Voltage and reactive power monitoring/control device and method for calculating required reactive power amount for suppressing a fluctuation component and selecting an appropriate equipment
10892640 ยท 2021-01-12
Assignee
Inventors
- Eisuke KURODA (Tokyo, JP)
- Toshiyuki Miyake (Tokyo, JP)
- Nao SAITO (Tokyo, JP)
- Masahiro Yatsu (Tokyo, JP)
- Taichirou KAWAHARA (Tokyo, JP)
Cpc classification
Y04S20/00
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
H02J3/00
ELECTRICITY
H02J13/00
ELECTRICITY
Y02E40/30
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
Y02E40/70
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
Y02B90/20
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
Y02E60/00
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
H02J3/003
ELECTRICITY
Y04S10/00
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
H02J13/00006
ELECTRICITY
Y04S10/22
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
H02J3/004
ELECTRICITY
International classification
H02J3/18
ELECTRICITY
H02J3/00
ELECTRICITY
Abstract
The voltage and reactive power monitoring/control method includes: measurement data for the power system and data for the system equipment of the power system are used to calculate the system status for the power system at the time of measurement; data for a status estimation calculation result and predicted data for the power generation and load of the power system are used to predictively calculate a system status at a future time from the time of the power system measurement; a fluctuation component is obtained for the predicted value of the data obtained from the power system; the reactive power required to suppress the fluctuation component is obtained, as a required reactive power amount; a reactive power distribution subject is selected from a plurality of pieces of control subject equipment; an output distribution calculation is performed for the required reactive power amount for the selected control subject equipment.
Claims
1. A voltage and reactive power monitoring/control device which is applied to a power system including a control subject equipment capable of adjusting a reactive power, and which monitors and controls a voltage and the reactive power, comprising: a storage device storing a plurality of programs; and a processor, the processor configured to execute the plurality of programs to perform steps of: calculating a fluctuation component of a predicted value of data obtained from the power system; obtaining the reactive power required for suppressing the fluctuation component as a required reactive power amount; selecting a reactive power distribution subject equipment among a plurality of control subject equipment; performing output distribution calculation of the required reactive power amount for the selected power distribution subject equipment; calculating a control instruction value for each control subject equipment from an output distribution calculation result determined for the selected power distribution subject equipment; calculating the fluctuation components in a plurality of periods in calculating the fluctuation component of the predicted value of the data obtained from the power system, and determining the fluctuation component to be suppressed by the reactive power and the fluctuation component to not be suppressed among the fluctuation components in the plurality of periods to obtain the required reactive power amount for the fluctuation component to be suppressed by the reactive power.
2. The voltage and reactive power monitoring/control device according to claim 1, wherein the predicted value of the data obtained from the power system is the voltage of the power system, and the required reactive power amount is obtained by conversion into the reactive power by using a conversion coefficient stored in advance.
3. The voltage and reactive power monitoring/control device according to claim 1, wherein the reactive power distribution subject selection unit selects the reactive power distribution subject equipment by taking into consideration an adjustment power of the plurality of control subject equipment with respect to the required reactive power amount.
4. The voltage and reactive power monitoring/control device according to claim 1, wherein the reactive power distribution subject selection unit selects the reactive power distribution subject by taking into consideration a changeable period of the plurality of control subject equipment and a period of the fluctuation component.
5. The voltage and reactive power monitoring/control device according to claim 4, wherein the changeable period of the plurality of control subject equipment corresponds to information indicating whether or not suppressing the fluctuation component in a particular period is appropriate for each control subject equipment.
6. The voltage and reactive power monitoring/control device according to claim 1, wherein, in a case where the control subject equipment is a generator, the output distribution calculation unit distributes the required reactive power according to capabilities of a plurality of the generators to be output distribution subjects.
7. The voltage and reactive power monitoring/control device according to claim 1, wherein in a case where the control subject equipment is a discrete reactive power supply device including a mechanical mechanism unit, the output distribution calculation unit distributes the required reactive power so that the number of times of manipulation of the mechanical mechanism unit of a plurality of the reactive power supply devices to be output distribution subjects is not biased.
8. The voltage and reactive power monitoring/control device according to claim 1, further comprising a display unit visualizing and displaying an operation state of the power system monitored and controlled by the voltage and reactive power monitoring/control device.
9. The voltage and reactive power monitoring/control device according to claim 8, wherein the display unit visually displays at least one or more of a time acquired for the data of the system, a relationship between a node voltage and constraint conditions (upper and lower limit values of an operation voltage, a target voltage width, and a target voltage), a probability density of the fluctuation component, and the number of times of manipulation of the reactive power supply device.
10. The voltage and reactive power monitoring/control device according to claim 8, wherein the display unit visually displays at least one or more of a distribution status of the required reactive power, a distribution effect by the distribution, a degree of deviation in the case of probability distribution, a frequency of use of each control device, display of the number of times, a relationship between a countermeasure and a band, a countermeasure equipment, and an insufficient capacity.
11. The voltage and reactive power monitoring/control device according to claim 8, wherein the display unit visually displays at least one or more of data used for monitoring and controlling by the voltage and reactive power monitoring/control device.
12. The voltage and reactive power monitoring/control device according to claim 1, wherein the output instruction unit gives the obtained control instruction value to the control subject equipment to control the power system.
13. The voltage and reactive power monitoring/control device according to claim 1, wherein the display unit visually displays at least one or more of an insufficient amount of the reactive power at a prediction time point, a proposal of a countermeasure, a past value and a predicted value of the required reactive power Q for each fluctuation component, and time elapse of a control subject equipment capacity and a required equipment capacity.
14. A voltage and reactive power monitoring/control device which is applied to a power system including a control subject equipment capable of adjusting a reactive power, and which monitors and controls a voltage and the reactive power, comprising: a storage device storing a plurality of programs; and a processor, the processor configured to execute the plurality of programs to perform steps of: calculating a system status at a time of power system measurement by using a measurement data of the power system and data of a system facility of the power system, to obtain a status estimation calculation result; predicting a future system status from the time of power system measurement by using data of the status estimation calculation result and a prediction data of power generation and load of the power system to obtain a predicted value; calculating a fluctuation component of a predicted value of data obtained from the power system; obtaining the reactive power required for suppressing the fluctuation component as a required reactive power amount; selecting a reactive power distribution subject equipment among a plurality of control subject equipment; performing output distribution calculation of the required reactive power amount for the selected reactive power distribution subject equipment; calculating a control instruction value for each control subject equipment from an output distribution calculation result determined for the selected reactive power distribution subject equipment; calculating the fluctuation components in a plurality of periods in calculating the fluctuation component of the predicted value of the data obtained from the power system, and determining the fluctuation component to be suppressed by the reactive power and the fluctuation component to not be suppressed among the fluctuation components in the plurality of periods to obtain the required reactive power amount for the fluctuation component to be suppressed by the reactive power.
15. A voltage and reactive power monitoring/control method which is applied to a power system including a control subject equipment capable of adjusting a reactive power, and which monitors and controls a voltage and the reactive power, comprising: obtaining a fluctuation component of a predicted value of data obtained from the power system and obtaining the reactive power required for suppressing the fluctuation component as a required reactive power amount; selecting a reactive power distribution subject among a plurality of control subject equipment; performing output distribution calculation of the required reactive power amount for the selected reactive power distribution subject equipment; calculating a control instruction value for each control subject equipment from an output distribution calculation result determined for the selected reactive power distribution subject equipment; calculating the fluctuation components in a plurality of periods in calculating the fluctuation component of the predicted value of the data obtained from the power system; and determining the fluctuation component to be suppressed by the reactive power and the fluctuation component to not be suppressed among the fluctuation components in the plurality of periods to obtain the required reactive power amount for the fluctuation component to be suppressed by the reactive power.
16. A voltage and reactive power monitoring/control method which is applied to a power system including a control subject equipment capable of adjusting a reactive power, and which monitors and controls a voltage and the reactive power, comprising: calculating a system status at a time of power system measurement by using a measurement data of the power system and data of a system facility of the power system; performing prediction calculation of a future system status from a time of power system measurement by using data of a calculation result of the system status at the time of power system measurement and a prediction data of power generation and load of the power system; obtaining a fluctuation component of a predicted value of data obtained from the power system, obtaining the reactive power required for suppressing the fluctuation component as a required reactive power amount, and selecting a reactive power distribution subject among a plurality of control subject equipment; performing output distribution calculation of the required reactive power amount for the selected reactive power distribution subject equipment; calculating a control instruction value for each control subject equipment from an output distribution calculation result determined for the selected reactive power distribution subject equipment; calculating the fluctuation components in a plurality of periods in calculating the fluctuation component of the predicted value of the data obtained from the power system, and determining the fluctuation component to be suppressed by the reactive power and the fluctuation component to not be suppressed among the fluctuation components in the plurality of periods to obtain the required reactive power amount for the fluctuation component to be suppressed by the reactive power.
Description
BRIEF DESCRIPTION OF DRAWINGS
(1)
(2)
(3)
(4)
(5)
(6)
(7)
(8)
(9)
(10)
(11)
(12)
(13)
(14)
(15)
(16)
DESCRIPTION OF EMBODIMENTS
(17) Hereinafter, embodiments of the present invention will be described in detail with reference to the drawings.
(18) Since the embodiments of the present invention include various modes, an overview of each embodiment will be described before starting the detailed description.
(19) Each of the embodiments of the present invention is configured with a central device that performs monitoring and controlling a power system and further an individual control device that is installed at an individual location of the power system to operate according to a transmission data from the central device.
(20) It is considered that the central device in the first embodiment which is described with reference to
(21) It is considered that the central device in the second embodiment which is described with reference to
(22) In a third embodiment, a modified alternative example of a control evaluation unit in the first or second embodiment is illustrated.
First Embodiment
(23) In the first embodiment, for example, a system configuration including a central device that is installed at a local power supply instruction station for monitoring and controlling in an area where a power system is divided into a plural parts to perform monitoring and controlling the power system, and further an individual control device that is installed at an individual location of the power system to operate according to a transmission data from the central device will be described.
(24)
(25) The power system 100 that is indicated as 100 and illustrated in
(26) The power system is configured with power supplies 110 (110a and 110b), nodes (buses) 120 (120a, 120b, 120c, 120d, 120e, 120f, 120h, 120i, and 120j), transformers 130 (130a, 130b, 130c, 130d, and 130e), branches (lines) 140 (140b, 140e, 140f, 140g, and 140h), loads 150 (150a 150b, and 150c) and the like as major main circuit constituent equipment, and disposes power condensers (SC: static condenser) 160 (160a, 160b, 160c, and 160d) and shunt reactors (ShR) 170 (170a and 170b) as equipment for power adjustment at appropriate individual locations.
(27) In addition, the transformers 130c and 130e are tapped transformers 131, and power condenser 160b and shunt reactors 170a and 170b are connected to the tertiary windings, respectively. Although not illustrated in
(28) In order to control a power system configured with a plurality of these various pieces of equipment, various measurement devices 44 are arranged at appropriate individual locations according to respective purposes at various locations of the power system. In addition, with respect to the controllable equipment among the plurality of these various pieces of equipment, the individual control devices 45 (45a, 45b) for controlling these pieces of equipment are arranged at appropriate individual locations according to the respective purposes.
(29) Among the above-described various pieces of equipments and the like, contents, structures, characteristics, and the like of equipment deeply related to the present invention are described below.
(30) First, the power source 110 includes a distributed type power source such as solar power generation or wind power generation, an inverter interconnection power source connected to the power system via an inverter, and the like besides a rotary type power source such as a thermal power generator, a hydraulic power generator, and a nuclear power generator.
(31) The measurement device 44 is a device that measures any one or a plurality of the node voltage V, the branch current I, the active power P, the reactive power Q, the power factor , the tap value, on/off information of a switch of a node, a branch, a transformer, a power condenser, a shunt reactor and the like, and the like. This is, for example, a meter transformer VT (Voltage Transformer), a meter transformer PT (Potential Transformer), and a meter current transformer CT (Current Transformer), and is Telemeter (TM) or Super Vision SV which has the function of transmitting data including a data measurement location identification ID or a built-in time stamp of the measurement device. In addition, a device, a phase measurement device (phasor measurement unit (PMU), or other measurement instrument that measures power information (phasor information of voltage) attached with absolute time using GPS may be used. The measurement device 44 is described as being in the power system 100 but may be installed on a bus or a line connected to the power source 110, the transformer 130, the tapped transformer 131, the load 150, the power condenser 160, the shunt reactor 170, the measurement device 44, and the individual control device 45.
(32) The power system of
(33) More specifically, herein, the reference bus measurement value data D5 which is the data content of the reception data 71 is any one or a plurality of data of the node voltage V, the branch current I, the power factor , the active power P, and the reactive power Q measured by the measurement device 44, is received by the voltage and reactive power monitoring/control device 10 via the communication network 300, and is stored in the internal reference bus measurement value database DB5. However, instead of directly receiving the reference bus measurement value data D5 from the measurement device 44, the reference bus measurement value data D5 may be collected at once by other monitoring devices, and after that, may be stored in the reference bus measurement value database DB5 via the communication network 300. Alternatively, the reference bus measurement value data D5 may be stored in the reference bus measurement value database DB5 from the measurement device 44 or other monitoring devices via the communication network 300. In addition, the reference bus measurement value data D5 may include a unique number for identifying data and a time stamp. In addition, the other monitoring devices are, for example, a central power supply instruction station, a system stability monitoring server, and the like.
(34) The hardware configuration of the voltage and reactive power monitoring/control device 10 in
(35) Among these components, the display unit 11 is configured as, for example, a display device, but a configuration using a printer device, a sound output device, or the like instead of or in addition to the display device may be used.
(36) The input unit 12 can be configured with at least one of a keyboard switch, a pointing device such as a mouse, a touch panel, a voice instruction device, and the like.
(37) The communication unit 13 includes a circuit and a communication protocol for connecting to the communication network 300.
(38) The CPU 14 reads and executes a predetermined computer program from the program database DB15. The CPU 14 may be configured with one or a plurality of semiconductor chips or may be configured as a computer device such as a calculation server.
(39) The memory 15 is configured as, for example, a RAM (Random Access Memory) to store the computer program read from the program database DB15 or to store calculation result data, image data, and the like required for each process. The screen data stored in the memory 14 is transmitted to the display unit 11 to be displayed. An example of the screen to be displayed will be described later.
(40) More specifically, the various databases DB are as follows. The database DB is configured with a predicted value database DB1 that stores a predicted value data D1, an distribution necessity determination reference database DB2 that stores a distribution necessity determination reference data D2, a control subject current output value database DB3 that stores a control subject current output value D3, a control subject output upper-lower limit value/increment value database DB4 that stores a control subject output upper-lower limit value/increment value data D4, a reference bus measurement value database DB5 that stores a reference bus measurement value data D5, a reference bus target value database DB6 that stores a reference bus target value data D6, a control subject sensitivity database DB7 that stores a control subject sensitivity data D7, a conversion coefficient database DB8 that stores a conversion coefficient data D8, a control subject changeable period database DB9 that stores a control subject changeable period data D9, a required reactive power calculation result database DB10 that stores a required reactive power calculation result data D10, a reactive power distribution subject selection result database DB11 that stores a reactive power distribution subject selection result data D11, an output distribution calculation result database DB12 that stores an output distribution calculation result data D12, a control instruction value calculation result database DB13 that stores a control instruction value calculation result data D13, a control evaluation result database DB14 that stores a control evaluation result data D14, a program database DB15 that stores a program D15, and a fluctuation component calculation result database DB16 that stores a fluctuation component calculation result data D16.
(41) In addition, among the data stored in these databases, a system measurement data may be collected through other monitoring/control devices or may be input from various measurement devices. In addition, a data related to system facilities can be received manually or received from the central power supply instruction station or the like. In addition, each data may be data that has been set in advance and stored in a database. In addition, data exchange via the bus line 43 is performed with respect to the data including data of an instruction value, a time, and ID.
(42)
(43) The processing functions of
(44) In the input system database DBI, the predicted value database DB1, the distribution necessity determination reference database DB2, the control subject current output value database DB3, the control subject output upper-lower limit value/increment value database DB4, the reference bus measurement value database DB5, the reference bus target value database DB6, the control subject sensitivity database DB7, the conversion coefficient database DB8, and the control subject changeable period database DB9 are positioned.
(45) In the result system database DBO, the required reactive power calculation result database DB10, the reactive power distribution subject selection result database DB11, the output distribution calculation result database DB12, the control instruction value calculation result database DB13, the control evaluation result database DB14, and the fluctuation component calculation result database DB16 are positioned.
(46) The calculation unit 41 is configured with a fluctuation component calculation unit 31, a required reactive power calculation unit 32, a reactive power distribution subject selection unit 33, an output distribution calculation unit 34, a control instruction value calculation unit 35, an output instruction unit 36, and a control evaluation unit 37.
(47) According to a series of processes of the calculation unit 41, the fluctuation component calculation unit 31 calculates a fluctuation component by using the predicted value data D1 which is the predicted value of the power system information and stores the calculated fluctuation component calculation result data D16 in the fluctuation component calculation result database DB16.
(48) The required reactive power calculation unit 32 calculates the required reactive power by using the conversion coefficient data D8 of the conversion coefficient database DB8 and the fluctuation component calculation result data D16 calculated by the fluctuation component calculation unit 31 and stores as the required reactive power calculation result data D10 in the required reactive power calculation result database DB10.
(49) The reactive power distribution subject selection unit 33 selects the reactive power distribution subject by using the control subject changeable period data D9 of the control subject changeable period database DB9, the fluctuation component calculation result data D16 calculated by the required reactive power calculation unit 32, the distribution necessity determination reference data D2 stored in the distribution necessity determination reference database DB2, the control subject current output value data D3 stored in the control subject current output value database DB3, and the control subject output upper-lower limit value/increment value data D4 stored in the control subject output upper-lower limit value/increment value database DB4. The selected reactive power distribution subject selection result is accumulated as the reactive power distribution subject selection result data D11 in the reactive power distribution subject selection result database DB11.
(50) The output distribution calculation unit 34 calculates the output distribution by using the control subject current output value data D3 stored in the control subject current output value database DB3, the control subject output upper-lower limit value/increment value data D4 stored in the control subject output upper-lower limit value/increment value database DB4, the reference bus measurement value data D5 stored in the reference bus measurement value database DB5, the reference bus target value data D6 stored in the reference bus target value database DB6, the control subject sensitivity data D7 stored in the control subject sensitivity database DB7, the calculated required reactive power calculation result data D10, and the calculated reactive power distribution subject selection result data D11 and stores as the output distribution as the output distribution calculation result data D12 in the output distribution calculation result database DB12.
(51) The control instruction value calculation unit 35 calculates the control instruction value by using the reference bus measurement value data D5 stored in the reference bus measurement value database DB5, the reference bus target value data D6 stored in the reference bus target value database DB6, the control subject sensitivity data D7 stored in the control subject sensitivity database DB7, and the calculated output distribution calculation result data D12 and stores as the control instruction value calculation result data D13 in the control instruction value calculation result database DB13.
(52) The output instruction unit 36 instructs to output the calculated control instruction value calculation result data D13.
(53) The control evaluation unit 37 evaluates control by using the calculated fluctuation component calculation result data D16, the calculated required reactive power calculation result data D10, the reactive power distribution subject selection result data D11, the output distribution calculation result data D12, and the control instruction value calculation result data D13. The evaluation result is accumulated as control evaluation result data D14 in the control evaluation result database DB14.
(54) In addition, in the display unit, various data accumulated in the databases DB is displayed in an appropriate format either alone or while illustrating correlation. For example, one or more of the predicted value data D1, the distribution necessity determination reference data D2, the control subject current output value data D3, the control subject output upper-lower limit value/increment value data D4, the reference bus measurement value data D5, the reference bus target value data D6, control subject sensitivity data D7, the calculated required reactive power calculation result data D10, the reactive power distribution subject selection result data D11, the output distribution calculation result data D12, the control instruction value calculation result data D13, and the control evaluation result data D14 is displayed.
(55) Simply describing the series of processes of the calculation unit 41 described above, it can be said that it is possible to obtain the fluctuation component from the predicted state of the power system, to determine the required reactive power required for suppressing the fluctuation component, and to determine the control subject equipment which can supply the required reactive power and the control amount thereof. In the following description, a method for realizing these series of processes will be described in detail.
(56)
(57) Returning to
(58) The memory 14 is a memory for temporarily storing the image data for display, the reference bus measurement value data D5, or each calculated temporary data and each calculation result data, and the CPU 14 generates necessary image data and displays the image data on the display unit 11 (for example, display screen). In addition, the display unit 11 of the voltage and reactive power monitoring/control device 10 may be a simple screen only for rewriting each of the control programs and the databases.
(59) A plurality of the databases DB are stored in the voltage and reactive power monitoring/control device 10 of the power system. With respect to the other databases DB (DB1 to DB14 and DB16) excluding the program database DB, the contents of data treated herein will be described more in detail.
(60)
(61)
(62) Describing the distribution necessity determination reference database DB2 more in detail, references for determining distribution necessity for, for example, a short-period fluctuation, a medium-period fluctuation, and a long-period fluctuation are described as the distribution necessity determination reference data D2. Herein, reference values of the distribution necessity determination reference data D2 are set for, for example, reactive powers Q1, Q2, and Q3 required for suppressing these fluctuations. The reference values are set in advance. However, for example, with respect to the reactive power that can be changed to both plus and minus with a constant load fluctuation, if the control is performed to sequentially correspond thereto, unnecessary control is performed. Therefore, a reference value that can be determined to exceed such a fluctuation is set. The reference values of such fluctuation data may be corrected by the operator by accumulating the system data or may be automatically corrected.
(63)
(64)
(65) The reference bus measurement value database DB5 includes the measurement time and the measured value, for example, the voltage V as the reference bus measurement value data D5. For example, one or a plurality of a voltage of the node 120 connected to the power system 100, a voltage V of the node 120 connected to the transformer 130, a voltage V of the power source 110 connected to the node 120, a voltage V of the load 150, voltages V of other nodes, branches, power sources, loads, control devices, and the like connected to the power system 100 that are measured in the measurement device 44 and other monitoring devices through a communication network are stored. In addition, the measurement device is a VT or the like. The reference bus measurement value data D5 may be obtained from the monitoring/control device, the central power supply instruction station, or the EMS or may be directly obtained from the measurement device of the entire system.
(66) The target value at each time is stored as the reference bus target value data D6 in the reference bus target value database DB6. If a target value is set in a schedule, the target value is stored every period in which the schedule is set. In addition, the value may be set and stored remotely from the monitoring/control device, the central power supply instruction station, or the EMS or may be manually set. Herein, the reference bus target value is assumed to be calculated and stored in advance in accordance with a method or the like disclosed in Voltage Stability Maintenance Measures of the Electric Power System, in Technical Report 11-73 of the Institute of Electrical Engineers of Japan, pp. 10-14 (1979).
(67) In the control subject sensitivity database DB7, as the control subject sensitivity data D7, a numerical value indicating how much the change in output of a certain control subject exerts on the bus is stored, and a sensitivity regarding the voltage V and the reactive power Q is stored. These data may be set remotely from the monitoring/control device, the central power supply instruction station, and EMS or may be manually set. In addition, by taking into consideration that the sensitivity varies every moment, these data may be sequentially calculated and stored by the following method.
(68) In addition, the above-described control subject sensitivity is a sensitivity matrix and is calculated and stored in advance or sequentially in accordance with a method or the like disclosed in a document by Yokoyama, Uniform sensitivity coefficient determination method for power system analysis and control, Journal of the Institute of Electrical Engineers of Japan, B, Vol. 94, No. 1, pp. 17 to 24 (1974), a document by CONEJO, A., GOMEZ, T., and DE LA FUENTE, J. I., Pilot-Bus Selection for Secondary Voltage Control, Eur. Trans. Electr. Power Eng., 1993, 3, (5), pp. 359-366. By using the above-described methods, there is an advantage that the sensitivity matrix can be obtained by a partial modification of the power flow calculation using the Newton-Raphson method which is often used in the related art.
(69) With respect to the fluctuations of the power system, the conversion coefficient database DB8 stores conversion coefficients for determining the reactive power required for suppressing these fluctuations. For example, in a case where the fluctuation is a fluctuation in the voltage of the power system, a coefficient for converting to the reactive power required for suppressing this voltage fluctuation is stored as a conversion coefficient. It is preferable that the conversion coefficients are prepared for various types of fluctuations and are prepared for each fluctuation period even though the fluctuation is of the same type.
(70) The control subject changeable period database DB9 stores response characteristics, adjustment power, and the like for each controllable equipment arranged in the power system. For example, the control subject changeable period database DB9 stores information indicating that coping with the fluctuations in a short period is not appropriate due to a mechanical structure but suppressing the fluctuations in a long period is appropriate, information indicating that suppressing the fluctuations in a short period is appropriate due to the configuration with power elements but an adjustment power is limited due to the included capacitor.
(71) The required reactive power for each fluctuation obtained from the prediction time-series average voltage fluctuation as illustrated in
(72) The selection result of the reactive power distribution subject determined by using the required reactive power calculation result data D10 and the distribution necessity determination reference data D2 is stored as the reactive power distribution subject selection result data D11 in the reactive power distribution subject selection result database DB11. This reactive power distribution subject selection result data D11 is included, so that there is an effect that unnecessary distribution to the system status varying every moment can be avoided.
(73) The calculation result of the output distribution as illustrated in
(74) The calculation result of the control instruction value obtained from the output distribution calculation result data D12 is stored as the control instruction value calculation result data D13 in the control instruction value calculation database DB13.
(75) As illustrated in
(76) Next, the contents of the calculation processes of the voltage and reactive power monitoring/control device 10 will be described with reference to
(77) First, in a fluctuation component calculation process step S31, fluctuation component calculation is performed by using the predicted value data D1 which is a predicted value of the power system information. The result of the fluctuation component calculation is stored as the fluctuation component calculation result data D16 in the fluctuation component calculation result database DB16.
(78) Next, in a required reactive power calculation process step S32, required reactive power calculation is performed by using the fluctuation component calculation result data D16 and the conversion coefficient data D8. The result of the required reactive power calculation is stored as the required reactive power calculation result data D10 in the required reactive power calculation result database DB2.
(79) Next, in a reactive power distribution subject selection process step S33, reactive power distribution subject selection is performed by using the control subject changeable period data D9, the distribution necessity determination reference data D2, the control subject current output value data D3, the control subject output upper-lower limit value/increment value data D4, and the calculated required reactive power calculation result data D10. The result of the reactive power distribution subject selection is stored as the reactive power distribution subject selection result data D11 in the reactive power distribution subject selection result database DB11.
(80) In an output distribution calculation process step S34, output distribution calculation is performed by using the control subject current output value data D3, the control subject output upper-lower limit value/increment value data D4, the reference bus measurement value data D5, the reference bus target value data D6, the control subject sensitivity data D7, the calculated required reactive power calculation result data D10, and the reactive power distribution subject selection result data D11. The result of the output distribution calculation is stored as the output distribution calculation result data D12 in the output distribution calculation result database DB12.
(81) Next, in a control instruction value calculation process step S35, control instruction value calculation is performed by using the reference bus measurement value data D5, the reference bus target value data D6, the control subject sensitivity data D7, and the calculated output distribution calculation result data D12. The result of the control instruction value calculation is stored as the control instruction value calculation data D13 in the control instruction value calculation database DB13.
(82) Next, in an output instruction process step S36, output instruction is performed by using the calculated control instruction value calculation result data D13.
(83) Next, in a process step S37, control evaluation is performed by using the calculated required reactive power calculation result data D10, the reactive power distribution subject selection result data D11, the output distribution calculation result data D12, the control instruction value calculation result data D13, the fluctuation component calculation result data D16. The result of the control evaluation is stored as the control evaluation result data D14 in the control evaluation result database DB14.
(84) Finally, in a screen display process step S11, screen display of one or more of the predicted value data D1, the distribution necessity determination reference data D2, the control subject current output value data D3, the control subject output upper-lower limit value/increment value data D4, the reference bus measurement value data D5, the reference bus target value data D6, the control subject sensitivity data D7, the conversion coefficient D8, the control subject changeable period data D9, the calculated required reactive power calculation result data D10, the reactive power distribution subject selection data D11, the output distribution calculation result data D12, the control instruction value calculation result data D13, the control evaluation result data D14, and the fluctuation component calculation result data D16 is performed. In addition, various calculation results and data accumulated in the memory during the calculation may be sequentially displayed on screens of other monitoring devices. With such a configuration, it is possible for the operator to easily grasp the operation state of the voltage and reactive power monitoring/control device 10. The flow of the above processes will be described step by step. In a case where a situation in which calculation cannot be executed occurs in some of the process steps of
(85) Hereinafter, the specific contents of each process will be described. First, in the fluctuation component calculation process step S31, the fluctuation component calculation is performed by using the predicted value data D1 which is the predicted value of the power system information, and the result is stored in the fluctuation component calculation result database DB16.
(86) Herein, an example of the fluctuation component calculation method is described with reference to
(87) In the example of
(88) With such a configuration, there is an effect that it is possible to easily determine how much the fluctuation component has the voltage change width. Herein, the example of the average voltage Vi is illustrated. However, as long as it can be converted into the required reactive power in the required reactive power calculation process step S32, a time-series waveform of a representative voltage may be used, or a time-series data of a demand may be used. As the filter for each fluctuation period, any processing device that passes a set fluctuation period or removes other than the set fluctuation period such as a high-pass filter, a low-pass filter, or a band pass filter may be used. With such a configuration, there is an effect that the magnitude of the fluctuation at a desired fluctuation period can be resolved. The filter is configured so that the set fluctuation period of the filter can be adjusted later. With such a configuration, there is an effect that, when a facility changes, the operator can extract the component of the desired fluctuation period corresponding to the facility.
(89) In the required reactive power calculation process step S32, the required reactive power calculation is performed by using the fluctuation component calculation result data D16 stored in the fluctuation component calculation process step S31, and the result is stored in the required reactive power calculation result database DB10. Herein, similarly to the description of the fluctuation component calculation process step S31, the pre-process of the required reactive power calculation method will be described with reference to
(90) In
(91) In the reactive power distribution subject selection process step S33, the reactive power distribution subject selection is performed by using the control subject changeable period data D9, the distribution necessity determination reference data D2, the control subject current output value D3, the control subject output upper-lower limit/increment value D4, and the required reactive power calculation result data D10 calculated in the power calculation process step S32, and the result is stored in the reactive power distribution subject selection result database DB11.
(92) More specifically, first, in a case where satisfying the reference value of the distribution necessity determination reference data D2 is satisfied with respect to the reactive powers Q1, Q2, and Q3 required for suppressing the fluctuations, the process proceeds to the calculation for selecting the reactive power distribution subject. In the distribution necessity determination reference database DB2 illustrated in
(93) With such a configuration, there is an effect that the reactive power distribution for events such as the corresponding unnecessary voltage fluctuation becomes unnecessary. This reference value is set in advance. However, for example, if the reactive power that can be changed both positively and negatively due to a constant load fluctuation is performed sequentially, useless control is performed. For this reason, a reference value that can be determined to exceed the fluctuation is set. The reference values of such fluctuation data may be corrected by the operator by accumulating the system data or may be automatically corrected.
(94) Subsequently, in the reactive power distribution subject selection process step S33, by using the control subject current output value data D3 and the control subject output upper-lower limit value/increment value data D4, it is determined whether or not the control subject has the current adjustment power. More specifically, if the current output of the control subject is the upper limit value or a value close thereto, the output can be adjusted in the decreasing direction but cannot be adjusted in the increasing direction, and thus, in a case where the output is required in the increasing and decreasing directions, the output is removed from the subject. On the other hand, in a case where the required reactive power is required in the decreasing direction, since the control subject has an adjustment power, so that the output is allowed to be included in the subject. The same is applied to the increasing direction. If the current output of the control subject is not the upper limit value or a value close thereto, the output is adjustable and is allowed to be included in the subject.
(95) Finally, in the reactive power distribution subject selection process step S33, the corresponding fluctuation is selected from the changeable periods of each control subject by using the control subject changeable period data D9 retained in advance in the control subject changeable period database DB9. Since the response characteristic (changeable period), the adjustment power, and the like are stored in the control subject changeable period database DB9 for each control subject (controllable equipment) arranged in the power system, it is possible to select a controllable equipment which becomes the reactive power distribution subject. In addition, it is possible to grasp the total adjustment power by the controllable equipment appropriate for suppressing the fluctuation in the fluctuation period, and if the corresponding control subject is insufficient, the control subject for an auxiliary fluctuation period may be retained in advance so that the control subject can be assisted by another control subject having a fluctuation period close to the fluctuation period. With such a configuration, there is an effect that the reactive power distribution subject selection is performed without missing. In a case where the control subject is still insufficient, an alarm is issued. With such a configuration, there is an effect that it is possible to notify the operator of which period fluctuation the reactive power distribution subject is insufficient.
(96) In the output distribution calculation process step S34, the output distribution calculation is performed by using the control subject current output value data D3, the control subject output upper-lower limit value/increment value data D4, the reference bus measurement value data D5, the reference bus target value data D6, the control subject sensitivity data D7, the required reactive power calculation result data D10 stored in the fluctuation component calculation process step S31, and the reactive power distribution subject selection result data D11 stored in the reactive power distribution subject selection process step S33, and the result is stored in the output distribution calculation result database DB12.
(97) Herein, an example of the output distribution calculation method will be described with reference to
(98) In the illustrated example, the upper limit of the reactive power output of the generator G1 at the distance dl is Qg1max, the upper limit of the reactive power output of the generator G2 is Qg2max, the reactive power output of the generator G1 at the distance d0 (initial) is Qg01, and the upper limit of the reactive power output of G2 is Qg02. In this case, since the upper limits Qg1max and Qg2max of the reactive power outputs of the generators G1 and G2 are different from the initial values Qg01 and Qg02, the respective slopes are different. Therefore, when the upper portion of
(99) In the lower portion of
(100) In the calculation of the reactive power distribution by the reactive power supply device, it is possible to equally distribute the reactive power amount by moving the distance ek leftward and rightward for each increment and performing calculation. In addition, since the distance is moved leftward and rightward for each increment, the number of times of control can be equally distributed, so that there is an effect that it is possible to allow the number of times of manipulation not to be biased to only one facility. With such a configuration, there is an effect that it is possible to prevent maintenance and inspection of the facility from being biased. Although the control of the reactive power supply device is discrete, the discrete values can be approximated and thus, can be treated as a straight line.
(101) Herein, the upper portion and the lower portion of
(102) In addition, although the generators that can be treated as continuous values and the discrete reactive power supply devices described above are exemplified as the control subject equipments capable of controlling the reactive power, representative ones other than the control subject equipments include an LRT, an SC, and an ShR. Since the LRT moves the tap and the SC and the ShR move an on/off device (switch), these devices are forced to be discrete. In these control subject equipments, it is a reason why it is necessary to discretely manipulate a mechanical mechanism unit such as a tap or a switch.
(103) In the control instruction value calculation step S35, the control instruction value calculation is performed by using the reference bus measurement value data D5, the reference bus target value data D6, the control subject sensitivity data D7, and the output distribution calculation result data D12 stored at the output distribution calculation process step S34, and the result is stored in the control instruction value calculation database 55. The control instruction value can be calculated by solving a quadratic programming method using the output distribution calculated in the output distribution calculation process step S34 and the control subject sensitivity.
(104) The control instruction value may be performed in accordance with a method disclosed in, for example, a document by A. Conejo, M. J. Aguilar (Secondary voltage control: Nonlinear selection of pilot buses, design of an optimal control law, and simulation results, IEE Proc.-Gener. Transm. Distrib., Vol. 145, No. 1. (1998), pp. 77-81), a document by J. L. Sancha, J. L. FernAndez, A. Cortes, and J. T. Abarca (SECONDARY VOLTAGE CONTROL: ANALYSIS, SOLUTIONS AND SIMULATION RESULTS FOR THE SPANISH TRANSMISSION SYSTEM, IEEE, 1995) or the like.
(105) Herein, an example of a quadratic objective function and a linear constraint will be described using the following Formulas of the latter document as an example. Formula (1) is a quadratic objective function, and Formulas (2) to (5) represent upper and lower limit constraints as linear constraints, respectively.
(106) In these series of formulas V.sub.p is a voltage deviation of a reference bus, V.sub.g is a voltage correction value of a bus of a control subject equipment, Q.sub.g is a reactive power deviation of the bus of the control subject equipment, V.sub.ps is a voltage of a critical bus of a non-control subject equipment, C.sub.v is a sensitivity matrix relating to a voltage value increment of the control subject equipment and a voltage value increment of the reference bus, C.sub.vs is a sensitivity matrix relating to a voltage value increment of the control subject equipment and a voltage value increment of a bus of a load not selected as the reference bus, C.sub.q is a sensitivity matrix relating to a voltage value increment of the control subject equipment and an applied reactive power increment of the control subject equipment, is a parameter for determining a closed loop time constant, m is a weight parameter for determining relative importance of two constituent elements of the objective function, V.sub.g.sup.max, Q.sub.g.sup.max, and V.sub.ps.sup.max are upper limit constraints, V.sub.g.sup.min, Q.sub.g.sup.max, and V.sub.ps.sup.min are lower limit constraints, and V.sub.p and V.sub.ps, and V.sub.g and Q.sub.g are real-time measurement values required to calculate the objective function.
[Formula 1]
Minimise{(V.sub.pC.sub.vV.sub.g).sup.2+m(aQ.sub.gC.sub.qV.sub.g).sup.2}(1)
[Formula 2]
V.sub.g.sup.minV.sub.g+V.sub.gV.sub.g.sup.max(2)
[Formula 3]
Q.sub.g.sup.minQ.sub.g+C.sub.qV.sub.gQ.sub.g.sup.max(3)
[Formula 4]
V.sub.ps.sup.minV.sub.ps+C.sub.vsV.sub.gV.sub.ps.sup.max(4)
[Formula 5]
|V.sub.g|V.sub.g.sup.max(5)
(107) Herein, Formula (1) includes two elements. The first one is an element minimizing the deviation of the reference bus voltage, and the second one is an element minimizing the deviation of the reactive power between the control subject equipments from the target value. Formulas (2) to (5) are the upper and lower limit constraints. Each sensitivity matrix corresponds to the control subject sensitivity data and is given by the control subject sensitivity database DB7. With such a configuration, the voltage deviation from the reference bus target value is minimized, and the deviation of the target reactive power determined by the reactive power output distribution on the generators included in the preset zones is minimized.
(108) In addition, as described above in the output distribution calculation process step S34, by performing the output distribution calculation as illustrated in
(109) Herein, with reference to the upper portion of
[Formula 6]
Q.sub.gi=Q.sub.g0i+k.sub.idQ.sub.gi(6)
(110) In Formula (6), Q.sub.gi is the reactive power deviation of the control subject equipment i, Qg.sub.0i is the initial reference value of the reactive power of the control subject equipment i, k.sub.i is the set slope of the control subject equipment i, the adjustment of the reactive power depends on the reference, and Q.sub.gi is the instantaneous reactive power value of the control subject equipment i.
(111) In addition, a document by A. Conejo, M. J. Aguilar, Secondary Voltage control: Nonlinear selection of pilot buses, design of an optimal control law, and simulation results, IEE Proc.-Gener. Transm. Distrib., Vol. 145, No. 1. (1998), pp. 77-81 or a document by Omura, Uryo: Study considering multiple operating points of basic voltage control strategy, Materials of Joint Study Group on Electric Power Technology and Electric Power System Technology, The Institute of Electrical Engineers of Japan, PE-03-122, PSE-03-133, pp. 7-11, 2003 discloses a method of selecting (setting) a reference bus, and the reference bus may be set by using the method of selecting a reference bus or the like disclosed in these documents or the like, or the reference bus may be set in advance. In the case of setting the reference bus in advance, the reference bus may be set according to the knowledge in the related art or may be set again by using the method of the above-described document. The number of reference buses may be decreased or may be increased. With such a configuration, it is possible to set the reference bus appropriately for the current observation point.
(112) By performing the output distribution calculation in the output distribution calculation process step S34 and the control instruction value calculation in the control instruction value calculation process step S35 described above for each fluctuation component with respect to the control subject equipment for the fluctuation component obtained by performing the fluctuation component calculation in the fluctuation component calculation process step S31, performing the required reactive power amount calculation in the required reactive power calculation process step S32, and selecting as the reactive power distribution subject in the reactive power distribution subject selection process step S33, the output distribution and the output instruction can be performed for any fluctuation component, and thus, even though the output fluctuation of the renewable energy or the change of the power source configuration or the system configuration occurs due to the weather along with the elapse of time, it is possible to maintain the balance between the voltage and the reactive power of the power system, and it is possible to improve economic efficiency.
(113) In the output instruction process step S36, the output instruction is performed by using the control instruction value calculation result data D13 stored in the control instruction value calculation process step S35. The transmission destination is, for example, an individual control device 45 for maintaining balance between the voltage and the reactive power in a certain area, and the individual control device 45 receives one or more of the control instruction value calculation result data D13 at a preset period and performs the voltage and reactive power control.
(114) In the control evaluation process step S37, in order to easily check whether or not the operator correctly follows the target value as the calculation of the control evaluation performed by using the required reactive power calculation result data D10 stored in the required reactive power calculation process step S32, the reactive power distribution subject selection result data D11 stored in the reactive power distribution subject selection process step S33, the output distribution calculation result data D12 stored in the output distribution calculation process step S34, and the control instruction value calculation result data D13 stored in the control instruction value calculation process step S35, a deviation between the target voltage and the measured value is calculated, and the result is stored in the control evaluation result database 56.
(115) In addition, in the control evaluation process step S37, probability distributions such as V.sub.p, V.sub.g, and Q.sub.gi indicating how much the voltage state and distribution effect are deviated as illustrated in
(116) With such a configuration, there is an effect that, on the screen 90 as illustrated in
(117) In addition, the display example of the screen 90 illustrated in
(118) In the screen display process step S11, the screen display of one or more of the predicted value data D1, the distribution necessity determination reference data D2, the control subject current output value data D3, the control subject output upper-lower limit value/increment value data D4, the reference bus measurement value data D5, the reference bus target value data D6, the control subject sensitivity data D7, the required reactive power calculation result data D10 stored in the required reactive power calculation process step S32, the reactive power distribution stored in the reactive power distribution subject selection process step S33 The target selection result data D11, the output distribution calculation result data D12 stored in the output distribution calculation process step S34, the control instruction value calculation result data D13 stored in the control instruction value calculation process step S35, and the control evaluation result data D14 stored in the control evaluation process step S37 is performed.
(119) As illustrated in
Second Embodiment
(120) Although the present invention discloses the system configuration including the central device for monitoring and controlling the power system and the individual control device installed at an individual location of the power system and operated by the transmission data from the central device, it is considered that the central device in the second embodiment described with reference to
(121) In this case, the voltage and reactive power monitoring/control device 10, which is the central device of the second embodiment, treats the data possessed by the central power supply instruction station, and the data obtained from the power system are also more various.
(122) In the second embodiment, since one or more calculation units for the predicted value data D1 and the reference bus target value data D6 according to the first embodiment are provided, the second embodiment is different from the first embodiment in terms of the input data, the configuration, the program, and the control flow.
(123) As a result, according to the first embodiment, even if it becomes impossible to receive the predicted value data D1 and the reference bus target value data D6 from the other device, it is possible to provide one or both of the effects of maintaining balance between the voltage and the reactive power and improving the economic efficiency in the power system by only the voltage and reactive power monitoring/control device 10. Hereinafter, an example of the voltage and reactive power monitoring/control device according to the second embodiment will be described. However, descriptions of the same operations at the same components as those of the first embodiment will be omitted.
(124)
(125) With respect to the hardware configuration of the voltage and reactive power monitoring/control device 10, in the second embodiment, two new databases DB are additionally provided. These are a system measurement database DB17 and a system facility database DB18 positioned in the input side database DBI of
(126)
(127)
(128) The above major different points will be described in detail below. First, as a premise thereof, the system measurement data D17 will be described. In addition, the reference bus measurement value data D5 is positioned as the data measured at the reference bus, but the system measurement data D17 may be regarded as a wider-range measurement data without specifying the measurement position. Similarly to the reference bus measurement value data D5, the system measurement data D17 of
(129) Next, the system facility data D18 will be described. A system configuration, a line impedance (R+jX), a ground capacitance (admittance: Y), a power source data, and the like are included and stored as the system facility data D18 in the system facility database DB18 of
(130) By using the system measurement data D17 and the system facility data D18, additional processes occur in the second embodiment in comparison with the calculation process contents of the first embodiment. In
(131) In the flowchart illustrated in
(132) In the status estimation calculation process step S38 of
(133) In addition, the status estimation calculation by the status estimation calculation program P38 is a calculation function of determining whether or not an abnormal data exists in an observation data and eliminating the abnormal data based on the observation data and the connection data of substations, power plants, and a power transmission/distribution equipment starting from a transmission line and estimating a likely system status at a specific time cross-section. Herein, the status estimation calculation may be performed in accordance with various methods disclosed in, for example, a document by Lars Holten, Anders Gjelsvlk, Sverre Adam, F. F. Wu, and Wen-Hs lung E. Liu, Comparison of Different Methods for Status estimation, IEEE Transaction on Power Systems, Vol. 3 (1988), pp. 1798-1806.
(134) In the predicted value calculation process step S39, the prediction calculation of the future system status from the time of the system measurement is performed by the predicted value calculation program P39 by using the status estimation calculation result data, the total demand prediction result data, the generator fuel consumption characteristic data, the data of the ratio of the substation load to the total demand, and the substation load PQ correlation data, and the system status is stored in the predicted value database DB1. For example, the total demand prediction result data may be calculated in accordance with a demand prediction method disclosed in a document by Ryoichi Hara, Analysis and prediction technique of time-series data related to supply and demand operation of power system, Journal of the Institute of Electrical Engineers of Japan, B, Vol. 134, No. 4, 2014, pp. 276-279, a method disclosed in a document by Kenichi et al., Development of short-term ahead power demand prediction method, Joint Study Group on Electric Power Technology and Electric Power System. Technology, The Institute of Electrical Engineers of Japan, PE-08-120, PSE-08-129, 2008, pp. 25-28, and the like. Alternatively, the total demand prediction result data to be performed at the central power supply instruction station may be periodically obtained via the communication network 300 or may be set in advance.
(135) In the case of the second embodiment, it is assumed that the voltage and reactive power monitoring/control device 10, which is the central device, cooperates with a central power supply instruction station which performs monitoring and controlling the entire power system or is installed at the central power supply instruction station to perform intra-area control. However, the data to be mainly used in the status estimation calculation process step S38 and the predicted value calculation process step S39 can be obtained by cooperation with the central power supply instruction station.
(136) The predicted value calculation in the predicted value calculation process step S39 can be performed in accordance with, for example, a method disclosed by Takahiro Ishida, et al., Predictive Preceding Voltage and Reactive Power Control Scheme to Key System Using LP Method, Electrotechnical Theory B, Vol. 117, No. 8, 1997, pp. 1116-1120.
(137) More specifically, the generator active power output of each generator is predicted and calculated from the total demand prediction result data and the generator fuel consumption characteristic data by using ELD (economic load distribution). In addition, the substation individual active power load is predicted and calculated from the total demand prediction result data and the data of the ratio of the substation load to the total demand by using Formula (7). In addition, in Formula (7), P.sub.li is the prediction result of the active power load of the substation i, P.sub.all is the prediction result of the total demand, and ratio.sub.i is the ratio of the active power load of the substation i to the total demand.
[Formula 7]
P.sub.li=P.sub.allratio.sub.i(7)
(138) In addition, the substation individual reactive power load is estimated and calculated from the prediction result of the substation individual active power load and the substation load PQ correlation data by using Formula (8). In Formula (8), Q.sub.li is the prediction result of the reactive power load of the substation i, and f.sub.i is the PQ correlation of the substation i.
[Formula 8]
Q.sub.li=f.sub.i(P.sub.li)(8)
(139) In addition, the power flow state in the future time cross-section from the prediction result of the generator active power output, the prediction result of the substation individual active power load, and the prediction result of the substation individual reactive power load by using an AC power flow calculation method. Thus, the predicted value data D1 can be obtained. Herein, the AC power flow calculation method can be performed in accordance with, for example, a method disclosed by William F Tinney and Clifford E Hart, Power Flow Solution by Newton's Method, IEEE Transaction on Power Apparatus and Systems, Vol. PAS-86, No. 11 (1967) pp. 1449-1967.
(140) In the reference bus target value calculation process step S40, the reference bus target value calculation is performed by using the predicted value data D1, the status estimation result data, and the system facility data D18. As described in the first embodiment, the reference bus target value may be calculated in an offline manner in accordance with a method or the like disclosed in Voltage Stability Maintenance Measures of the Electric Power System, in Technical Report 11-73 of the Institute of Electrical Engineers of Japan, pp. 10-14 (1979) or may be calculated in accordance with a method or the like disclosed in a document by Junki Someya et al., Study of optimum control of reference voltage by interior point method in East Japan power system, 2003, National Convention of the Institute of Electrical Engineers of Japan, 6-159, pp. 273-274. With such a configuration, it is predicted that the output of renewable energy fluctuates due to the weather along with the elapse of time, the output distribution and the output instruction can be performed for any fluctuation component, so that it is possible to maintain the balance between the voltage and the reactive power of the power system, and it is possible to improve economic efficiency.
Third Embodiment
(141) In a third embodiment, as the contents of the control evaluation in step S37 performed by the control evaluation unit 37 in the first or second embodiment, an example of a screen of a trend display of the required reactive power, the future prediction, the current/past reactive power equipment capacity, and the future required equipment capacity is additionally illustrated. The equipment configuration and the evaluation flow are the same as those in the first embodiment or the second embodiment.
(142) The display example of the screen 90 illustrated in
(143) By using the screen of
REFERENCE SIGNS LIST
(144) 10: voltage and reactive power monitoring/control device 12: input unit 13: communication unit 14: CPU 15: memory DB1: predicted value database (predicted value data D1) DB2: distribution necessity determination reference database (distribution necessity determination reference data D2) DB 3: control subject current output value database (control subject current output value data D3) DB 4: control subject output upper-lower limit value/increment value database (control subject output upper-lower limit value/increment value data D4) DB 5: reference bus measurement value database (reference bus measurement value data D5) DB 6: reference bus target value database (reference bus target value data D6) DB 7: control subject sensitivity database (control subject sensitivity data D7) DB 8: conversion coefficient database (conversion coefficient data D8) DB 9: control subject changeable period database (control subject changeable period data D9) 31: fluctuation component calculation unit 32: required reactive power calculation unit 33: reactive power distribution subject selection unit 34: output distribution calculation unit 35: control instruction value calculation unit 36: output instruction unit 37: control evaluation unit 40: input system database 41: calculation unit 42: result system database 43: bus line 44: measurement device 45a, 45b: individual control device 46a, 46b, 46c, 46d, 46e: control device DB10: required reactive power calculation result database (required reactive power calculation result data D10) DB11: reactive power distribution subject selection result database (reactive power distribution subject selection result data D11) DB12: output distribution calculation result database (output distribution calculation result data D12) DB13: control instruction value calculation result database (control instruction value calculation result data D13) DB14: control evaluation result database (control evaluation result data D14) DB15: program database (program data D15) DB16: fluctuation component calculation result database (fluctuation component calculation result data D16) 71: reception data (reference bus measurement value data D5) 72: transmission data (output command value calculation result data D13) 100: transmission system 110a, 110b: power supply 120a, 120b, 120c, 120d, 120e, 120f, 120h, 120i, 120j: node 130a, 130b, 130c, 130d, 130e: transformer 140b, 140e, 140f, 140g, 140h: branch 150a, 150b, 150c: load 160a, 160b, 160c, 160d: power condenser 170a, 170b: shunt reactor 300: communication network