MOVABLE WATER-PERMEABLE PILE SPUR DIKE AND OPERATION METHOD THEREOF
20240003107 ยท 2024-01-04
Inventors
- Huichao DAI (Beijing, CN)
- Jinqiao MAO (Nanjing, Jiangsu, CN)
- Hanmei LI (Nanjing, Jiangsu, CN)
- Yiqing GONG (Nanjing, Jiangsu, CN)
- Jie DAI (Nanjing, Jiangsu, CN)
Cpc classification
E02B3/02
FIXED CONSTRUCTIONS
International classification
E02B3/06
FIXED CONSTRUCTIONS
Abstract
The present invention has disclosed a movable water-permeable pile spur dike and an operation method thereof. The pile spur dike includes a fixed rail, a plurality of movable rails, a plurality of movable water-permeable piles, pressure sensors, flow meters and a control platform, wherein the plurality of movable water-permeable piles are arranged on the fixed rail and the plurality of movable rails, the pressure sensor and the flow meter are arranged at each monitoring point on the outer side wall of each movable water-permeable pile, the control platform is used for analysis and calculation according to the monitoring data from each pressure sensor and each flow meter and adjusts the positions of each movable rail and each movable water-permeable pile, so that the water flow velocity and spur dike's pressure at each monitoring point are less than a corresponding flow velocity threshold value and pressure threshold value.
Claims
1. A movable water-permeable pile spur dike, comprising a fixed rail (2), a plurality of movable rails (3), a plurality of movable water-permeable piles (1), pressure sensors (11), flow meters (12) and a control platform (4), wherein one end of each movable rail (3) is slidably connected to one side of the downstream face of said fixed rail (2), and can move relatively in the extending direction of said fixed rail (2); said plurality of movable water-permeable piles (1) are arranged on said fixed rail (2) and said plurality of movable rails (3); said pressure sensors (11) and said flow meter (12) are arranged at each monitoring point on the outer side wall of each movable water-permeable pile (1) and respectively used to monitor the changes in the water pressure on each monitoring point and the changes in the water flow velocity about it; said plurality of movable rail (3), said plurality of movable water-permeable pile (1), each of said pressure sensors (11) and each flow meter (12) are respectively connected to said control platform (4) in a communication mode, which is used for analysis and calculation according to the monitoring data from each of said pressure sensors (11) and each flow meter (12) and adjusts the positions of each movable rail (3) and each movable water-permeable pile (1), so that the water flow velocity and spur dike's pressure at each monitoring point are both less than a corresponding flow velocity threshold value and pressure threshold value, and the spur dike's water permeability falls within a setting range.
2. The movable water-permeable pile spur dike according to claim 1, wherein each movable water-permeable pile (1) comprises a hollow cylinder, of said hollow cylinder, the upstream face is provided with a plurality of upstream face permeable holes (14) whose diameters increase from top to bottom, and the downstream face is provided with a plurality of downstream face permeable holes (15) whose diameters decrease from top to bottom, each upstream face permeable hole (14) and each downstream face permeable hole (15) penetrate through said water-permeable pile to its hollow, and said upstream face permeable holes (14) and said downstream face permeable holes (15) are completely alternately arranged in the vertical direction.
3. The movable water-permeable pile spur dike according to claim 1, wherein the upper surfaces of said fixed rail (2) and said plurality of movable rail (3) are provided with two or more than two pile-sliding grooves (21) arranged in parallel, two sides of each pile-sliding groove (21) are provided with tooth-shaped grooves (2101); the bottom of each water-movable permeable pile (1) is provided with two or more than two rows of pile roller groups, each of which corresponds to one pile-sliding groove (21), and each of which comprises one or more than one pile roller unit, each pile roller unit comprises a connector, a pile roller (61) and an electromagnetic group (6301), of said connector, the top is embedded inside said mobile water-permeable pile (1), the middle part is a hollow connecting block (6203), and the two ends of the bottom extend downwards to form connecting pieces (6202), both of which are connected by a connecting rod (6201), said connecting rod (6201) passes through the center of said pile roller (61), a pile-fixing clamp (63) is sleeved on said connecting rod (6201), said electromagnetic group (6301) is arranged in the hollow connecting block (6203) of said connector, said pile roller (61) and said electromagnetic group (6301) are connected with said control platform (4) in a communication mode, so as to be rolled and magnetically adsorb said pile-fixing clamp (63) under the control of said control platform (4), respectively; in the case that said electromagnetic group (6301) has not magnetically adsorbed said pile-fixing clamp (63), said pile-fixing clamp (63) is embedded in said tooth-shaped grooves (2101) of its rail under the action of gravity, in the case that said electromagnetic group (6301) has magnetically adsorbed said pile-fixing clamp (63), said pile-fixing clamp (63) leaves said tooth-shaped grooves (2101).
4. The movable water-permeable pile spur dike according to claim 3, wherein said pile-fixing clamp (63) comprises 2 U-shaped bent iron sheets (6302), the two ends of each U-shaped bent iron sheet (6302) are respectively sleeved on said connecting rod (6201), and can rotate around said connecting rod (6201), in the case that said electromagnetic group (6301) has not magnetically adsorbed said pile-fixing clamp (63), said two U-shaped bent iron sheets (6302), under the action of gravity, respectively, are embedded in said tooth-shaped grooves (2101) of their rails in the opposite direction.
5. The movable water-permeable pile spur dike according to claim 4, wherein the sides of the two straight ends of each U-shaped bent iron sheet (6302) are fan-shaped.
6. The movable water-permeable pile spur dike according to claim 4, wherein said 2 U-shaped bent iron sheets (6302) are connected with each other through a telescopic chain net, said telescopic chain net (6303) is made from elastic wear-resistant material, in the case that said electromagnetic group (6301) has magnetically adsorbed said 2 U-shaped bent iron sheets (6302), said telescopic chain net (6303) shrinks, in the case that said electromagnetic group (6301) has not magnetically adsorbed said 2 U-shaped bent iron sheets (6302), said telescopic chain net (6303) spreads out and covers the surface of said pile roller (61) after its both ends being stretched.
7. The movable water-permeable pile spur dike according to claim 1, wherein said fixed rail (2) is an irregular curved rail, or a broken-line rail formed by splicing multiple segments of straight sub-rails.
8. The movable water-permeable pile spur dike according to claim 1, wherein the lower surface of said fixed rail (2) is provided with one or more than one four-sided hollowed-out pyramid (22) sinking in the river bed, the quadrilateral bottom surface of said four-sided hollowed-out pyramid (22) is embedded in the lower surface of said fixed rail (2), and has a pyramided outer frame formed by metal wires, each hollowed out surface also has a plurality of metal wires wound across its edges, said plurality of four-sided hollowed-out pyramids (22) are arranged along such three straight lines, as the edges of the corresponding fixed rail and the central axis of the long end, and the four-sided hollowed-out pyramids along the two adjacent straight lines are alternated with each other.
9. The movable water-permeable pile spur dike according to claim 1, wherein one side of the downstream face of said fixed rail (2) is provided with a groove (2201) whose inside is provided with a movable rail groove (2202), one end connecting each movable rail (3) to said fixed rail (2) is provided with a moving slider (33), and the bottom of one end away from said fixed rail is provided with a movable rail roller (31), which is inlaid into said movable rail groove (2202) inside said groove (2201), said movable rail roller (31) is connected with said control platform (4) in a communication mode, and can roll along the matched convex single rail (32) fixed on the river bed under the control of said control platform, thereby driving said moving slider (33) to slide, so as to adjust the position of the corresponding movable rail (3).
10. An operation method of the movable water-permeable pile spur dike according to claim 1, comprising the following steps: (S1) performing statistical analysis based on each interannual or annual data results of rivers, setting the water permeability range of said movable water-permeable pile spur dike and the initial position of said plurality of movable water-permeable piles (1) and said plurality of movable rails (3), arranging said control platform (4) according to the initial position, and controlling and adjusting said plurality of movable water-permeable piles (1) and said plurality of movable rails (3) to form said movable water-permeable pile spur dike in its initial state; (S2) each flow meter (12) monitoring the flow velocity of water flow that comprises longitudinal flow velocity u.sub.x and lateral flow velocity u.sub.y, at its monitoring point of the spur dike in real time; of each flow meter, a sampling interval period being denoted by t, a monitoring period being denoted by T, an average longitudinal flow velocity value within said monitoring period T being denoted by U.sub.x, and an average transverse flow velocity value being denoted by as U.sub.y; each flow meter (12) sending U.sub.x and U.sub.y to said control platform (4) as monitoring data; each of said pressure sensors (11) monitoring the pressure borne by it that comprises hydrostatic pressure P.sub.1 and hydrodynamic pressure P.sub.2, at its monitoring point of the spur dike in real time; of each pressure sensor, a sampling interval period also being denoted by t, a monitoring period also being denoted by T, an average value of the sum of the hydrostatic pressure and the hydrodynamic pressure within said monitoring period T being denoted by P; each of said pressure sensors (11) sending P to said control platform (4) as monitoring data; (S3) said control platform (4) calculating the real-time water permeability of said movable water-permeable spur dike based on the real-time monitoring data from each pressure sensor (11) and each flow meter (12) according to Formula (1):
11. The movable water-permeable pile spur dike according to claim 2, wherein the upper surfaces of said fixed rail (2) and said plurality of movable rail (3) are provided with two or more than two pile-sliding grooves (21) arranged in parallel, two sides of each pile-sliding groove (21) are provided with tooth-shaped grooves (2101); the bottom of each water-movable permeable pile (1) is provided with two or more than two rows of pile roller groups, each of which corresponds to one pile-sliding groove (21), and each of which comprises one or more than one pile roller unit, each pile roller unit comprises the connector, the pile roller (61) and the electromagnetic group (6301), of said connector, the top is embedded inside said mobile water-permeable pile (1), the middle part is a hollow connecting block (6203), and the two ends of the bottom extend downwards to form connecting pieces (6202), both of which are connected by a connecting rod (6201), said connecting rod (6201) passes through the center of said pile roller (61), a pile-fixing clamp (63) is sleeved on said connecting rod (6201), said electromagnetic group (6301) is arranged in the hollow connecting block (6203) of said connector, said pile roller (61) and said electromagnetic group (6301) are connected with said control platform (4) in the communication mode, so as to be rolled and magnetically adsorb said pile-fixing clamp (63) under the control of said control platform (4), respectively; in the case that said electromagnetic group (6301) has not magnetically adsorbed said pile-fixing clamp (63), said pile-fixing clamp (63) is embedded in said tooth-shaped grooves (2101) of its rail under the action of gravity, in the case that said electromagnetic group (6301) has magnetically adsorbed said pile-fixing clamp (63), said pile-fixing clamp (63) leaves said tooth-shaped grooves (2101).
12. The method of claim 10, wherein each movable water-permeable pile (1) comprises the hollow cylinder, of said hollow cylinder, the upstream face is provided with the plurality of upstream face permeable holes (14) whose diameters increase from top to bottom, and the downstream face is provided with the plurality of downstream face permeable holes (15) whose diameters decrease from top to bottom, each upstream face permeable hole (14) and each downstream face permeable hole (15) penetrate through said water-permeable pile to its hollow, and said upstream face permeable holes (14) and said downstream face permeable holes (15) are completely alternately arranged in the vertical direction.
13. The method of claim 10 wherein the upper surfaces of said fixed rail (2) and said plurality of movable rail (3) are provided with two or more than two pile-sliding grooves (21) arranged in parallel, two sides of each pile-sliding groove (21) are provided with tooth-shaped grooves (2101); the bottom of each water-movable permeable pile (1) is provided with two or more than two rows of pile roller groups, each of which corresponds to one pile-sliding groove (21), and each of which comprises one or more than one pile roller unit, each pile roller unit comprises the connector, the pile roller (61) and the electromagnetic group (6301), of said connector, the top is embedded inside said mobile water-permeable pile (1), the middle part is a hollow connecting block (6203), and the two ends of the bottom extend downwards to form connecting pieces (6202), both of which are connected by a connecting rod (6201), said connecting rod (6201) passes through the center of said pile roller (61), a pile-fixing clamp (63) is sleeved on said connecting rod (6201), said electromagnetic group (6301) is arranged in the hollow connecting block (6203) of said connector, said pile roller (61) and said electromagnetic group (6301) are connected with said control platform (4) in a communication mode, so as to be rolled and magnetically adsorb said pile-fixing clamp (63) under the control of said control platform (4), respectively; in the case that said electromagnetic group (6301) has not magnetically adsorbed said pile-fixing clamp (63), said pile-fixing clamp (63) is embedded in said tooth-shaped grooves (2101) of its rail under the action of gravity, in the case that said electromagnetic group (6301) has magnetically adsorbed said pile-fixing clamp (63), said pile-fixing clamp (63) leaves said tooth-shaped grooves (2101).
14. The method of claim 13 wherein said pile-fixing clamp (63) comprises 2 U-shaped bent iron sheets (6302), the two ends of each U-shaped bent iron sheet (6302) are respectively sleeved on said connecting rod (6201), and can rotate around said connecting rod (6201), in the case that said electromagnetic group (6301) has not magnetically adsorbed said pile-fixing clamp (63), said two U-shaped bent iron sheets (6302), under the action of gravity, respectively, are embedded in said tooth-shaped grooves (2101) of their rails in the opposite direction.
15. The method of claim 14 wherein the sides of the two straight ends of each U-shaped bent iron sheet (6302) are fan-shaped.
16. The method of claim 14 wherein said 2 U-shaped bent iron sheets (6302) are connected with each other through a telescopic chain net, said telescopic chain net (6303) is made from elastic wear-resistant material, in the case that said electromagnetic group (6301) has magnetically adsorbed said 2 U-shaped bent iron sheets (6302), said telescopic chain net (6303) shrinks, in the case that said electromagnetic group (6301) has not magnetically adsorbed said 2 U-shaped bent iron sheets (6302), said telescopic chain net (6303) spreads out and covers the surface of said pile roller (61) after its both ends being stretched.
17. The method of claim 10 wherein said fixed rail (2) is the irregular curved rail, or the broken-line rail formed by splicing multiple segments of straight sub-rails.
18. The method of claim 10, wherein the lower surface of said fixed rail (2) is provided with one or more than one four-sided hollowed-out pyramid (22) sinking in the river bed, the quadrilateral bottom surface of said four-sided hollowed-out pyramid (22) is embedded in the lower surface of said fixed rail (2), and has a pyramided outer frame formed by metal wires, each hollowed out surface also has a plurality of metal wires wound across its edges, said plurality of four-sided hollowed-out pyramids (22) are arranged along such three straight lines, as the edges of the corresponding fixed rail and the central axis of the long end, and the four-sided hollowed-out pyramids along the two adjacent straight lines are alternated with each other.
19. The method of claim 10, wherein one side of the downstream face of said fixed rail (2) is provided with the groove (2201) whose inside is provided with the movable rail groove (2202), one end connecting each movable rail (3) to said fixed rail (2) is provided with the moving slider (33), and the bottom of one end away from said fixed rail is provided with the movable rail roller (31), which is inlaid into said movable rail groove (2202) inside said groove (2201), said movable rail roller (31) is connected with said control platform (4) in a communication mode, and can roll along the matched convex single rail (32) fixed on the river bed under the control of said control platform, thereby driving said moving slider (33) to slide, so as to adjust the position of the corresponding movable rail (3).
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0034]
[0035]
[0036]
[0037]
[0038]
[0039]
[0040]
[0041]
[0042]
[0043]
DETAILED DESCRIPTION OF SOME EMBODIMENTS
[0044] We shall further describe the present disclosure as follows in combination with the drawings and specific examples, but the protection scope of the present disclosure is not limited to the enumerated examples.
[0045] As shown in
[0046] Each movable water-permeable pile 1 includes a hollow cylinder, that is a cylindrical concrete pile whose interior is hollowed out. Each movable water-permeable pile 1 has the arc-shaped upstream face with 3 permeable holes whose diameters increase from top to bottom on its center line, as well as the arc-shaped downstream face with 3 permeable holes whose diameters decrease from top to bottom on its center line, and the permeable holes on each face may be set as a combination of permeable holes with multi-diameters of 50 cm, 20 cm, and 10 cm. The permeable holes on both faces of the water-permeable pile penetrate through the water-permeable pile to its hollow, and the permeable holes on both face are completely alternately arranged in the vertical direction. In this way, the water flow passes through the permeable holes of each pile, reducing the flow around the spur dike head and influencing 3D flow field distribution rule of the water flow at the spur dike head and near the dike body, with an effective decrease in the partial maximum flow velocity of the dike head at the axis of the spur dike, which reduces scouring the spur dike head and the hollowing out the dike body foundation with benefit to stably arrange the dike body, and also reduces affecting on the river ecological environment owing to the built spur dike, alleviating the partition between aquatic organisms and bank slopes to a certain extent.
[0047] In order to realize the movement of the movable water-permeable pile 1 along the fixed rail 2 and the movable rails 3, the upper surfaces of the fixed rail 2 and each movable rail 3 are provided with a pile-sliding groove 21, and the pile-sliding groove 21 is respectively arranged on the upper surface of the fixed rail 2 or the movable rail 3 along two parallel lines, and two sides of the pile-sliding groove 21 are provided with symmetrical tooth-shaped grooves 2101. The bottom of each water-movable permeable pile 1 is provided with two rows of pile roller groups, each of which corresponds to one pile-sliding groove 21, and each of which includes two pile roller units. Each pile roller unit includes a connector, a pile roller 61 and an electromagnetic group 6301. The pile roller 61 is also provided with a pile-fixing clamp 63. Specifically, of the connector, the top is embedded on both sides of the bottom of the corresponding mobile water-permeable pile 1, the middle part is a hollow connecting block 6203 used to arrange a driver and the electromagnetic group 6301, and the two ends of the bottom extend downwards to form connecting pieces 6202, both of which are connected by a connecting rod 6201. The connecting rod 6201 passes through the center of the pile roller 61, as shown in
[0048] Preferably, reinforced concrete can be poured to form the main body of the fixed rail 2, of which sinks in the river bed, and the lower surface of which is provided with a plurality of four-sided hollowed-out pyramids 22 sinking in the river bed. Each four-sided hollowed-out pyramid 22 is positioned with its pyramid tip downwards, and its quadrilateral bottom surface is embedded in the lower surface of the fixed rail 2, connected with the reinforced concrete inside it, and has a pyramided outer frame formed by metal wires. Each hollowed out surface also has a plurality of metal wires wound across its edges. The above-mentioned plurality of four-sided hollowed-out pyramids 22 are arranged along such three straight lines, as the edges of the corresponding fixed rail and the central axis of the long end, and the four-sided hollowed-out pyramids along the two adjacent straight lines are alternated with each other, so this structure can increase the contact area with the river bed and have an advantage to stabilize the spur dike body.
[0049] The height of the downstream face of the fixed rail 2 is horizontally cut inwards to form a groove 2201 whose vertical side is provided with a movable rail groove 2202. One end connecting each movable rail 3 to the fixed rail 2 is provided with a moving slider 33, and the bottom of one end away from the fixed rail is provided with a movable rail roller 31, which is inlaid into the movable rail groove 2202 inside the groove 2201 and can move in the movable rail groove 2202 inside the groove 2201. The movable rail roller 31 is connected with the control platform 4 in a communication mode, and can roll along the matched convex single rail 32 fixed on the river bed under the control of the control platform, thereby driving the moving slider 33 to slide smoothly in the vertical water flow direction, so as to adjust the position of the corresponding movable rail 3. The convex single rail 32 is parallel to the fixed rail and used to move the movable rail, so that the sediments carried by the water flow will not hinder the movable rail roller 31 from rolling.
[0050] In this example, the fixed rail 2 is an integrally-formed linear rail. It should be noted that, in other examples, the fixed rail 2 can also be an irregular broken-line rail, a curved rail, or a linear rail, a broken-line rail or a curved rail formed by splicing multiple segments of straight sub-rails, as shown in
[0051] In this example, the control platform 4 is arranged on the river bank, including a signal transmission device, a control system and some electromechanical equipment. The signal transmission device receives the data signals coming from the pressure sensors and the flow meters, and then transmits them to the control system, which will analyze and process the received data signal of the river changes and the situation of the spur dike partially bearing pressure to make an appropriate adjustment plan for the water-permeable pile spur dike, and then the control platform sends instructions to the electromechanical equipment, thereby moving the movable water-permeable piles to make an appropriate adjustment step, so as to change the water permeability of the spur dike body and the spur dike shape, replying the changes in the river and the spur dike. In other examples, the control platform 4 can also be arranged at other positions, and contain some electromechanical equipment that can also be installed at appropriate positions on the spur dike after waterproofing, for example, near the movable rail roller 31 or the pile roller 61.
[0052] The spur dike is arranged in the river, so that the water flow is respectively divided by ways of flowing around the dike head, passing through the water-permeable piles, and penetrating through the free flow area between the permeable piles. The permeable piles of the spur dike can move freely on each rail.
[0053] In the dry season of a river, in the case that the pressure and flow values of the spur dike are within a corresponding preset threshold value, the required water permeability range is smaller than that in the flood season, providing a certainty to decrease the distance L.sub.i between the permeable piles and the water permeability a of the spur dike, improve a water-blocking effect and bank up the water level, and an advantage to maintain the navigable water depth of the river. In the case that the water pressure partially borne by the spur dike is gradually more than the threshold value H, the spur dike's pressure P increase so as to seriously scour the partial permeable pile foundation, having a disadvantage to stabilize the dam itself. By simulation-optimization calculation, we know that the water permeability a of the spur dike needs to be increased. When both the pressure and flow velocity of the spur dike are less than the preset threshold value in the control system, the control platform 4 simulates the optimal water permeability of the spur dike to increase the distance between the partial fixed rail piles through the signal transmission device, thereby enhancing the flow capacity of dike body and reducing the partial pressure borne by the spur dike. At the same time, the water-permeable piles on the partial movable rail is reduced in the distance to the fixed rail, with the distance increased between the parallel movable rails, thereby enhancing the overall compressive strength of the spur dike and ensuring the stability and the effective operation effect of the spur dike.
[0054] In the flood season of the river, according to the measured hydrologic data in the early flood season of previous years, an optimized plan had been deduced in advance for arrangement, providing a certainty to previously increase the number of the water-permeable piles on the rail. With the approach of the river flood season, the river flow increases, in the case that the spur dike's pressure or the flow velocity exceeds the corresponding preset threshold value, the control platform receives a current warning data signal, and simulates and predicts an optimal plan to adjust the dike body, that is, the spacing L.sub.i between the piles in the middle section of the spur dike body is increased, and the movable rails are moved to the horizontal centerline between the adjacent piles, appearing in an alternate arrangement. The piles on the movable rail move away from the fixed rail to enhance the flow capacity of the spur dike body, alleviate scouring the dike head, and stabilize the spur dike body, so that the water pressure and the flow velocity borne by the spur dike body are gradually less than the preset threshold value.
[0055] Therefore, the present disclosure also provides an operation method of the movable water-permeable pile spur dike, comprising the following steps: [0056] (S1) performing statistical analysis based on each interannual or annual data results of rivers, setting the water permeability range of the movable water-permeable pile spur dike and the initial position of the plurality of movable water-permeable piles 1 and the plurality of movable rails 3, arranging the control platform 4 according to the initial position, and controlling and adjusting the plurality of movable water-permeable piles and the plurality of movable rails to form the movable water-permeable pile spur dike in its initial state; [0057] (S2) each flow meter 12 monitoring the flow velocity of water flow that includes longitudinal flow velocity u.sub.x and lateral flow velocity u.sub.y, at its monitoring point of the spur dike in real time; of each flow meter, a sampling interval period being denoted by t, a monitoring period being denoted by T, an average longitudinal flow velocity value within the monitoring period T being denoted by U.sub.x, and an average transverse flow velocity value being denoted by as U.sub.y; each flow meter 12 sending U.sub.x and U.sub.y to the control platform 4 as monitoring data; each of the pressure sensors 11 monitoring the pressure borne by it that includes hydrostatic pressure P.sub.1 and hydrodynamic pressure P.sub.2, at its monitoring point of the spur dike in real time; of each pressure sensor, a sampling interval period also being denoted by t, a monitoring period also being denoted by T, an average value of the sum of the hydrostatic pressure and the hydrodynamic pressure within the monitoring period T being denoted by P; each of the pressure sensors 11 sending P to the control platform 4 as monitoring data; [0058] (S3) the control platform 4 calculating the real-time water permeability of the movable water-permeable spur dike based on the real-time monitoring data from each pressure sensor 11 and each flow meter 12 according to Formula:
[0064] The movable water-permeable spur dike in the above-mentioned examples can also be applied to put together a spur dike group, providing a certainty to adjust the water permeability of each permeable spur dike and the shape of the spur dikes in the spur dike group respectively, so that the spur dike group can enhance a water blocking effect, decompose the impact force of the water flow on the spur dike body stage by stage and slow down the flow velocity of the water flow, so as to ensure that the trajectory bucket effect of the spur dike is good and the spur dike group is stable.
[0065] As shown in
[0066] The above examples do not impose limitations on the present disclosure, and the present disclosure is not limited to the above examples. Any changes, modifications, additions or substitutions within the scope of the present disclosure made by a person skilled in the art also fall within the protection scope of the present disclosure.