STEEL PLATE BUILT-UP BEAM FOR STEEL-CONCRETE COMPOSITE BEAM
20230037589 · 2023-02-09
Assignee
Inventors
Cpc classification
E04C5/0604
FIXED CONSTRUCTIONS
E04C3/07
FIXED CONSTRUCTIONS
International classification
Abstract
A steel plate built-up beam for a steel-concrete composite beam, which is for the purpose of forming a steel-concrete composite beam by filing the inside thereof with concrete, includes: a pair of web plates spaced apart from each other; a lower flange provided on the lower portions of the web plates so as to connect the lower portions of the pair of web plates; and upper angles provided on the upper portions of the web plates, respectively, such that one leg of the upper angle is coupled to side surfaces of the web plates, and other leg of the upper angle is formed to bend in directions perpendicular to the web plates.
Claims
1. A steel plate built-up beam for forming a steel-concrete composite beam by being filled with concrete (c), the steel plate built-up beam comprising: a pair of web plates (21) spaced apart from each other; a lower flange (22) provided at a lower portion of the web plate (21) to connect lower portions of a pair of web plates (21); and upper angles (23) provided on upper portions of the web plates (21), wherein one leg (231) of the upper angle (23) is coupled to the side surface of each web plate (21) and the other leg (232) of the upper angle (23) is bent at right angles to the web plate (21).
2. The steel plate built-up beam according to claim 1, wherein one leg of the upper angle is coupled to a web plate by coupling bolts.
3. The steel plate built-up beam according to claim 2, wherein at least one of the coupling bolts is a through bolt passing through both web plates.
4. The steel plate built-up beam according to claim 1, wherein the one leg of the upper angle is coupled to an inner surface of a web plate.
5. The steel plate built-up beam according to claim 1, wherein the other leg of the upper angle is disposed at the top of the web plate.
Description
DESCRIPTION OF DRAWINGS
[0018]
[0019]
[0020]
[0021]
[0022]
[0023]
[0024]
[0025]
[0026]
BEST MODE
[0027] In order to achieve the above object, the present invention relates to a steel plate built-up beam for forming a steel-concrete composite beam by being filled with concrete. The steel-concrete composite beam according to an embodiment of the present invention includes: a pair of web plates spaced apart from each other; a lower flange provided at a lower portion of the web plate to connect lower portions of a pair of web plates; and upper angles provided on upper portions of the web plates, wherein one leg of the upper angle is coupled to the side surface of each web plate and the other leg of the upper angle is bent at right angles to the web plate.
MODE FOR INVENTION
[0028] Hereinafter, the present invention will be described in detail with reference to the accompanying drawings and the preferred embodiment.
[0029]
[0030] Moreover,
[0031] Furthermore,
[0032] As illustrated in
[0033] The present invention is to provide a steel plate built-up beam for a steel-concrete composite beam, which has excellent structural performance while minimizing a welding process when a steel plate built-up beam is manufactured for forming a steel-concrete composite beam by filling the inside with concrete C.
[0034] The a steel plate built-up beam 2 for a steel-concrete composite beam according to the present invention includes web plates 21, a lower flange 22, and upper angles 23.
[0035] A pair of the web plates 21 are arranged at the right and left sides to be spaced apart from each other.
[0036] The web plates 21 serve as struts of the existing RC beam so as to support shearing force acting the beams.
[0037] The lower flange 22 is disposed at the lower portions of the web plates 21 to connect the lower portions of a pair of the web plates 21.
[0038] The lower flange 22 serves as a lower root of the RC beam.
[0039] The lower flange 22 may be bent to be extended integrally from the web plates 21.
[0040] Additionally, as illustrated in
[0041] As illustrated in
[0042] Stud bolts ST for integration with concrete C may be coupled on the upper surface of the lower flange 22 (see
[0043] The upper angle 23 is provided on an upper portion of each web plate 21.
[0044] The upper angle 23 serves as an upper flange, and is coupled to an upper side surface of the web plate 21.
[0045] One leg 231 of the upper angle 23 is coupled to a side surface of the web plate 21, and the other leg 232 is bent at right angles to the web plate 21.
[0046] Unlike the conventional TSC beam supporting a tensile force acting on the upper portion of the beam by the bending moment in a negative moment section just by the plate-shaped upper flange, the present invention supports a tensile force by the upper angle 23 which is a section steel material.
[0047] Therefore, since the entire cross section of one leg 231 and the other side leg 232 of the upper angle 23 serves as an upper flange, based on the same structural performance, the other leg 232 may be narrower than the upper flange of the conventional TSC beam. That is, since a space between the both upper angles 23 can be secured as much as possible, it is easy to pour concrete C in the space.
[0048] The length of one leg 231 of the upper angle 23 is enough for coupling with the web plate 21. In addition, since the other leg 232 of the upper angle 23 has a greater effect on the cross-sectional coefficient, it is preferable that the upper angle 23 is a scalene angle of which the other leg 232 is longer than the one leg 231.
[0049] The other leg 232 of the upper angle 23 may be provided to face the outside or the inside of the web plate 21.
[0050] In particular, in a case in which the steel plate built-up beam 2 of the present invention is coupled to the PSRC column 3 in which a -shaped section steel 31 is disposed, when the other leg 232 of the upper angle 23 is disposed to face the inside of the web plate 21, it is easy to directly attach the upper angle 23 to the
-shaped section steel 31 of the PSRC column 3.
[0051] That is, as illustrated in -shaped section steel 31 of the PSRC column 3 to be fixed by a bolt or the like. At this time, the upper angle 23 is configured to pass through the PSRC column 3 to deliver the upper negative moment of the beam.
[0052] The upper angle 23 is excellent at cross-sectional efficiency since being set independently in thickness from the web plate 21.
[0053] Meanwhile, a mold such as a deck plate 10 for pouring slab concrete may be mounted on the upper surface of the other leg 232 of the upper angle 23 (
[0054] Moreover, stud bolts or the like may be coupled to the upper surface of the other leg 232 of the upper angle 23 to be integrated with the slab concrete.
[0055] As illustrated in
[0056] In this case, the steel plate built-up beam according to the present invention can reduce the manufacturing period of time by minimizing the welding work, and prevent deformation of members due to welding heat.
[0057] The coupling bolts 24 or nuts 25 fastened to the coupling bolts 24 are embedded in the concrete C poured in the steel plate built-up beam 2 to serve as a shear connector, thereby integrating the steel plate built-up beam 2 and the concrete C.
[0058] A plurality of through-holes for penetration of the coupling bolts 24 can be formed at positions corresponding to each other on the web plate 21 and the one leg 231 of the upper angle 23.
[0059] As illustrated in
[0060] The coupling bolts 24 for fixing the upper angle 23 to the web plate 21 are through bolts 24′, which are long bolts, to fix both upper angles 23 at the same time.
[0061] In addition, the through bolts 24′ prevent the steel plate built-up beam 2 from being widened with respect to the concrete side pressure. Therefore, foam ties are not necessary.
[0062] The through bolts 24′ are mounted to pass through all of the left and right web plates 21, and the inner and outer sides of the one leg 231 of each upper angle 23 and the web plate 21 are fastened by the nuts 25.
[0063] As illustrated in
[0064] In this case, since the one leg 231 of the upper angle 23 is not exposed to the outside of the web plate 21, it is easy to finish the exterior.
[0065] Furthermore, when the one leg 231 of the upper angle 23 is coupled to the outer surface of the web plate 21, concrete paste leaks between the web plate 21 and the one leg 231 of the upper angle 23 so that the web plate 21 may be contaminated. Accordingly, the one leg 231 of the upper angle 23 is coupled to the inner side of the web plate 21 so that the joining surface of these members is positioned inside the steel plate built-up beam 2.
[0066] Accordingly, when the other leg 232 of the upper angle 23 is bent inward or outward from the web plate 21, it is possible to prevent the concrete paste from leaking to the outer surface of the web plate 21 through the paste bonding surface.
[0067] As illustrated in
[0068] When the top of the web plate 21 is level with the upper angle 23, the web plate 21 and the upper angle 23 can stably support the deck plate 10 at the same time.
[0069] In the positive moment section, a large compressive force is generated on the upper portion of the cross section. Since the one leg 231 of the upper angle 23 gets in close contact with the side surface of the web plate 21 to support the web plate 21, thereby preventing plate buckling of the upper end of the web plate 21.
INDUSTRIAL APPLICABILITY
[0070] The steel plate built-up beam for a steel-concrete composite beam according to the present invention includes the upper angles in each of which one leg is coupled to the side surface of each of a pair of web plates spaced apart from each other, there by minimizing welding during manufacturing and freely setting the thickness of the upper angle so as to maximize sectional efficiency. In addition, since the space between both upper angles is maximally secured, it is easy to pour concrete therein.