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F16L1/24
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
International classification
F16L1/12
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F16L1/20
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F16L1/24
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
Abstract
A method for installing a non-metallic pipeline assembly, the method comprising the steps of: forming a pipe assembly by coupling a load bearing member and counter weight to a non-metallic pipe; floating the pipe assembly proximate to the water surface until in position, then; permitting the pipe assembly to sink to the sea bed.
Claims
1. A method for installing a non-metallic pipeline assembly, the method comprising the steps of: forming a pipe assembly by coupling a load bearing member and counter weight to a non-metallic pipe; floating the pipe assembly proximate to the water surface until in position, then; permitting the pipe assembly to sink to the sea bed.
2. The method according to claim 1, wherein the load bearing member and the counter weight are the same element.
3. The method according to claim 2, wherein the element is a chain.
4. The method according to claim 1, further including the steps of coupling selectively removable buoyancy tanks to the pipe assembly, and detaching the buoyancy tanks from the pipe assembly when the pipe assembly is in position.
5. The method according to claim 1, wherein the pipe assembly is pulled by at least one boat so as to place the pipe assembly in position.
6. A non-metallic pipeline assembly arranged to be installed offshore, comprising: a pipe having a load bearing member coupled along a length of said pipe, said load bearing member arranged to receive a tensile force sufficient to pull the pipe assembly through water; a counter weight coupled along the length of the pipe, said counter weight arranged to increase the specific gravity of the pipe assembly.
7. The pipeline assembly according to claim 6, wherein the load bearing member and the counter weight are the same element.
8. The pipeline assembly according to claim 7, wherein the element is a chain coupled along a length of the pipe.
9. The pipeline assembly according to claim 6, further including a plurality of selectively removable buoyancy tanks coupled along the length of the pipe.
Description
BRIEF DESCRIPTION OF DRAWINGS
[0008]
[0009]
[0010]
DETAILED DESCRIPTION
[0011] Whilst the invention is applicable for any installation site from offshore to the shoreline, the following example will make reference to drilling platforms.
[0012]
[0013] The first platform 10 includes an end fitting and hang off 20, 25 to which the pipe is mounted. From each drilling platform 10, 15 is provided an I-Tube 30, 60 to guide and direct the pipe to the base of the drilling platform so as to lay across the sea floor. In order to achieve the correct curvature of the pipe as it moves from a substantially vertical position in the I-Tube to the horizontal position laying on the seabed, bend restrictors 35, 55 are further provided and thus controlling the orientation of the pipe leading from each of the drilling platforms.
[0014] A feature of the installation of the pipeline involves the use of chains as the load bearing component of the assembled pipeline. The chain is coupled to the pipe in a manner to bear the tensile load applied during the installation, such that the assembly of the chain and pipe is pulled into position.
[0015] Once in position, the chain acts as a counter weight against the buoyancy of the pipe to ensure the pipe settles on the sea floor. To this end, the counter weight acts to ensure the pipe assembly has a specific gravity substantially greater than 1.0. This combination of features of load bearing member and counterweight is critical in permitting the use of non-metallic materials for offshore pipes. As discussed, metallic pipes have inherent flaws in offshore applications, but in the absence of a viable alternative, have been the material of choice.
[0016] It will be appreciated that the load bearing member, being a member coupled to the pipe and bearing the tensile load as the pipe is pulled into place, may be a distinct element from the counterweight. The counterweight, therefore, may be a heavy and relatively inexpensive material, such as concrete, with the load bearing member being a cable that may be selectively releasable from the pipe for reuse.
[0017] In the embodiment of
[0018] Referring to
[0019] As additional lengths of the pipe 90 are drawn out 115, stabilizing craft 125 may be used to stabilize the length of pipe as well as attach buoyancy tanks 120 to maintain the pipe in a buoyant condition until properly positioned.
[0020] As seen in
[0021]
[0022] Thus the pipe is progressively lowered and once in position the lowering cable 145 is detached 165 separating the boat from control of the pipe. This happens progressively as shown in
[0023] The installation method can be used for very significant lengths being well in excess of one kilometer. The limiting factor being the tensile strength of the load bearing member which for the present example may be a chain having a dry weight of 25 to 30 kilograms per meter. This will vary given the specific gravity of the non-metallic pipe being used. For instance such NMP's may have a specific gravity of about 1.4. While denser than water, the buoyant forces will prevent placement of the pipe without the use of the counter weight.
[0024] The process of pipeline assembly and launching may include placing a reel of non-metal pipe (NMP) onto a drive system for the reel. The chain may fit to a rail having a guide and rollers to couple to the pipeline as well as the buoyancy tanks.
[0025] The chain may be positioned so as to be beneath the pipe and thus through launching the pipe will remain relatively buoyant and the chain free to move to a lower position during the deployment. The chain link may also function to prevent the strap slip along the pipe during the towing process. The pipe buoyancy tanks and chain are then progressively assembled as the pipe is launched and dragged by the boat. Typically the chain will be mounted to the pipe every 0.2 to 0.5 m though this will be subject to installation and design criteria that may vary considerably. It may be preferable to use a non-metallic strap in couple the chain to the pipe.
[0026] The buoyancy tanks may be installed in pairs so as to ensure a uniformly buoyant force to the pipe. The buoyancy tanks may be mounted to the pipe every 9 or 10 meters but again this will depend upon a range of criteria including environmental conditions. The buoyancy tanks may be mounted to the pipe using a non-metallic strap. Importantly the buoyancy tanks will include a wire rope connected to each of the buoyancy tanks and a stripping line.
[0027] On positioning the pipe at the desired location, the buoyancy tanks are progressively stripped from the pipeline by the stripping line shearing through the non-metallic straps, allowing the progressive sinking of the pipe and weighted chain.