CONSTRUCTION UNIT FOR A FRAME
20210207371 ยท 2021-07-08
Inventors
Cpc classification
E04C3/005
FIXED CONSTRUCTIONS
E04B2/7459
FIXED CONSTRUCTIONS
International classification
E04B2/74
FIXED CONSTRUCTIONS
Abstract
Construction unit (1) for building up a frame (2), wherein the frame (2) comprises at least two girders (3a, 3b) and multiple uprights (4), wherein the construction unit (1) comprises a first construction profile (4), a second construction profile (5) and a third construction profile (6), wherein the first construction profile (4) is provided to serve as an upright (4) and the second and the third construction profile (5, 6) are each provided to be part of a respective girder (3a, 3b), wherein each construction unit (1) is provided to form only one upright (4) of a frame (2) and that multiple such construction units (1) are provided to be successively interconnected so that the first construction profiles (4) of successively construction units (1) extend at a distance from one another.
Claims
1. Construction unit for building up a frame, wherein the frame comprises at least two girders extending opposite one another and multiple uprights interconnecting these girders, wherein the construction unit comprises a first construction profile, a second construction profile and a third construction profile, wherein the second and the third construction profile are each respectively connected to an end part of the first construction profile and wherein the first construction profile is provided to serve as an upright and the second and the third construction profile are each provided to be part of a respective girder, wherein the construction unit comprises only one said first construction profile, one said second construction profile and one said third construction profile so that each construction unit is provided to form only one upright of a frame, that the second and the third construction profile each comprise a first and a second end extending opposite each other, wherein, in use, each said first end extends at a distance from the first construction profile and that multiple such construction units are provided to be successively interconnected so that the first end of the second construction profile of a said construction unit is connected to the second end of the second construction profile of a successive said construction unit and that the first end of the third construction profile of the first-mentioned construction unit is connected to the second end of the third construction profile of the said successive construction unit, so that the first construction profiles of successive construction units extend at a distance from one another.
2. Construction unit according to claim 1, wherein the second construction profile is hingeably connected to the first construction profile between at least a first position, wherein the second construction profile virtually extends according to the first construction profile and the second position, wherein the second construction profile virtually makes an angle of 90 to the first construction profile.
3. Construction unit according to claim 2, wherein said third construction profile is hingeably connected to the first construction profile between at least a first position, wherein the said third construction profile virtually extends according to the first construction profile and the second position, wherein the said third construction profile virtually makes an angle of 90 to the first construction profile.
4. Construction unit according to claim 1, wherein the first construction profile is elongated and comprises two profile parts slidable relative to each other in the longitudinal direction of the first construction profile, so that the length of the first construction profile is settable.
5. Construction unit according to claim 1, wherein the ends of the second construction profile are built up such that respective ends of second construction profiles of successive construction units are engageable into one another for connection of the successive construction units.
6. Construction unit according to claim 5, wherein the ends of the third construction profile are built up such that respective ends of third construction profiles of successive construction units are engageable into one another for connection of the successive construction units.
7. Construction unit according to claim 5, wherein the first end of the second and/or the third construction profile comprises a cavity and the second end of the second and/or the third construction profile comprises one or more clamping elements or vice versa, wherein the one or more clamping elements are snappably receivable in a said cavity.
8. Construction unit according to claim 1, wherein the construction unit operatively virtually extends according to a plane and the first construction profile has an H-shaped or a U-shaped cross section across virtually its complete length, so that the first construction profile comprises two opposite U-shaped gutters or one U-shaped gutter, wherein each said gutter is accessible via an opening extending virtually perpendicularly to the said plane.
9. Construction unit according to claim 1, wherein the second and/or the third construction profile has a U-shaped cross section, so that the second and/or the third construction profile comprises a U-shaped gutter, wherein the respective end part of the first construction profile is provided in this gutter for connection of the first construction profile to the second and/or the third construction profile.
10. Construction unit according to claim 2, wherein the second and/or the third construction profile has a U-shaped cross section, so that the second and/or the third construction profile comprises a U-shaped gutter, wherein the respective end part of the first construction profile is provided in this gutter for connection of the first construction profile to the second and/or the third construction profile and wherein the width of the U-shaped gutter is larger than the corresponding dimension of the portion of the first construction profile extending in the proximity of the respective end part, and that, in the first position, this said portion extends in the U-shaped gutter.
11. Construction unit according to claim 1, wherein the respective ends of the second construction profiles of successive construction units are snappably interconnectable and/or the respective ends of third construction profiles of successive construction units are snappably interconnectable.
12. Construction unit according to claim 1, wherein the second construction profile is connected to the first construction profile at the height of the second end of the second construction profile and/or the third construction profile is connected to the first construction profile at the height of the second end of the third construction profile.
13. Construction unit according to claim 1, wherein, viewed in the direction of the first construction profile and in use, the first and the second end of the second construction profile extend on both sides of the first construction profile and each extends at a distance of the first construction profile and/or the first and the second end of the third construction profile extend on both sides of the first construction profile and each extends at a distance of the first construction profile.
14. Frame for a wall, comprising multiple construction units successively interconnected, wherein the construction units are construction units according to claim 1.
15. Method of building up a frame, wherein multiple construction units according to claim 1 are provided and wherein these construction units are successively interconnected.
Description
[0042] In this detailed description, reference numerals are used to refer to the appended drawings, wherein
[0043]
[0044]
[0045]
[0046]
[0047]
[0048]
[0049]
[0050]
[0051]
[0052]
[0053]
[0054]
[0055]
[0056]
[0057]
[0058]
[0059]
[0060]
[0061]
[0062]
[0063]
[0064]
[0065]
[0066]
[0067] The construction units (1) as shown in
[0068] Each construction unit (1) comprises one first construction profile (4), one second construction profile (5) and one third construction profile (6). Each first construction profile (4) is elongated and has a U-shaped cross section. Further, the first construction profile (4) is built up from two profile parts (8a, 8b) with a U-shaped cross section. These two profile parts (8a, 8b) are telescopically slidable relative to each other. The one profile part (8a) is designed to be slightly wider than the other profile part (8b), so that the other profile part (8b) is slidably receivable in the one profile part (8a). The first construction profile (4) further comprises a snap fastener (12) to fix the two profile parts (8a, 8b) with respect to each other. The second and the third construction profile (5, 6) are each respectively connected to an end part of the first construction profile (4). This specifically means that the second construction profile (5) is connected to the one profile part (8a) while the third construction profile (6) is connected to the other said profile part (8b).
[0069] The length, the shape and the dimensions of the second construction profile (5) virtually correspond to the length, the shape and the dimensions of the third construction profile (6). The second and the third construction profile (5, 6) have a virtually U-shaped cross section and therefore have a U-shaped gutter. Further, they have a first end which does not deviate from the U-shape and therefore comprises a cavity (9a, 9b) and they also have a second end located opposite this first end, wherein this second end comprises two clamping elements (10a, 10b) extending in the longitudinal direction of the second and the third construction profile (5, 6), respectively. With the first type, each end part of the construction profile (4) is received centrally and therefore at a virtually equal distance from the first and the second end in the gutter of the second and the third construction profile (5, 6), respectively, and this according to a connection (7a, 7b) allowing a rotation of the second and the third construction profile (5, 6), respectively, relative to the first construction profile (4). With each second type, each end part of the first construction profile (4) is, at the height of the second end, received in the gutter of the second and the third construction profile (5, 6), respectively and this according to a connection (7a, 7b) allowing a rotation of the second and the third construction profile (5, 6), respectively, relative to the first construction profile (4). With both types, the first ends and the second ends extend on both sides of the first construction profile (4) in use.
[0070] Since the second and the third construction profile (5, 6) are rotatably connected to the first construction profile (4) and the length of the first construction profile (4) is adjustable, the construction unit (1) may assume many different positions. Thus, the construction unit (1) may assume a first position, wherein the construction unit (1) takes up a minimum volume so that this first position is mainly used to transport and/or to stock the construction unit (1). This first position is shown in
[0071] A second position is a position of use wherein the length of the first construction profile (4) is not minimal and both the second and the third construction profile (5, 6) make an angle of virtually 90 to the first construction profile (4). In this second position, the construction unit (1) has a I-shape for the first type and a [-shape for the second type. This second position is shown in
[0072] Such construction units (1) are used to form a frame (2) for a wall, such as a facing wall or a non-bearing partition. As shown in
[0073] For the sake of simplicity, the placement of the frame (2) is discussed with reference to the
[0074] Then a second construction unit (1) is connected to the already placed first construction unit (1). Thus, for example, the second construction profile (5) of the second construction unit (1) will connect to the second construction profile (5) of the first construction unit (1) and this is done by clamping the clamping elements (10a) in the cavity (9a) of the first end of the second construction profile (5) of the first construction unit (1). How this is done is shown in steps in
[0075] After all construction units (1) have been placed, the frame (2) is preferably finished further with additional profiles. Eventually, then a frame (2) is obtained with one girder (3a) connected to the floor (13), one girder (3b) connected to the ceiling (14) and multiple uprights (4), wherein the first construction profiles (4) and any additional profiles form the uprights (4). To be able to connect the girders (3a, 3b) to the floor (13) and the ceiling (14), respectively, hook-and-loop fasteners may be provided, wherein then a first side of the hook-and-loop fasteners is provided against the floor (13)/the ceiling (14) and each second respective third construction profile (5, 6) comprises a second side of the hook-and-loop fasteners. With the aid of the additional profiles, a frame (2) consisting of multiple rectangular parts may simply be provided, onto which standard rectangular wall elements, such as MDF boards or plasterboards may be placed and connected for forming a wall. Thus, for example, one additional profile may be connected to each construction unit (1) located immediately next to a said side wall, so that also a profile extends next to the said side wall. In this manner, a wall element may simply be connected to the frame (2) at the height of the side wall. When the side wall shows imperfections or is not at right angles, the wall element may then be cut to shape. Prior to connecting the wall elements to the built-up frame (2), insulating material such as glass wool may be placed between the construction units (1). This may simply be done since all construction profiles (4, 5, 6) have a U-shaped cross section.