EXTENSIBLE SHELLS AND RELATED METHODS FOR CONSTRUCTING A DUCTILE SUPPORT PIER
20210087769 ยท 2021-03-25
Assignee
Inventors
Cpc classification
E02D7/28
FIXED CONSTRUCTIONS
E02D27/20
FIXED CONSTRUCTIONS
E02D3/08
FIXED CONSTRUCTIONS
International classification
E02D27/20
FIXED CONSTRUCTIONS
E02D3/08
FIXED CONSTRUCTIONS
Abstract
Extensible shells and related methods for constructing a support pier are disclosed. An extensible shell can define an interior for holding granular construction material and define a first opening at a first end for receiving the granular construction material into the interior and a second opening at a second end. The extensible shell can be flexible such that the shell expands when granular construction material is compacted in the interior of the shell. A method may include positioning the extensible shell in the ground and filling at least a portion of the interior of the shell with the granular construction material. The granular construction material may be compacted in the interior of the extensible shell to form a support pier.
Claims
1. An extensible shell for constructing a ductile support pier in ground, the extensible shell defining an interior for holding granular construction material and defining a first end having a first opening therethrough for receiving the granular construction material into the interior and an opposing second end having an end closed by a cap.
2. The extensible shell of claim 1, wherein the cap is integral to the shell.
3. The extensible shell of claim 1, wherein the cap is removable.
4. A system for installing ductile support piers in ground, the system comprising: an extensible shell defining an interior for holding granular construction material and defining a first end having a first opening therethrough for receiving the granular construction material into the interior and an opposing second end having an end closed by a cap; a driving mandrel for nesting in to the extensible shell, the driving mandrel further comprising a removable driving collar for using in driving the nested extensible shell, and a removable pin.
5. A method for constructing a ductile support pier in ground, the method comprising: positioning an extensible shell for driving into ground, the shell defining an interior for holding granular construction material and defining a first end having a first opening therethrough for receiving the granular construction material into the interior and an opposing second end having an end closed by a cap; inserting a driving mandrel into the shell, the driving mandrel further comprising a removable driving collar for using in driving the nested extensible shell, and a removable pin; driving the shell into the ground using the driving mandrel; removing the driving collar and continuing to drive the mandrel such that the shell cap is removed; filling the shell with granular construction material; compacting the granular construction material such that a bottom bulb is formed beneath the shell as driven into the ground; raising the mandrel out of the shell while simultaneously adding additional granular construction material to fill the shell and form a ductile pier.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0024]
[0025]
[0026]
[0027]
[0028]
[0029]
[0030]
[0031]
[0032]
[0033]
[0034]
[0035]
[0036]
[0037]
[0038]
[0039]
[0040]
[0041]
DETAILED DESCRIPTION OF THE INVENTION
[0042] The present invention is directed to an extensible shell and related methods for constructing a support shell pier in ground. Particularly, an extensible shell in accordance with embodiments of the present invention can have an interior into which granular construction material can be loaded and compacted. The shell can be positioned in a cavity formed in the ground (the cavity being formed through a variety of methods as described in more detail below, including driving the shell from grade to form the cavity). After positioning in the ground, granular construction material can be loaded into the interior through an opening of the shell. The granular construction material may be subsequently compacted. The shell can be extensible (or flexible) such that walls of the shell expand when the granular construction material is compacted in the interior of the shell. Therefore, since the shell maintains the compacted granular construction material in a contained manner (i.e., the material cannot expand laterally beyond the shell walls into the in-situ soil) the ground surrounding the shell is reinforced and improved for supporting shallow foundations and other structures. The present invention can be advantageous, for example, because it allows for much higher load carrying capacity due to its ability to limit the granular construction material from bulging laterally outward during loading. The shell is typically made of relatively permanent, substantially non-corrosive and/or non-degradable material such that the lateral bulging of the material is limited for the life of the pier.
[0043]
[0044] Opposing the enclosed end 102 is another end, open end 106, which defines an opening 108 for receiving granular construction material into an interior (not shown in
[0045]
[0046]
[0047] The shape of the exterior of the shell 100 may be articulated to form a plurality of panels that form a hexagonal shape in cross-section as viewed from the top or bottom of the shell. Alternatively, the shape may be octagonal, cylindrical, conical, or any other suitable shape.
[0048] The extensible shell 100 is often shaped to taper downward from the open end 106 to the enclosed end 102. In one embodiment, the shell 100 tapers at a 2 degree angle, although the shell may taper at any other suitable angle.
[0049] The extensible shell 100 may be made of plastic, aluminum, or any metallic or non-metallic material of suitable extensibility, and preferably substantially non-corrosive and/or non-degradable material. The shell 100 may be relatively thin-walled. The thickness of the wall of the shell 100 may range, for example, from about 0.5 mm to about 100 mm. The example shell 100 of
[0050]
[0051] After the partial cavity 202 has been formed, the extensible shell 100 may be positioned within the cavity 202, as shown in
[0052] After the extensible shell 100 has been driven into (while forming) the fully enlarged cavity 202, the mandrel 206 is removed, leaving behind the shell 100 in the cavity 202 and with the interior 110 being empty. The shell 100 may then be filled with a granular construction material 212, such as sand, aggregate, admixture-stabilized sand or aggregate, recycled materials, crushed glass, or other suitable materials as shown in
[0053]
[0054] Referring to
[0055] In an embodiment of the present invention, a second mandrel 212 may be used to compact the upper portion of the material 304 in the direction 302, as shown in
[0056] In an embodiment of the present invention, the shell 100 may define apertures 218 that extend between the interior 110 and an exterior of the shell 100 to the in-situ soil (see
[0057] Other embodiments may not define apertures, or may provide one or more apertures 218 on only one side of the shell 100. Alternatively, the apertures 218 may be defined in the shell 100 such that they are positioned along a portion of the length of the shell 100, are positioned along the full length of the shell 100, or may be positioned asymmetrically in various configurations. The sizes and placements of the apertures 218 can vary according to the size of the shell 100, the conditions of the ground (e.g., where higher water pressure is known to exist), and other relevant factors. The apertures 218 may range in size from about 0.5 mm to about 50 mm; such as from about 1 mm to about 25 mm. In another embodiment, the top of the shell 100 may be enclosed and connected to vacuum pressure to further increase and accelerate drainage of excess water pressure in the surrounding soil through the apertures 218.
[0058] The mandrel 206 may be constructed of sufficient strength, stiffness, and geometry to adequately support the shell 100 during driving and to be able to be retracted from the shell 100 after driving. In one embodiment, the shape of the exterior of mandrel 206 is substantially similar to the shape of the interior 110 defined by the shell 100. In another embodiment, the mandrel 206 is comprised primarily of steel. Other materials are also envisioned including, but not limited to, aluminum, hard composite materials, and the like.
[0059] The mandrel 206 may be driven by a piling machine or other suitable equipment and technique that may apply static crowd pressure, hammering, or vibration sufficient to drive the mandrel 206 and extensible shell 100 into the surface of ground 204. In one embodiment, the machine may be comprised of an articulating, diesel, pile-driving hammer that drives the mandrel 206 using high energy impact forces. The hammer may be mounted on leads suspended from a crane. In another embodiment, the hammer may be a sheet pile vibrator mounted on a rig capable of supplying a downward static force. In another embodiment, the shell 100 may be placed in a pre-formed cavity 200 and constructed without the use of an extractable mandrel. Standard methods of driving mandrels into the ground are known in the art and therefore, can be used for driving.
[0060] The following Examples illustrate further aspects of the invention.
Example I
[0061] As an example, piers were constructed using extensible shells in accordance with embodiments of the present invention at a test site in Iowa. Load tests were conducted on the piers using a conventional process. The extensible shells used in the tests and the methods of their use consisted essentially of that described above and shown in the attached Figures. In this test, extensible shells formed from LEXAN polycarbonate plastic were installed at a test site characterized by soft clay soil. This testing was designed to compare the load versus deflection characteristics of an extensible shell in accordance with the present invention to aggregate piers constructed using a driven tapered pipe. Two comparison aggregate piers (of fine and coarse aggregate) were constructed to a depth of 12 feet below the ground surface.
[0062] In this test, the extensible shell was formed by bending sheets of the plastic to form a tapered shape having a hexagonal cross-section and that tapered downward from an outside diameter of 24 inches (610 mm) at the top of the shell to a diameter of 18 inches (460 mm) at the bottom of the shell. A panel of the shells overlapped, and this portion was both glued and bolted together. The length of the extensible shell was 9.5 feet (2.9 m). In this embodiment, apertures were formed in the extensible shell by perforating the sides of the shell with 3 mm to 7 mm diameter weep holes spaced apart from each another. The bottom portion of the shell was capped with a steel shoe to facilitate driving. LEXAN polycarbonate plastic has a tensile strength of approximately 16 MPa (2300 psi) at 11 percent elongation and a Young's modulus of 540 MPa (78,000 psi). The extractable mandrel used in this test was attached to a high frequency hammer, which is often associated with driving sheet piles. The hammer is capable of providing both downward force and vibratory energy for driving the shell into the ground and for compacting aggregate construction material in the shell.
[0063] In this example, the extensible shell was driven into the ground without pre-drilling of the cavity or hole. Particularly, in this test, the two shells were installed by orientating each shell in a vertical direction, placing approximately 4 feet (1.2 m) of sand at the base of the shell, and then driving the shell into the ground surface with an extractable mandrel with exterior dimensions similar to those of the interior of the shell. The shell was driven to a depth of approximately 8.5 feet (2.6 m) below grade. The mandrel was removed and the shells were filled with sand. The extractable mandrel was then re-lowered within the shells and vertical compaction force in combination with vibratory energy was applied to both compact the sand to drive the shell to a depth of 9 feet (2.7 m) below grade. The mandrel was then extracted and the upper portion of the shell was then filled with crushed stone to a depth of 0.5 feet (0.2 m) below grade. A concrete cap was then poured above the crushed stone fill to facilitate load testing.
[0064] Radial cracks were observed to extend outward from the edge of the shell pier. These cracks form drainage galleries that are the result of high radial stresses and low tangential stresses created in the ground during pier installation. Drainage was afforded by the perforations in the shell and allowed soil water to drain into the sand and aggregate filled piers.
[0065] The shell piers were load tested using a hydraulic jack pushing against a test frame.
Example II
[0066] In other testing, extensible shells were formed from high-density polyethylene polymer (HDPE) and installed at the test site as described in Example I. This testing program was designed to compare the load versus deflection characteristics of this embodiment of the present invention to aggregate piers constructed using a driven tapered pipe as described in Example I. A total of six shell piers were installed as part of this example.
[0067] In this test, the extensible shell was formed by a rotomolding process. The shells defined a tapered shape having a hexagonal cross-section and that tapered downward from an outside diameter of 585 mm (23 inches) at the top of the shell to a diameter of 460 mm (18 inches) at the bottom of the shell. The bottom of the extensible shell was integrally constructed as part of the shell walls as a result of the rotomolding process. The mandrel in this embodiment was attached to the same hammer as described in Example I.
[0068] The installation process in this Example was somewhat different from that in Example I and included pre-drilling a 30 inch (0.76 m) diameter cavity to a depth of 2 feet (0.61 m) to 3 feet (0.9 m) below the ground surface (rather than driving the shell initially from top grade). The shell was then placed vertically in the pre-drilled cavity. The extractable mandrel was then inserted into the shell, and the shell was driven to a depth 11 feet (3.4 m) to 12 feet (3.7 m) below grade. The extensible shell was then filled with aggregate construction material and compacted in four lifts; with each lift about 7.4 cubic feet (0.2 cubic meters) in volume. The aggregate consisted of sand in five of the piers and consisted of crushed stone in one of the piers. Each lift was compacted with the downward pressure and vibratory energy of the extractable mandrel.
[0069] After placement and compaction of sand within the extensible shells, the top of the shells were situated at about 2 feet (0.61 m) to 3 feet (0.9 m) below the ground surface. Crushed stone was then placed and compacted above the extensible shell to a depth of 1 foot (0.3 m) below the ground surface. A concrete cap was then poured above the crushed stone fill to facilitate load testing.
[0070] The shell piers were load tested using a hydraulic jack pushing against a test frame.
Example III
[0071] In another test, an extensible shell of the same embodiment described in Example II was installed at the test site as described in Example I. This testing program was designed to compare the load versus deflection characteristics of this embodiment of the invention to aggregate piers constructed using a driven tapered pipe as described in Example I. The mandrel, hammer, and extensible shell used for testing were the same as used in Example II.
[0072] In this embodiment of the present invention, the installation process included pre-drilling a 30 inch (0.76 m) diameter cavity to a depth of 3 feet (0.9 m) below the ground surface. The extractable mandrel was then inserted into the pre-drilled cavity, to create a cavity with a total depth of 5 feet (1.5 m) below the ground surface. This cavity was then backfilled to the ground surface with sand. The extensible shell was then driven vertically through the sand filled cavity with the extractable mandrel to a depth of 9 feet (2.7 m) below the ground surface, so that the top of the shell was situated 6 inches above the ground surface. The extensible shell was then filled with sand in four lifts, with each lift about 7.4 cubic feet (0.2 cubic meters) in volume. Each lift was compacted with the downward pressure and vibratory energy of the mandrel. A concrete cap encompassing the top of the shell was then cast over the shell to facilitate load testing.
[0073] The shell pier was load tested using a hydraulic jack pushing against a test frame.
Example IV
[0074] In yet another test, an embodiment of the present invention was installed at a project site characterized by 3 feet (0.9 m) of loose sand soil over 7 feet (2.1 m) of soft clay soil over dense sand soil. The embodiment of the present invention at the project site was used to support structural loads, such as those associated with building foundations and heavily loaded floor slabs. The mandrel, hammer, and extensible shell used for testing were the same as used in Examples II and III.
[0075] In this embodiment of the present invention, the installation process included pre-drilling a 30 inch (0.76 m) diameter pre-drill to a depth of 3 feet (0.9 m) below the ground surface. Approximately 7.4 cubic feet (0.2 cubic meters) of sand was then placed in the pre-drilled cavity. This resulted in the pre-drilled cavity being about half-full.
[0076] The extensible shell was then placed vertically in the partially backfilled pre-drilled cavity. The extractable mandrel was then inserted into the shell, and the shell was driven to a depth 12.5 feet (3.8 m) below grade. The extensible shell was then filled with sand in four lifts; with each lift about 7.4 cubic feet (0.2 cubic meters) in volume. Each lift was compacted with the downward pressure and vibratory energy of the mandrel.
[0077] After placement and compaction of sand within the extensible shell, a lift of crushed stone about 4.9 cubic feet (0.14 cubic meters) in volume was placed and compacted within the extensible shell. Crushed stone was then placed and compacted above the extensible shell until the crushed stone backfill was level with the ground surface.
[0078] At one shell location, a 30 inch (0.76 m) diameter concrete cap was placed over the shell to facilitate load testing. At a second shell location, a 6 foot (1.8 m) wide by 6 foot (1.8 m) wide concrete cap was placed over the shell to facilitate loading and to measure the load deflection characteristics of the composite of native matrix soil and extensible shell (to simulate a floor slab).
[0079] The shell piers were load tested using a hydraulic jack pushing against a test frame, with the results of the load testing being shown in
Slotted Shell Embodiment
[0080] With reference to
[0081] As an example, a slotted extensible shell of this embodiment was installed at a test site in Iowa to compare the load versus deflection characteristics of this embodiment of the extensible shell to aggregate piers constructed using a driven tapered pipe. The test site was characterized by soft clay soil and the two comparison aggregate piers (of fine and coarse aggregate) were constructed to a depth of 12 feet below the ground surface.
[0082] For this test of the extensible shell, the shell was formed from High Density Polyethylene polymer and was formed by the rotomolding process. The shell formed a tapered shape that was hexagonal in cross section and tapered downward from an outside diameter of 23 inches (585 mm) at the top of the shell to a diameter of 18 inches (460 mm) at the bottom of the shell. The bottom of this embodiment of the extensible shell was integrally constructed as part of the shell walls as a result of the rotomolding process. In this embodiment of the invention (similar to that shown in
[0083] In this example, the installation process included a 30 inch (0.76 m) diameter pre-drill to a depth of 1.5 feet (0.46 m) below the ground surface. The shell was then placed vertically in the pre-drilled hole and then the shell was driven with an extractable mandrel with exterior dimensions similar to those of the interior of the shell. The shell was driven to a depth of 11 feet (3.4 m) below grade. The mandrel was removed and the extensible shell was then filled with aggregate in four lifts; with each lift about 7.4 cubic feet (0.2 cubic meters) in volume. Each lift was compacted with the downward pressure and vibratory energy of the extractable mandrel.
[0084] After placement and compaction of aggregate within the extensible shell, the top of the shell was situated at about 1.5 feet (0.46 m) below the ground surface. The aggregate backfill was then leveled with the top of the shell, and a concrete cap was then poured above the shell to facilitate load testing.
[0085] The slotted shell pier was load tested using a hydraulic jack pushing against a test frame.
Open-End Embodiment
[0086] With reference to
[0087] Open-end extensible shell 1000 can be any length and any width or diameter. Without limitation, the length of open-end extensible shell 1000 can be from about 3.05 m (5 feet) to about 6.1 m (20 feet) in one example, or can be about 3.05 m (10 feet) in another example. Without limitation, the width or diameter of open-end extensible shell 1000 can be from about 61 cm (24 in) to about 46 cm (18 in) in one example, or can be about 51.8 cm (20.4 in) in another example. In one example, open-end extensible shell 1000 can be formed of plastic, such as high-density polyethylene polymer (HDPE) plastic. In another example, open-end extensible shell 1000 can be formed of metal, such as steel or aluminum.
[0088] Open-end extensible shell 1000 is not limited to a straight tubular shape. For example,
[0089]
[0090] However, the position of shoulder collar 1215 can be adjustable along the length of closed pipe mandrel 1210. Namely, shoulder collar 1215 can be adjustable such that a range of depths and relative positions of open-end extensible shell 1000 and closed pipe mandrel 1210 can be achieved without the need to change mandrels. For example,
[0091]
[0092] At a step 1410, open-end extensible shell 1000 is driven into the ground using a mandrel. For example and referring again to
[0093] At a step 1415, the mandrel (e.g., closed pipe mandrel 1210) is withdrawn from open-end extensible shell 1000, leaving open-end extensible shell 1000 in the ground. For example,
[0094] At a step 1420, shell cavity 1220 is backfilled with sand, aggregate, cementitious grout, and/or any other material. For example,
[0095] At a step 1425, the mandrel (e.g., closed pipe mandrel 1210) is reinserted into open-end extensible shell 1000. Then, material 1225 is packed to below advancing open end 1010 of open-end extensible shell 1000. For example,
[0096] At a step 1430, the mandrel (e.g., closed pipe mandrel 1210) is withdrawn from open-end extensible shell 1000, again as shown in
[0097] At a step 1435, the remaining portion of shell cavity 1220 is backfilled with material 1225 (e.g., sand, aggregate, cementitious grout, and/or any other material).
[0098] At a step 1440, the mandrel (e.g., closed pipe mandrel 1210) is reinserted into open-end extensible shell 1000. Then, material 1225 is packed into shell cavity 1220 of open-end extensible shell 1000.
[0099] At a step 1445, the mandrel (e.g., closed pipe mandrel 1210) is withdrawn from open-end extensible shell 1000, again as shown in
[0100] At a decision step 1450, it is determined whether the construction of the support pier is complete. If the construction of the support pier is complete, then method 1400 ends. However, if the construction of the support pier is not complete, then method 1400 returns to 1435.
[0101] A benefit of using open-end extensible shell 1000 and method 1400 is that it provides increased stiffness for the shell support layer and increased overall length of the extensible shell system in the upper zone (open-end extensible shell 1000 plus bulb depth).
Example V
[0102] As an example, support piers were constructed using extensible shells in accordance with embodiments of the present invention at a test site in Iowa. Load tests were conducted on the piers using a conventional process. The extensible shells used in the tests and the methods of their use consisted essentially of that described above and shown in
[0103] In this test, the extensible shell was formed by a rotomolding process. The shells defined a tapered shape having a hexagonal cross-section (e.g., as shown in
[0104] The extractable mandrel used in this test was attached to a high frequency hammer, which is often associated with driving sheet piles. The hammer is capable of providing both downward force and vibratory energy for driving the shell into the ground and for compacting aggregate construction material in the shell. The open bottom extensible shell pier and the aggregate pier were constructed with a similar mandrel and high frequency hammer.
[0105] In this example, a 61 cm (24 in) diameter and 61 cm (24 in) deep pre-drill hole was formed at the ground surface prior to driving the extensible shell. The purpose of the pre-drill is to facilitate the placement of a concrete cap for the load test. The extensible shell, and Tapered Mandrel were then driven into the ground such that the tip of the tapered mandrel was at a depth of about 5.2 m (17 feet) below the ground surface, the bottom of the extensible shell was at a depth of about 3.65 m (12 feet) below the ground surface, and the top of the shell was at a depth of about 61 cm (24 in) below the ground surface.
[0106] The tapered mandrel used in this example is hollow such that such that the mandrel can be filled with aggregate, and allowed to flow out the bottom of the mandrel. An aggregate pier is constructed with this mandrel by raising and lowering the mandrel pre-determined distances to construct the aggregate pier. In this example, an aggregate pier was constructed below and within the extensible shell using a similar process.
[0107] The open bottom extensible shell piers were load tested using a hydraulic jack pushing against a test frame.
Ductile Pier Embodiment
[0108] With reference to
[0109] Once the mandrel 1210 is inserted into the closed end shell 1700 and the driving collar 1215 attached, then the mandrel is used to drive the closed-end extensible shell 1700 into the subsurface soil 1600. When the desired driving depth is reached, the driving hammer is arrested and the pin 1217 and driving collar 1215 is removed as shown in
[0110] As shown in
[0111] A further embodiment of the present invention includes the ability to install the extensible shell 1700 in shortened modular sections. An extensible shell 1700, shortened to a minimum length, may be installed in similar fashion as described above to reinforce only a short section of the overall length of the pier. For example, a short section of the extensible shell 1700 may be installed just in the upper portion of the subsurface soil 1600 where lateral loads may be higher while a pier, unreinforced by an extensible shell, may be constructed to an arbitrary depth below. A second possible variation might include installing the short section of the extensible shell 1700 at only the mid-span of the overall pier while constructing and unreinforced pier to arbitrary elevations below and above.
[0112] One of the primary advantages of the use of an extensible shell in pier construction is the ability of the shell to extend and in turn bend and deform laterally during applications of lateral loads. The extensibility of the shell results from the relatively pliable elastic modulus values exhibited by the polymeric materials. This allows the shells to both function as extensible shells and also as ductile elements that may deform elasto-plastically without rupture. This allows the extensible shells to constrain the infill materials during many different combinations of load direction and intensity.
Example VI
[0113] The pier construction process described in
[0114]
[0115]
[0116]
[0117]
[0118] The foregoing detailed description of embodiments refers to the accompanying drawings, which illustrate specific embodiments of the invention. Other embodiments having different structures and operations do not depart from the scope of the invention. The term the invention or the like is used with reference to certain specific examples of the many alternative aspects or embodiments of the applicant's invention set forth in this specification, and neither its use not its absence is intended to limit the scope of the applicant's invention or the scope of the claims. Moreover, although the term step may be used herein to connote different aspects of methods employed, the term should not be interpreted as implying any particular order among or between various steps herein disclosed unless and except when the order of individual steps is explicitly described. This specification is divided into sections for the convenience of the reader only. Headings should not be construed as limiting of the scope of the invention. It will be understood that various details of the invention may be changed without departing from the scope of the invention. Furthermore, the foregoing description is for the purpose of illustration only, and not for the purpose of limitation.