METHOD OF RETROFITTING A WIND TURBINE WITH AN ENERGY GENERATING UNIT
20230050065 · 2023-02-16
Inventors
Cpc classification
F03D7/0292
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
Y02P70/50
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
F03D7/0224
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F05B2230/80
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
Y02E10/72
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
F03D7/042
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
International classification
F03D80/50
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F03D7/02
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
Abstract
A method of retrofitting a wind turbine having a tower and a first energy generating unit with a second energy generation unit is disclosed. The wind turbine has been operated for a first period of time at a first tower life rate and has a first tower life expectancy design value. The method includes determining the tower life of the wind turbine tower used during the first period of time; determining the remaining tower life of the wind turbine tower; replacing the first energy generating unit with the second energy generating unit; and operating the retrofitted wind turbine at a second tower life rate less than the first tower life rate so as to extend the life expectancy value of the tower beyond the first tower life expectancy design value.
Claims
1. A method of retrofitting a wind turbine having a tower and a first energy generating unit with a second energy generating unit, the method comprising: removing the first energy generating unit from an upper end of the tower; coupling a tower transition adaptor to the upper end of the tower, the tower transition adaptor having a first end with a first interface sized for engaging with an interface on the upper end of the tower and a second end with a second interface sized for engaging with an interface on the second energy generating unit; and coupling the second energy generating unit to the second end of the tower transition adaptor.
2. The method according to claim 1, wherein first and second interfaces of the tower transition adaptor include annular flanges and the diameter of the annular flanges are different from each other.
3. The method according to claim 1, wherein coupling the tower transition adaptor further includes: determining a tower height at which the second energy generating unit may be operated; and increasing the tower height of the retrofitted wind turbine in response to the determined tower height being greater than the height of the tower of the wind turbine.
4. The method according to claim 1, wherein the wind turbine has been operated for a first period of time at a first tower life rate and has a first tower life expectancy design value, the method further comprising: determining a tower life of the wind turbine tower used during the first period of time; and determining the remaining tower life of the wind turbine tower.
5. The method according to claim 4, wherein determining the tower life of the wind turbine tower used during the first period of time further comprises: inspecting the wind turbine tower; and assigning an effective used tower life to the tower based on the inspection.
6. The method according to claim 4, further comprising: operating the retrofitted wind turbine at a second tower life rate less than the first tower life rate so as to extend the service life of the wind turbine tower beyond the first tower life expectancy design value to a second tower life expectancy value.
7. The method according to claim 6, wherein the second energy generating unit has a generating unit life expectancy design value, and wherein the difference between the second tower life expectancy value and the first period of time is substantially equal to the generating unit life expectancy design value.
8. The method according to claim 6, wherein operating the wind turbine at the second tower life rate further comprises operating the wind turbine within 10% of a rated power curve for the second energy generating unit.
9. The method according to claim 6, wherein operating the wind turbine at the second tower life rate further comprises operating the wind turbine at the rated power curve for the second energy generating unit.
10. The method according to claim 6, wherein operating the retrofitted wind turbine at the second tower life rate further comprises maintaining an effective tower life rate below a predetermined threshold.
11. The method according to claim 10, wherein maintaining the effective tower life rate includes: measuring the loads acting on the tower over a period of time after replacing the first energy generating unit; determining the effective tower life rate based on the measured loads over the period of time; and reducing operating loads on the tower when the effective tower life rate determined is equal to or exceeds the predetermined threshold.
12. The method according to claim 11, wherein reducing operating loads on the tower comprises pitching one or more blades on the second energy generating unit.
13. The method according to claim 11, wherein reducing operating loads on the tower comprises controlling the speed of the rotor on the second energy generating unit.
14. The method according to claim 6, wherein operating the retrofitted wind turbine at the second tower life rate further comprises: determining a tower height at which the second energy generating unit may be operated; and increasing or decreasing the tower height of the retrofitted wind turbine in response to the determined tower height being greater or less than the height of the tower of the wind turbine, respectively.
15. The method according to claim 14, further comprising: determining a maximum tip height of the blades of the second energy generating unit; and decreasing the height of the tower in response to the tip height exceeding a maximum predetermined value.
16. The method according to claim 6, wherein operating the retrofitted wind turbine at the second tower life rate further comprises: determining a tower height at which the second energy generating unit may be operated; and increasing or decreasing the tower height of the retrofitted wind turbine in response to the determined tower height being greater or less than the height of the tower of the wind turbine, respectively.
17. The method according to claim 16, further comprising: determining a maximum tip height of the blades of the second energy generating unit; and decreasing the height of the tower in response to the tip height exceeding a maximum predetermined value.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate one or more embodiments of the invention and, together with a general description of the invention given above, and the detailed description given below, serve to explain the invention.
[0018]
[0019]
[0020]
[0021]
[0022]
[0023]
DETAILED DESCRIPTION
[0024] With reference to
[0025]
[0026] Curve A (solid line) illustrated in
[0027] As noted above, for some wind turbine installations, wind turbine components, such as various bearings, gear box components, generator components, converter components, hub and blade components, etc., may have reliability issues such that the costs for maintaining the wind turbine 10 in an operational state may be unexpectedly high. In some cases, the costs may be so high that the return on investment in the wind turbine 10 may be significantly compromised and the wind turbine operator may take a financial loss with further operation of the wind turbine 10. In some instances, for example, a business case may be made that it is better to discontinue operation of the wind turbine rather than continue operation until the end of the service life of the wind turbine. Aspects of the present invention address these issues and provide a solution that allows wind turbine operators to extend operation of the wind turbine and thereby be afforded an opportunity to achieve a return on their investment.
[0028] In this regard and in accordance with an aspect of the invention, one approach available to wind turbine operators having wind turbines operating at higher than expected costs (and less than expected productivity) as a result of reliability issues is to retrofit the wind turbine tower with another, improved energy generating unit and operate the wind turbine in a manner that extends the service life of the retrofitted wind turbine at least to and preferably beyond the service life of the original wind turbine. Since this approach calls for the same tower to be used for the second generating unit, the retrofitted wind turbine should be operated in a manner that extends the service life of the tower at least to and preferably beyond the life expectancy design value of the tower. This may be achieved, for example, if the loads imposed on the tower by the second energy generating unit are relatively low, and lower than the original design loads, such that the tower life rate after the retrofit is less than the first tower life rate 32 on the design curve A.
[0029] To this end, the inventors of the present application appreciate that not all energy generating units are created the same. In other words, the inventors appreciate that the loads on the tower 12 as a result of the operation of the wind turbine 10 may very well depend on the structural aspects of the energy generating unit and/or on how the energy generating unit is controlled during operation (i.e., the control strategy). Due to a plethora of blade designs, hub designs, nacelle designs and various control strategies for operating a wind turbine, the loads imposed on the tower through operation of the energy generating unit may be generally manufacturer specific. In this regard, some wind turbine manufacturers have designs and control strategies that result in relatively low loads being imposed on the tower during operation. If the second energy generating unit is properly selected, the loads imposed on the tower 12 during operation of the retrofitted wind turbine may be low enough to have a tower life rate sufficient to extend the service life of the tower beyond the original tower life expectancy design value 34. Thus, the wind turbine operator may operate the retrofitted wind turbine beyond the original life expectancy design value and provide additional time to recoup the investment in the wind turbine.
[0030] Curve B illustrated in
[0031] In an exemplary embodiment, the second energy generating unit 40 may be operated so as to have a second tower life rate 42 that results in a second tower life expectancy value 44 that is equal to, and preferably exceeds, the first tower life expectancy design value 34. More particularly, the second energy generating unit 40 includes a life expectancy design value 46 and in order to completely use the full service life of the second energy generating unit 40, the second tower life rate 42 may be selectively controlled so that the second life expectancy value 44 of the tower 12 minus the first period of time 36 is substantially equal to the life expectancy design value 46 of the second energy generating unit 40. Stated another way, the sum of the first time period 36 and the life expectancy design value 46 of the second energy generating unit 40 is substantially equal to the second tower life expectancy value 44. In this way, the second energy generating unit 40 and the tower 12 reach the end of their service life at approximately the same time. By way of example, if the first period of time 36 is ten years and the life expectancy design value of the second energy generating unit 40 is the typical twenty years, then the second tower life rate 42 may be such that the second tower life expectancy is extended to thirty years.
[0032] Upon retrofitting the wind turbine 10 with the second energy generating unit 40, the goal is to maximize power production until the life expectancy of the second energy generating unit 40 and/or the tower 12 are reached (as noted above, preferably they reach the end of their service life together). A number of scenarios are possible here depending on the loads imposed on the tower 12 by the second energy generating unit 40. For example and without limitation, at the original height of the tower 12, it may be possible to operate the second energy generating unit 40 at a rated power curve so that the second tower life expectancy value 44 is substantially equal to the sum of the second energy generating unit life expectancy design value 46 (e.g., twenty years) and the first period of time 36. In other words, the second energy generating unit 40 is so gentle on the tower 12 that the service life of the retrofitted wind turbine tower 12′ is extended to the second tower life expectancy value 44 without substantially any reduction in power production. Thus, it may be possible to extend the service life of the wind turbine tower without any sacrifice in power production from the retrofitted wind turbine.
[0033] In an alternative embodiment, however, there may be the case that at the rated power curve for the second energy generating unit 40, the service life of the tower 12 may expire before the service life of the second energy generating unit 40 expires (i.e., the second energy generating unit still has service life available). Thus, in order to extend the service life of the tower 12 by some amount (preferably a small amount) such that the service life of the tower 12 and the second energy generating unit 40 expire together, the retrofitted wind turbine 10′ may be operated with a de-rated performance such that its power output lies slightly below the rated power curve. By way of example, the retrofitted wind turbine 10′ may be operated with a power output within about 10%, and preferably within about 5%, of the rated power curve of the second energy generating unit 40. Because the wind turbine 10′ is being operated at less than the rated power, the loads on the tower 12, and thus the tower life rate may be reduced so as to prolong the service life of the tower 12 and thereby match the service life of the second energy generating unit 40.
[0034] As evidenced from the above, there may be times when the operation of the retrofitted wind turbine 10′ may be controlled in order to obtain the desired second tower life rate 42 and extend the service life of the tower 12 beyond its original life expectancy 34. As noted above, the tower life rate 42 depends on the loads being imposed on the tower 12 during operation of the retrofitted wind turbine 10′. The imposed loads on the tower 12 may be controlled to a certain extent through operation of the wind turbine 10′. In this regard and in an exemplary embodiment, the loads (e.g., forces, moments, etc.) on the tower 12 may be monitored to ensure that an averaged or effective tower life rate does not exceed a predetermined threshold. Should the effective tower life rate get near (e.g., within 5%) or exceed the predetermined rate threshold, then the operation of the retrofitted wind turbine 10′ may be altered so as to reduce the load experienced by the tower 12 during operation.
[0035]
[0036] In an exemplary embodiment, the controller 52 may be operatively coupled to a pitch mechanism 56 capable of pitching one or more of the blades 26 on the second energy generating unit 40. By pitching the blades 26 in an appropriate manner, wind energy may be dumped (i.e., allowed to pass by the wind turbine) so as to reduce the loads on the tower 12 and/or reduce the speed of the rotor 22. Additionally, or alternatively, the controller 52 may be operatively coupled to a resistance mechanism 58 that provides resistance to the rotation of the rotor 22 and thus controls the speed at which the rotor 22 rotates. By way of example, the resistance mechanism 58 may be a physical or electrical braking mechanism which may be used to reduce the speed of the rotor 22. For example, by regulating the power of the generator, the speed of the rotor 22 may be controlled (e.g., reduced). Through the operation of the resistance mechanism 58, the loads imposed on the tower may be reduced. It should be recognized, however, that there may be other ways to reduce the loads imposed on the tower 12 during operation of the wind turbine 10′ and the invention is not limited to the specific examples provided above.
[0037] While in the above, the height of the wind turbine tower 12 was essentially maintained at its original height and the second energy generating unit 40 was coupled to the top end 60 of the original tower 12, depending on a number of factors, including the remaining life in the tower 12 and the loads imposed on the tower 12 by the second energy generating unit 40 during operation, it may be desirable to increase the height of the tower or decrease the height of the tower for operating the second energy generating unit 40 at a height different than the height of the original tower 12. For example, at the original height of the tower 12, it may be the case that operating the second energy generating unit 40 at the rated power curve results in the second tower life expectancy value being greater than the sum of the second energy generating unit life expectancy design value 46 and the first period of time 36, i.e., the service life of the tower 12 will outlast the service life of the second energy generating unit 40 even operating at the rated power curve (e.g., due to the low forces imposed on the tower 12 during operation). In this case, the height of the original tower 12 may be increased in order to locate the second energy generating unit 40 higher within the atmosphere where faster air currents and less turbulence exist. It is believed that the annual energy production (AEP) of the wind turbine will be increased as a result of the increased height. However, the increased height of the tower 12′ increases the loads acting on the tower 12′ (e.g., think of a cantilevered beam with a large load on its end) and thus increases the second tower life rate accordingly. Nevertheless, depending on the particular application, it may be possible to increase the height of the tower 12′ and operate the second energy generating unit 40 at the rated power curve such that the wind turbine tower 12′ and the second energy generating unit 40 reach the end of their service life at the same time (and at the life expectancy design value of the second energy generating unit).
[0038] As illustrated in
[0039] To retrofit the wind turbine 10, the first energy generating unit 14 may be removed from the tower 12 (
[0040] In many regions where wind turbines are located, there may exist local or regional laws, regulations, ordinances, etc. which limit the height at which structures, such as wind turbines, may extend above the ground. These may exist, for example, as a safety precaution to avoid aviation accidents or for other safety considerations. In any event, when increasing the overall height of the retrofitted wind turbine 10′, the wind turbine operator may want to verify the blade tip height when one of the blades 26 of the second energy generating unit 40 is at the twelve o'clock position (i.e., at the maximum height of the wind turbine 10′) to ensure the retrofitted wind turbine 10′ meets the applicable standards. If the tip height of the blades 26 exceed a predetermined threshold established by the laws, regulations, ordinances, etc. in which the retrofitted wind turbine 10′ is located, then the height of the tower transition adaptor 68 (or possibly even the height of the original tower, see below) may have to be reduced in order to comply with the applicable laws, regulations, ordinances, etc.
[0041] As described above, the tower transition adaptor 68 was added to the top end 60 of the original tower 12, such that substantially the entirety of the original tower 12 was “reused” in the retrofitted wind turbine 10′. This represents an efficient use of the existing structure in the retrofit process. The invention, however, is not limited to that embodiment. In this regard and in an alternative embodiment, a portion of the original tower 12 may be removed in order to establish a new tower interface at which the tower transition adaptor 68 may be coupled. As is generally known and as illustrated in
[0042] Once a portion of the tower 12 has been removed, the tower transition adaptor 68 may be coupled to the new tower interface 88, such as by welding or a flanged connection, for example. More particularly, the first interface 72 at the first end 70 of the tower transition adaptor 68 may be coupled to the new tower interface 88 at the top end of the intermediate tower section 12b (
[0043] In the above where the uppermost tower section 12c is removed during the retrofit process, it should be recognized that the length of the tower transition adaptor 68 may be such that the new height of the tower 12′ of the retrofitted wind turbine 10′ may be greater than or less than the original height of the tower 12. At least one reason for making the height of the tower 12′ greater than the original tower height is provided above (i.e., to be in a location of faster air currents and less turbulence). Such a situation is not always possible, however, and it should be recognized that there may be times when the height of the retrofit tower 12′ may be less than the original height of the tower 12 in order to extend the service life of the wind turbine. For example and as noted above, there may be the case that at the rated power curve for the second energy generating unit 40, the service life of the tower 12 may expire before the service life of the second energy generating unit 40 expires. One approach as noted above is to operate the second energy generating unit 40 below the rated power curve. Another approach, however, is to decrease the height of the tower 12′ of the retrofitted wind turbine 10′. Decreasing the height of the tower will decrease the loads imposed on the tower 12′ by the second energy generating unit 40 during operation (again think of a cantilevered beam with a large load on its end). With the height of the tower 12′ decreased relative to the original height of the tower 12, it may be possible to operate the second energy generating unit 40 at or near the rated power curve. Thus in embodiments in accordance with the present invention, the height of the tower 12′ of the retrofitted wind turbine 10′ may be less than the height of the tower 12 of the original wind turbine 10 but a benefit still be achieved.
[0044] As illustrated in
[0045] By way of example and as illustrated in
[0046] Next, the tower transition adaptor 68 may be coupled to the new tower interface 88. By way of example, the tower transition adaptor 68 may be welded to new tower interface 88. Alternatively, the tower transition adaptor may be coupled to the new tower interface 88 via a flanged connection. More particularly, the first interface 72 at the first end 70 of the tower transition adaptor 68 may be coupled to the new tower interface 88 at the site of the cut in the tower section 12c (
[0047] Subsequent to the retrofit process, the retrofitted wind turbine 10′ may be returned to service and operated at the second tower life rate. The retrofitted wind turbine 10′ should preferably be operational until the service life of the tower 12′ and the second energy generating unit 40 have expired. By extending the service life of the wind turbine 10′ through the retrofitting process, the wind turbine operator may be provided additional time in which to obtain a return on investment in the wind turbine. In this embodiment and similar to the above, it should be recognized that the length of the tower transition adaptor 68 may be such that the new height of the tower 12′ of the retrofitted wind turbine 10′ may be greater than or less than the original height of the tower 12. The tip height of the blades 26 may also be checked to confirm that the height of the retrofitted wind turbine 10′ is within the applicable standards.
[0048] In summary, a financial case may be made to implement a retrofit process on a wind turbine even if it is operating along its design curve, e.g., curve A in
[0049] In the above description, one motivation for implementing a retrofit process as discussed above is that due to low reliability of various wind turbine components, the wind turbine was operating a higher than expected costs and lower than expected power production such that financial viability was jeopardized. In that case and as laid out above, there may be financial reasons to implement the retrofit process in order to extend the service life of the tower and the wind turbine as a whole and increase the amount of time in which the wind turbine operator has to obtain a return on their investment. Aspects of the present invention, however, are not limited to such a situation. There may be several reasons why a wind turbine operator might perform a retrofit process as described above.
[0050] In this regard, in some wind turbine installations the estimated loads acting on the wind turbine tower 12 during operation may have been underestimated. In other words, the loads acting on the tower 12 during operation of the wind turbine 10 may be significantly higher than those estimated during the design phase of the wind turbine 10. There may be several reasons why a wind turbine tower may be subject to loads greater than the expected design loads. For example, the wind conditions might be stronger or more turbulent on the whole than expected. Another reason, however, is that some energy generating units are built and/or operated in a manner that result in relatively large loads being imposed on the tower 12. For whatever reason, the first tower life rate 32 according to the design may be lower than that being actually experienced by the wind turbine tower 12. Such a deviation from the design criteria may be difficult to detect initially and the wind turbine 10 may be operated for a first period of time 36 before a wind turbine operator either detects the issue or decides to take action to resolve the issue. Curve C (dashed line) illustrated in
[0051] By way of example and without limitation, after a first period of time of about ten years of wind turbine operation, the tower 12 will have used about 50% of its total tower life 30 according to design curve A. However, suppose it is discovered that during the ten years of wind turbine operation, the operating loads on the tower 12 have been higher than expected such that about 66% of the total tower life has been used during the first period of time 36. In this regard, the amount of tower life used during the first time period 36 may be assigned as a result of conducting an inspection on the tower 12 and equating the state of the tower to an effective age that is typical in the normal course of operation. For example, upon inspection, the ten year old tower 12 may have characteristics more akin to a thirteen year old tower and be assigned a used tower life (and therefore a remaining tower life) consistent with a thirteen year old tower. The inspection may be, for example, a visual inspection and/or other non-invasive inspection techniques (e.g., ultrasound) conducted on the tower 12 by a structural specialist or the like. Once the used tower life has been assigned based on the inspection, the remaining tower life may be determined. By way of example, and according to the hypothetical example above, there may be about 33% of the tower life remaining at the end of the first time period 36. This inspection process is not limited to the current embodiment and may be implemented in most retrofit processes, event that described above, to confirm used tower life.
[0052] Should the wind turbine tower 12 be subject to higher than expected loads during operation, then service life of the tower 12 will deviate (i.e., decrease) from the life expectancy design value 34 of the tower 12. For example, at the higher loads, the service life of the tower 12 may be only about thirteen years instead of the full twenty years. This is illustrated by line 92 in
[0053] Again depending on several factors, including the remaining life of the tower and the loads that the second energy generating unit 40 imposes on the tower, a financial gain may be obtained by replacing the first energy generating unit 14 with the second, improved energy generating unit 40 and extending the life of the wind turbine as a whole at least to and preferably beyond the service life of the original wind turbine. As discussed above, it may be possible to implement this retrofit process and still operate the retrofitted wind turbine at the rated power curve (i.e., no sacrifice in power production). This scenario is illustrated by curve D in
[0054] While the present invention has been illustrated by a description of various preferred embodiments and while these embodiments have been described in some detail, it is not the intention of the Applicant to restrict or in any way limit the scope of the appended claims to such detail. Additional advantages and modifications will readily appear to those skilled in the art. Thus, the various features of the invention may be used alone or in any combination depending on the needs and preferences of the user.