CRANE COMPRISING COUNTERJIB, AND METHOD FOR ERECTING THE COUNTERJIB
20230051341 · 2023-02-16
Inventors
Cpc classification
B66C23/365
PERFORMING OPERATIONS; TRANSPORTING
International classification
Abstract
This invention relates to a crane in particular a mobile crane or crawler crane, comprising a main boom and a counter-boom as well asan erecting trestle arranged on the uppercarriage of the crane, which is connected to a guying of the counter-boom via a cable adjuster, wherein there is provided at least one pressure prop articulated to the counter-boom or on the pivot axis of the counter-boom in order to temporarily receive the cable adjuster and/or the guying, wherein the receiving positionpoint of the pressure prop is designed such that the cable adjuster or guying can lift off from the pressure prop on its own at a particular erecting angle of the counter-boom.
Claims
1. A crane comprising a main boom and a counter-boom as well as an erecting trestle arranged on the uppercarriage of the crane, which is connected to a guying of the counter-boom via a cable adjuster, wherein at least one pressure prop articulated to the counter-boom or on the pivot axis of the counter-boom is provided in order to temporarily receive the cable adjuster and/or the guying, wherein the receiving point of the pressure prop is designed such that the cable adjuster or guying can lift off from the pressure prop on its own at a particular erecting angle of the counter-boom.
2. The crane according to claim 1, wherein the pressure prop is pivotally attached to the back of the counter-boom in the vicinity of its boom foot or its pivot axis.
3. The crane according to claim 2, wherein the bearing point of the pressure prop for receiving the cable adjuster includes an arresting device or a stop for the cable adjuster/guying received in order to be able to apply a tensile force causing a pivotal movement of the pressure prop onto the pressure prop by means of the cable adjuster.
4. The crane according to claim 3, wherein by means of the bearing point of the pressure prop the roller axis of a top block of the cable adjuster can be received, wherein a locking mechanism is provided for the temporary fixation of the roller axis at the bearing point.
5. The crane according to claim 1, wherein the erecting trestle is designed as a stationary .
6. The crane according to claim 1, wherein the counter-boom is a lattice boom.
7. A method for erecting the counter-boom of a crane according to claim 3, wherein the cable adjuster or guying is received by the bearing point of the pressure prop at the beginning of the erecting process of the counter-boom at a small erecting angle of the counter-boom, in order to be urged away from the back of the counter-boom by means of the pressure prop, and the cable adjuster or guying lifts off from the pressure prop on its own at a defined erecting angle of the counter-boom.
8. The method according to claim 7, wherein in a first step the counter-boom is mounted on the uppercarriage together with the pressure prop.
9. The method according to claim 8, wherein after the assembly of the counter-boom, the pressure prop is folded forwards in the direction of the counter-boom tip, the cable adjuster is connected to the guying, and the pressure prop is deposited on the bearing point.
10. The method according to claim 9, wherein by retracting the retracting mechanism of the cable adjuster, the pressure prop is erected and the guying is tensioned.
11. The method according to claim 10, wherein the counter-boom is erected by retracting the retracting mechanism of the cable adjuster.
12. The method according to claim 7, wherein the pressure prop is connected to the cable adjuster or the guying only for erecting the counter-boom.
13. The crane according to claim 2, wherein the pressure prop is pivotable about a horizontal axis.
14. The crane according to claim 5, wherein the erecting trestle is designed on the uppercarriage as a stationary and is mounted at the rear end of the uppercarriage, wherein the erecting trestle receives the retracting winch of the cable adjuster.
Description
BRIEF DESCRIPTION OF THE FIGURES
[0022] Further advantages and properties of the invention will be explained in detail below with reference to an exemplary embodiment illustrated in the Figures. In the drawing:
[0023]
[0024]
[0025]
[0026]
DETAILED DESCRIPTION
[0027] The crane constructions according to the prior art, as shown in
[0028] The construction according to the invention is shown in
[0029] At the rear end of the uppercarriage 2 an erecting trestle 40 is located, which is stationarily mounted on the uppercarriage 12 as a rigid construction. The erecting trestle 40 substantially is triangular. At the uppermost point of the erecting trestle 40 the cable adjuster 5 is mounted. The length of the cable adjuster 5 can be set by means of the retracting mechanism 5a, which likewise is mounted on the erecting trestle 40.
[0030] The guying 6, consisting of individual guy rods, is bolted directly to the top block 51 of the cable adjuster 5. By actuating the retracting mechanism 5a, i.e. by retracting the cable, the length of the cable adjuster 5 is reduced, whereby the guying can be tensioned, varied in length, and the derrick boom 3 can be luffed.
[0031] The pressure prop 311 according to the invention is mounted on the articulation foot of the derrick boom 3 so as to be pivotable about a horizontal axis. Its free end is provided with a suitable bearing point 311a in order to receive the top block 51 and exert a compressive force on the pressure prop 311.
[0032] The assembly and deposition process of the derrick boom 6 can be illustrated with reference to the crane states of
[0033] In the succeeding method step as shown in
[0034] In the next method step as shown in
[0035] By further retraction of the stranding of the cable adjuster 5 by means of the retracting mechanism 5a, the counter-boom 3 can be erected, which is shown in
[0036] Accordingly, neither the cable adjuster 5 nor the guying 6 contacts the pressure prop 311 during the regular crane operation. The pressure prop hence remains functionless during the entire crane operation and is only required for erecting the derrick boom 3.
[0037] In
[0038] In the crane according to the invention, a distinctly smaller length L at the same time is necessary for the cable length in the retracting mechanism of the cable adjuster 5. A direct comparison of a stationary erecting trestle 4 of conventional construction (
[0039] Furthermore, the solution according to the invention also provides a better lever arm H′ for the cable adjuster 5 (see
[0040] In addition, a slightly better geometry can be obtained in the crane according to the invention (