Method for erecting a wind turbine and lifting beam for mounting a rotor blade of a wind turbine
10823149 ยท 2020-11-03
Assignee
Inventors
Cpc classification
F03D1/0658
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
B66C23/72
PERFORMING OPERATIONS; TRANSPORTING
B66C1/108
PERFORMING OPERATIONS; TRANSPORTING
F05B2230/61
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
B66C13/06
PERFORMING OPERATIONS; TRANSPORTING
F03D13/10
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
Y02E10/72
GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
International classification
F03D13/10
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
F03D1/06
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
B66C23/72
PERFORMING OPERATIONS; TRANSPORTING
B66C13/06
PERFORMING OPERATIONS; TRANSPORTING
Abstract
A method of erecting a wind power installation which has an aerodynamic rotor having rotor blade connections. A lifting beam having a ballast unit is fixed to a crane hook of a crane. A rotor blade is fixed to a second crane hook at an underside of the ballast unit by means of lifting cables. The lifting beam and the rotor blade are lifted by the crane for mounting the rotor blade at one of the rotor blade connections.
Claims
1. A method of erecting a wind power installation having an aerodynamic rotor blade having a plurality of rotor blade connections, the method comprising: selecting at least one ballast weight so that a predetermined ratio in meters squared per ton between a surface area of the rotor blade and a sum of both the at least one ballast weight and a weight of the rotor blade is equal to or less than 1; fixing the at least one ballast weight to a lifting beam; fixing the lifting beam with the at least one ballast weight to a crane hook of a crane; fixing a rotor blade by lifting cables to a second crane hook at an underside of the at least one ballast weight; and lifting the lifting beam with the at least one ballast weight and the rotor blade by the crane for mounting the rotor blade at one of the plurality of rotor blade connections.
2. The method according to claim 1, comprising: prior to lifting the beam with the at least one ballast weight and the rotor blade by the crane, fixing a rotor blade root of the rotor blade to a hook of a winch unit; and wherein lifting the rotor blade comprises lifting the rotor blade by the winch unit and the crane.
Description
BRIEF DESCRIPTION OF THE SEVERAL VIEWS OF THE DRAWINGS
(1) Advantages and embodiments by way of example of the invention are described in greater detail hereinafter with reference to the drawing.
(2)
(3)
(4)
(5)
DETAILED DESCRIPTION
(6)
(7)
(8) The lifting beam having a ballast unit 300 is used to increase the weight to be lifted by the crane 400. The invention is based on the notion that, by increasing the weight to be lifted by the crane 400, the ratio between the area of the component to be mounted (here a rotor blade) to the weight of the component is reduced, by virtue of the weight to be lifted being increased by the ballast weight of the ballast unit 300. It is possible in that way to ensure that the rotor blade can be mounted even at higher wind speeds.
(9)
(10) The ballast weights 330 can be fixed within the frame.
(11) According to an aspect of the present invention a parking means or a parking unit 322 can be provided, by means of which the lifting beam can be set down on the ground even when the second crane hook 340 is mounted.
(12) Calculation of the permissible wind speed for lifting a rotor blade is explained hereinafter:
A.sub.W=A.sub.p*c.sub.W
A.sub.W=135 m.sup.2.Math.1.1
A.sub.W=148.5 m.sup.2
[Formula for Calculating the Wind Engagement Area]
(13)
[Formula for Calculating the Permissible Wind Speed]
(14)
(Maximum Permissible Wind Speed for the Hub of a Rotor Blade)
(15) Calculation of the permissible wind speed for lifting a rotor blade and increasing the mass by using an additional lifting beam with ballast weights of the mounting crane is carried out as follows:
A.sub.W=148.5 m.sup.2
(Assuming the Wind Engagement Area does not Change Although there is a Distribution Between Auxiliary Winch and Mounting Crane)
(16)
(Assuming the Crane has a Lift Capacity of 80 t which is Also Needed to Mount the Pod Components)
(17)
(Maximum Permissible Wind Speed for Lifting a Rotor Blade by Using Added Ballast)
(18)
(19) The calculation of the permissible wind speed for lifting a rotor blade and increasing the mass by using an additional lifting beam having ballast weights of the mounting crane, and taking account of the distribution of load between an ancillary device and the mounting crane, is effected as follows:
A.sub.W1=135 m.sup.2.Math.1.1
A.sub.W=99 m.sup.2
[Assuming that of the Area Act on the Crane]
(20)
(Area of the Lifting Beam with Additional Ballast)
(21) According to the invention the permissible maximum speed can be considerably increased by means of the lifting beam when mounting the rotor blades. The maximum permissible wind speed can be increased from 4.4 m.sup.2 to 7.2 m.sup.2 by using the lifting beam with the ballast unit. If the winch unit is used in accordance with an aspect of the present invention the permissible wind speed can be increased to 8.5 m/s. That is particularly advantageous because in that way the rotor blade can be mounted even at relatively high wind speeds.