Method for Installing a Subsea Structure
20200298944 ยท 2020-09-24
Assignee
Inventors
Cpc classification
E21B43/017
FIXED CONSTRUCTIONS
F17C2270/0126
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
B65D90/20
PERFORMING OPERATIONS; TRANSPORTING
F17C13/082
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
E02B2017/0039
FIXED CONSTRUCTIONS
E02D29/06
FIXED CONSTRUCTIONS
E02B17/02
FIXED CONSTRUCTIONS
B63B21/29
PERFORMING OPERATIONS; TRANSPORTING
B63B77/00
PERFORMING OPERATIONS; TRANSPORTING
International classification
B63B77/00
PERFORMING OPERATIONS; TRANSPORTING
F17C13/08
MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
B65D90/20
PERFORMING OPERATIONS; TRANSPORTING
E02B17/02
FIXED CONSTRUCTIONS
Abstract
A method for installing a subsea structure at a target installation site in an underwater location is disclosed. The method includes connecting at least one mooring line and at least one leading line to the structure, and towing the structure via the leading line from a deployment position to the target installation site, such that the structure moves both vertically and horizontally between the deployment position and the target installation site. The mooring line is anchored, e.g. to an anchoring device on the seabed, and can incorporate a ballast to apply a sinking force to the structure in proportion to the length of unsupported line. The mooring line and the leading line can together stabilise the structure as it descends to the installation site. The non-vertical installation allows accurate structure placement, e.g. in crowded fields, with less sensitivity to tidal or current forces.
Claims
1. A method for installing a subsea structure at a target installation site in an underwater location, the method comprising connecting at least one mooring line to the structure, connecting at least one leading line to the structure, and towing the structure via the leading line from a deployment position spaced laterally away from a target installation site to an installation position above the target installation site, and moving the structure both vertically and horizontally through the water between the deployment and installation positions.
2. A method as claimed in claim 1, the method including anchoring at least one mooring line to at least one anchor point, wherein the length of the at least one mooring line between the anchor point and the structure is substantially equivalent to the distance between the anchor point and the target installation site.
3. A method as claimed in claim 1, including floating the structure on the surface of the water at the deployment position, and adjusting at least one of the buoyancy and ballast acting on the structure to facilitate sinking of the structure through the water, while controlling the orientation of the structure in the water during sinking of the structure by varying tension in at least one of the at least one mooring line and the at least one leading line.
4. A method as claimed in claim 1, the method including connecting the at least one leading line in a catenary configuration between the structure and a towing vessel, and paying out said leading line as the towing vessel tows the structure laterally towards the target installation site.
5. A method as claimed in claim 1, the method including towing the structure by the at least one leading line in a lateral direction away from the at least one anchored mooring line, towards the target installation site.
6. A method as claimed in claim 1, the method including connecting the at least one leading line and the at least one mooring line to the structure at spaced apart locations.
7. A method as claimed in claim 6, wherein the connection points of the lines are symmetrically positioned.
8. A method as claimed in claim 6, the method including connecting at least two mooring lines and at least one leading line to the structure at circumferentially spaced apart locations on the structure, wherein the at least one leading line is connected at an opposite side of the structure to the at least two mooring lines, and wherein the at least one leading line connection is opposite to a bisector between the at least two mooring line connections.
9. A method as claimed in claim 8, the method including towing the structure by the at least one leading line in a direction opposite to the bisector between the at least two mooring lines.
10. A method as claimed in claim 6, the method including connecting at least two leading lines to the structure, wherein the leading lines are spaced apart; and wherein the vector sum of the forces applied to the structure by the at least two leading lines has a direction component acting in the opposite direction to the vector sum of the forces applied by the at least two mooring lines.
11. A method as claimed in claim 10, wherein the mooring line is recovered by a separate support vessel and passed to a towing or trailing vessel for connection to the structure.
12. A method as claimed in claim 1, the method including controlling the descent of the structure to the target installation site by adjusting at least one of the tension and the length of the leading line between the structure and the lead towing vessel.
13. A method as claimed in claim 12, the method including applying sufficient tension to the leading line to maintain a horizontal component of movement of the structure during descent, and maintaining tension in the mooring lines to resist changes in the orientation of the structure during the descent.
14. A method as claimed in claim 12, the method including checking the position, heading, and depth of the structure prior to landing of the structure on the seabed in the target installation site.
15. A method as claimed in claim 12, including adjusting ballast and buoyancy on the structure system and adjusting leading line tension during the descent and final landing of the structure on the seabed in the target installation site.
16. (canceled)
17. (canceled)
18. method as claimed in claim 1, including tethering a buoy to the structure after the structure has been installed on the target installation site, wherein the method includes connecting at least one buoy mooring line between the buoy and an anchor point on the seabed before connecting tethers between the buoy and the structure.
19. A method as claimed in claim 18, including paying out leading line from the lead towing vessel once the buoy is in position above the installed structure, and using the paid-out leading line as an additional mooring line for the buoy.
20. A method as claimed in claim 19, the method including connecting an anchoring device to the end of the paid-out leading line prior to its deployment on the seabed, and laying out the paid-out leading line under tension to minimum slack, the mooring lines connected to the buoy acting together to constrain movement of the buoy relative to the installed structure.
21. A method as claimed in claim 18, including spacing the structure away from the seabed and constraining movement of the structure in the spaced position relative to the seabed by the tensioned mooring lines.
22. (canceled)
23. (canceled)
24. (canceled)
25. (canceled)
26. (canceled)
27. (canceled)
28. (canceled)
29. (canceled)
30. (canceled)
31. (canceled)
32. (canceled)
33. A subsea storage tank assembly having at least one storage compartment for storage of production fluids produced from an offshore subsea oil or gas well, the subsea storage tank assembly comprising at least one item of subsea equipment supported on the storage tank assembly and wherein the subsea equipment comprises a structural support frame adapted to resist movement of the subsea equipment relative to the storage tank assembly.
34. (canceled)
35. (canceled)
36. (canceled)
37. (canceled)
38. (canceled)
39. (canceled)
40. (canceled)
41. (canceled)
42. (canceled)
43. (canceled)
44. (canceled)
45. (canceled)
46. (canceled)
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0053] In the accompanying drawings:
[0054]
[0055]
[0056]
[0057]
[0058]
[0059]
[0060]
[0061]
[0062]
[0063]
[0064]
[0065]
[0066]
[0067]
[0068]
[0069]
[0070]
[0071]
[0072]
[0073]
[0074]
[0075]
[0076]
[0077]
[0078]
[0079]
[0080]
[0081]
DETAILED DESCRIPTION
[0082]
[0083] Before installation of the storage tank assembly 1, the installation site is optionally prepared by measuring the horizontal distance from an anchor point of each mooring line 10 on the seabed S, and a target installation site T (see
[0084]
[0085]
[0086] Initially, at the deployment position, with the tank assembly 1 on the surface, and awaiting installation as shown in
[0087] As can be seen in
[0088] The trailing vessels 20 recover the end of each pre-laid mooring line 10 from the seabed S whilst still connected to the storage tank assembly 1 via a trailing tow line 15, and can connect the mooring line 10 either directly to the tank assembly 1, or more commonly can connect the two components indirectly with a mooring line connector shackle. Alternatively a separate support vessel such as an ROV (remotely operated vehicle) may recover the end of the pre-laid mooring lines 10 and pass this across to the trailing vessels 20, or this may be carried out by a diver. The mooring lines 10 can be connected to the tank assembly 1 at connection points on the ballast tanks, or on the storage tank itself via the tow lines 15, which themselves will have been measured to ensure the tank assembly 1 lands on the target installation site T. These connection points can be padeyes, clamps, latches, ball and taper, shackles, or any other means of connection of a mooring line to a subsea structure.
[0089] Once connected to the mooring lines 10 and to the leading line 16, the buoyancy of the tank assembly 1 is gradually decreased when the tank assembly 1 is moved into the deployment position as shown in
[0090] The ballast is added until the tank assembly 1 reaches a greater depth, at which point the tank assembly 1 can continue its controlled descent with the mooring lines 10 and the leading line 16 acting as additional ballast as well as stabilising the tank assembly 1 during descent and landing. The ballast can take the form of seawater, concrete, mud, or another material, or any combination thereof. Alternatively, to reduce the buoyancy of the tank assembly 1, water can be allowed to enter the tank 1t in a controlled manner, while optionally allowing venting of the air inside the tank.
[0091] The mooring lines 10 are flexible, and can incorporate ballast (which can be integral to the mooring lines 10 and/or can be separately attached thereto), and so the mooring lines 10 themselves exert a downward sinking force on the tank assembly 1 acting to sink the tank assembly 1. The downward force exerted by the mooring lines 10 is in proportion to the amount of mooring line 10 that is unsupported between the seabed S and the structure. The mooring line 10 can be a chain, or a rope, or another material suitable for marine mooring applications.
[0092] The leading line 16 and mooring lines 10 are connected to the storage tank assembly 1 at symmetrically spaced apart locations with an angular difference between each tether point, e.g. at diametrically or diagonally opposite locations, so that downward force exerted by the leading line 16 and mooring lines 10 is applied to symmetrically spaced locations on the tank assembly 1, thereby balancing the force and enhancing the stability of the tank assembly 1.
[0093] One example of a controlled descent path of the tank assembly 1 is shown in
[0094]
[0095] Attaching the mooring lines 10 at connection points on the storage tank assembly 1 that are angularly spaced around the tank assembly 1 allows positioning to be controlled in different horizontal directions and can improve control of the heading and position during the descent and landing operation. The angular spacing between the two mooring lines 10 and between at least one of the mooring lines 10 and the leading line 16 is approximately equal, with the angular spacing between adjacent lines approximately 120 degrees. However, for alternate sites with different prevailing subsea conditions, this angular spacing can be adjusted to suit.
[0096] Before sinking of the tank assembly 1 from the deployment position, and after both of the pre-installed mooring lines 10 are connected to the tank assembly 1, the trailing vessels 20 can pay out their tow lines, which can be disconnected from the tank assembly 1, freeing the trailing vessels for other duties. During this time the lead vessel 21 moves forward, adjusting its position as necessary to ensure tension is maintained on the leading line 16 and the mooring lines 10, thus controlling the heading, drift and orientation of the tank assembly 1. In certain cases one or more trailing vessels can remain connected to the tank assembly 1 during deployment of the tank assembly 1 to the target installation site (not shown) in order to further control the descent of the tank assembly 1, by adjustment of the weight of the catenary observed by the tank.
[0097] During de-ballasting of the tank assembly 1, as the tank assembly 1 moves forward with a horizontal component of movement from the deployment position towards the target installation site during later installation steps, the anchored ends 11 of the mooring lines 10 remain fixed in position. As a result, the angular separation of the mooring lines 10 decreases during the movement of the tank assembly 1 to the target installation site and subsequent landing on the target installation site. In this example, by the time the tank assembly 1 has reached the target installation site, the mooring lines and the tow line are peripherally spaced about the tank assembly 1 by equal amounts as is best shown in
[0098]
[0099] The lowering operation may include a number of different methods to reduce the buoyancy of the tank assembly 1, for example, gas-filled compartments of the ballast tanks 1b can be flooded, fluids in the ballast tanks 1b can be replaced by denser fluids, and/or weights can be added to the tank assembly 1 as described above.
[0100] Once the tank assembly 1 is neutrally buoyant and starts sinking, the tension in the mooring lines 10 can reduce slightly and at this stage, the lowering operation can be controlled by the lead vessel 21 adjusting the applied force and length of the leading line 16.
[0101] The tank assembly 1 is towed via the leading line 16 and leading vessel 21 from the deployment position spaced laterally away from the target installation site to an installation position above the target installation site for landing on the installation site. As the mooring lines 10 are connected between the seabed anchors 11 at their far ends remote from the tank and the corners of the ballast tanks 1b, the towing of the tank assembly 1 by the leading vessel 21 causes the tension in the mooring lines to increase and the tank assembly 1 to sink through the water moving both horizontally and vertically in a linear or arcuate path towards the target installation site.
[0102]
[0103] The tension in the mooring lines 10 and the leading line 16 maintains stability of the tank assembly 1 in the water, so that the tank assembly 1 descends in a controlled manner, moving laterally in a horizontal plane as well as vertically through the water column with respect to the target installation site until it is located directly above the target installation site on the seabed S. This method of deployment can allow more accurate placement of the tank assembly 1, especially in crowded fields where existing subsea structures can act as obstacles and inhibit deployment, especially of larger structures. Some examples of the method can be less sensitive to uncontrolled lateral movements of the tank assembly 1 away from the target installation site, resulting from, for example, tide or current forces in the water.
[0104] As the leading vessel 21 tows the storage tank assembly 1 laterally away from the anchored mooring lines 10 and towards the target installation site as it descends, the catenary configuration of the leading line 16 can be adjusted in order to control the amount of ballast applied to the tank assembly 1 by the leading line. This can help to maintain the tank assembly 1 in a generally stable horizontal plane. In other words, as the leading line 16 is tensioned, resulting from the movement of the leading vessel 21 away from the deployment position and the storage tank assembly 1, the leading line 16 is gradually paid out from the tow vessel taking into account speed of the leading tug 21, in order to control the catenary configuration of the leading line 16, and hence exert the correct amount of weight on the tank assembly 1 from the ballast in the leading line 16. The catenary configuration of the leading line 16 can be adjusted during descent of the storage tank assembly 1 to balance the tank assembly 1 during the descent, so that the tank assembly 1 descends in an the desired path (optionally an arcuate path) through the water.
[0105] The paying out of the leading line 16 by the leading vessel 21 as it moves laterally and the corresponding sinking of the tank assembly 1 through the water results in the leading line 16 reaching sufficient length whereby the leading line 16 begins to be deposited on the seabed S. As the tank assembly 1 descends further, and also moves horizontally under the guidance of the leading vessel 21, the mooring lines 10 are also increasingly laid down on the seabed S. As more length of the lines 10,16 is deposited on the seabed S an equilibrium position is achieved wherein the tension in the lines is balanced relative to one another and the angles between the lines are equal at 120 degrees.
[0106] To assist with the controlled descent, ballasting of the tank assembly 1 can be continued, either through for example increasing the ballast in the ballast tanks, or by attaching weights, or by flooding designated compartments within the storage tank. Designated ballast compartments within the storage tank are of finite volume and located so that when ballasting commences, the tank assembly 1 is not destabilised, and does not roll or tip. For example, a ballast compartment may be integrated into the centre of the storage tank, or may form a ring around the base circumference of the storage tank, either from a single compartment or multiple compartments, or the ballast compartments may take some other configuration. Optionally the ballast compartment in the storage tank can be centralised and symmetrical within the tank, so that filling the ballast compartment in the storage tank reduces the buoyancy of the tank assembly 1 but does not affect the trim. Optionally the outer ballast tanks can be filled initially, until the threshold between positive and negative buoyancy is approaching, and thereafter manipulation of the ballast can be achieved by filling and draining the centralised tank to cause the tank assembly 1 to rise and ascend without affecting the trim of the tank assembly 1 (e.g. the angle of the tank assembly 1 in the water with respect to the horizontal axis).
[0107] The ballast compartments may have a valve that is accessible either to an ROV or to a diver. The ROV may be docked onto the tank, or it may be operated via a downline from an ROV control vessel (22,
[0108] Prior to landing the structure on the seabed S in the target installation site, and/or during the descent, the position, heading, and depth may be checked by optional transponder devices fitted to the structure, or by ROV, or another suitable method. The ROV may be docked to the tank for measurement of, for example, the angle of the storage tank assembly 1 during descent and local control or operation of flooding valves. Once the tank assembly 1 is directly above the target installation site, optionally within 5-10 m of vertical separation between the tank assembly 1 and the target installation site, the final lowering step can be performed using a combination of adjustment of ballast and buoyancy on the ballast tanks 1b and the storage tank 1t, and leading line 16 tension.
[0109] As shown in
[0110] The tank assembly 1 can remain anchored in position by the mooring lines as well as by any ballast contained in the tank assembly 1. Alternatively or additionally, as seen in
[0111] While the pile sleeve 30 and the pile 31 are connected by the sling 35 or other connector, the pile 31 cannot be deployed from the pile sleeve. Once the tank assembly 1 is landed on the target installation site, the connection can be broken, for example using an ROV to cut the sacrificial sling 35, or change the configuration of the latch or other retention device, and the pile 31 is then released from the pile sleeve and engages the seabed S ready to be driven into the seabed S in a conventional manner, with the desired alignment of the pile relative to the tank assembly 1 being determined by the relative angles of the pile sleeve with the central vertical axis of the tank 1t. For safety, the pile 31 can be lifted slightly away from the seabed S by a crane on a vessel or by an ROV, to slacken off the sling 35 prior to cutting, to prevent damage to the ROV during the cutting process. The pile sleeve 30 can act as a guide for positioning of the pile 31 during anchoring, to ensure the pile 31 remains vertical during installation.
[0112] The mooring lines can be left in place in addition to the piles, or alternatively they may be removed such that the tank assembly is anchored solely by the piles. The mooring lines can additionally have unconnected tails left in place connected to the same anchors at the ends of the mooring lines after anchoring of the tank assembly, for tethering of an additional structure.
[0113] In certain examples the storage tank assembly 1 can be towed in one horizontal direction towards the target installation site by the leading line, and the horizontal movement of the tank assembly towards the target installation site can be controlled by a second, or further, tow line applying a force in the opposite direction for at least some of the time during the movement of the tank assembly. Thus, two or more tow vessels can be used for the installation operation and can be connected to the tank assembly at different locations, e.g. at opposite ends of the tank assembly. Each tow line can be attached to a respective tow vessel, with a leading tow line attached to the forward end of the tank assembly closest to the target installation site, and the other, trailing, tow lines attached to connection points which connect to the mooring lines towards the rear of the tank assembly, further away from the target installation site.
[0114] After anchoring of the tank assembly, a floating structure can be tethered above the tank assembly 1, in this example an offshore production buoy 50. The buoy 50 in this example is towed to the installation site for use, optionally at the same time as the tank assembly 1.
[0115] Once the buoy 50 has been towed to the installation site the trailing vessel 20 picks up a first unconnected tail of a pre-installed buoy mooring line 10b connected to the same anchor 11 that is anchoring the storage tank assembly 1 to the seabed S via the mooring line 10. The unconnected tail of the buoy mooring line 10b can be laid out on the seabed S during the pre-installation procedure for the tank assembly 1, or tethered to a surface buoy for pickup by a surface vessel. Alternatively, the buoy mooring lines 10b for tethering the buoy 50 to the anchor 11 can be attached to the top of the tank assembly 1 during load-out, so that the mooring lines 10b can be picked up from the tank assembly 1 during the installation process for the buoy 50, and thereafter connected to the buoy 50 in the same way as the tail of the mooring line 10.
[0116]
[0117] The mooring lines 10b are connected to the buoy 50 well above the seabed S, so the horizontal position of the buoy 50 will be affected by the magnitude and direction of the prevailing current and other forces acting laterally upon it. The tension in the mooring lines 10b for the buoy 50 is determined in concert with the length of the mooring lines 10b to minimise the horizontal movement of the buoy 50 after installation. The mooring lines 10b are optionally connected at their lower ends to the same anchors 11 that anchor the mooring lines 10 for the storage tank assembly 1 or at a point along the mooring lines 10 for the storage tank assembly 1, or to independent anchors (not shown). The mooring lines 10b for each of the buoy 50 and the tank assembly 1 can be the same length, but in this example the tails of the mooring lines 10b that are connected to the buoy 50 are longer than those connected to the tank assembly 1, to take account of the additional vertical distance of the buoy 50 from the seabed S. In an alternative example, where the mooring lines 10b for the buoy 50 are connected to a point on the mooring lines 10 of the tank assembly 1, the mooring lines 10b of the buoy 50 can be shorter than or the same length as the mooring lines 10 of the tank assembly 1.
[0118] Once both of the mooring lines 10b are connected to the buoy 50, the trailing vessel 20 can commence paying out of tow line 15b and can disconnect from the buoy 50 being towed. During this time the lead vessel 21 can move forward towards the anchor 11 at the end of leading line 16 forming the third mooring line of the tank assembly 1, adjusting position as necessary to ensure tension is maintained on the leading line 16b, and on the mooring lines 10b, thus controlling the heading and drift of the buoy 50, essentially as described for the installation of the tank assembly 1 above.
[0119]
[0120] After the buoy 50 is moored in position over the tank 1t as shown in
[0121] The tank assembly 1 can be connected to a ballast control/ROV vessel 22 by a corresponding ROV. The ballast control vessel can supply ballast to the tank assembly 1 by means of a ballast line 221. The ROV can open ballast compartment valves to permit removal of ballast, either from the designated compartments within the storage tank 1t, or the ballast tanks 1b, or can add buoyant fluid to the ballast tanks of the tank assembly 1 via the ballast line 221. The ballast can be extracted to the vessel for return to the tank assembly 1 after tethering of the buoy 50 is completed. The tank assembly 1 then lifts off the seabed S under the force of its own buoyancy as shown in
[0122] Once the tank assembly 1 has been sufficiently de-ballasted to lift it clear from the seabed S as shown in
[0123] After tethering of the buoy 50 and the tank assembly 1, ballast is returned from the vessel 22 to the tank assembly 1, and the tank assembly 1 sinks back down onto the seabed S. The descent of the tank assembly 1 pulls the buoy 50 vertically downwards to a working depth at the operating position shown in
[0124] In an alternative example of the buoy installation method, the storage tank assembly remains on the sea bed and the buoy is pulled down towards it by attachment of ballast weight to pre-defined locations on the mooring lines connected to the buoy. This increases the draught of the buoy and allows connection of tethers between the buoy and the tank assembly. The additional ballast is released after connection of the tethers to float the buoy to the working depth. For additional stability and security, mooring lines can still be connected to the buoy after the ballasting and connection operation is complete.
[0125] Removal of the buoy or replacement of the tethers may be carried out using the installation method in reverse, to either increase the draught of the buoy or to increase the buoyancy of the tank assembly to reduce the distance between the tank assembly and the buoy.
[0126] The mooring system described here is particularly useful when decommissioning and re-floating the storage tank assembly once it has completed operations at a given site. Due to the multiple unknown factors that affect buoyancy of a marine structure after it has been in position for some time, for example marine growth on the tank assembly 1, contents of the tank 1t, material loss due to corrosion, or the suction effects of the soils in the seabed, ascent of the tank assembly 1 being re-floated can be unpredictable. The mooring system offers additional control of the ascent of the tank assembly, thus mitigating rapid and uncontrolled breakout of the tank assembly from the seabed and subsequent uncontrolled ascent.
[0127] Once the structures have been tethered together, dynamic flexible risers are installed between the buoy 50 and fluid flow lines located on the seabed to allow fluid communication and flow of production fluids from the subsea wells to the buoy 50, via the subsea fluid flow lines from the wellheads and the riser.
[0128] In certain examples, the storage tank assembly 1 may be used as a base for subsea equipment thereby avoiding the requirement for a separate gravity base or anchor for other pieces of subsea equipment. In one example, the storage tank assembly 1 comprises a riser support structure in the form of a fixed or optionally a lazy S riser support arch 81, adapted to support and anchor a dynamic flexible riser 80, thereby avoiding a requirement for a separate base for the riser 80. The dynamic flexible riser 80 forms an S-shape as it drapes over the support arch 81. The riser 80 then connects to a rigid spool 84 via a valve 85 attached to the flattest part of the domed roof of the tank assembly 1. The rigid spool 84 then bends at 90 degrees to pass vertically down a side of the tank assembly 1, and bends at 90 degrees again to travel along the seabed S and connect to a hydrocarbon pipeline 88 laid on the seabed S. Providing anchoring and support mechanisms on the tank assembly 1 (regardless of how it has been deployed on the target installation site) mitigates the need for separate seabed anchors and bases for the riser supports, thereby de-cluttering the field around the tank assembly 1 and simplifying design of the field, and hence forms a separate aspect of the present invention.
[0129] The valve 83 and the first section of the rigid spool 84, up to and including the first 90 degree bend, are protected from damage, for example from dropped objects, by a protective housing 85. The housing 85 can be rigid and made from metal or plastic, or another material that is sufficiently resistant to water pressure at the installation depth of the storage tank assembly 1. The rigid spool 84 may be routed inside the structure of the storage tank assembly 1 to provide further protection.
[0130] In a further example, a dynamic flexible riser 80 is supported by a fixed or a lazy S riser support arch 81 as above, however, a portion of the rigid spool 84 is located within the storage tank assembly 1 rather than wholly externally to the tank assembly 1. The rigid spool 84 connects to the riser 80 through a valve 83 on the roof of the tank assembly 1 as before. The rigid spool 84 then bends at 90 degrees to pass through a channel in the roof of the storage tank assembly 1 towards the seabed S. When the rigid spool 84 nears the end of the channel at the base of the tank assembly 1, it again bends at 90 degrees to travel horizontally, passing through a side of the storage tank assembly 1, and connecting to a pipeline 88 laid on the seabed S. The channel through which the rigid spool 84 passes can be sealed such that it is watertight and resistant to ingress of seawater even at high pressure.
[0131] The valve 83 is protected by a protective housing 85 as before.
[0132] In an alternative example, the storage tank assembly 1 comprises a fixed or lazy S support arch 81, supporting a dynamic flexible riser 80 feeding into a valve connection 83 as before. In this example, the valve 83 connects the riser to a branched connection 93, where a single conduit branches into two, which then go on to connect to two rigid spools 84 via valves 83 on each conduit. Each rigid spool 84 connects with one of two pipelines 88 laid on the seabed S as before.
[0133] The valves 83 also have umbilical cables 95 connecting to them at one end, and connecting to an umbilical subsea distribution unit 98 at the other end. The umbilicals 95 and the subsea distribution unit 98 can be housed within the storage tank assembly 1, or can be on the roof of the tank assembly 1, protected along with the manifold connection 90 by a protective housing 92, formed from rigid material as before. Thus manifolds can also be mounted on the tank assembly 1 avoiding the need for a separate base for the manifold. In a further example, the manifold can be a subsea isolation valve, mounted on the top of the tank 1.
[0134] A second fixed or lazy S riser support arch 81 supports an umbilical cable 95 travelling between the subsea distribution unit 98 and the buoy 50. Further umbilical cables can be connected to the subsea distribution unit 98 if required.
[0135] In a further example, the storage tank assembly 1 comprises a dynamic riser support structure 89, sited on the roof of the storage tank assembly 1, and adapted to support a dynamic flexible riser 80. The dynamic riser support structure 89 guides and supports the rigid spool 84 and dynamic flexible riser 80, anchoring it so that the dynamic riser support structure 89 is resistant to movement under the influence of environmental forces and/or movement of the upper end of the dynamic flexible riser 80. The support structure can comprise a frame, a box or another structure capable of resisting movement of the rigid spool connected to the dynamic riser.
[0136] As before, the flexible riser 80 connects to a rigid spool 84, but in this configuration the point of connection is located within the dynamic riser support structure 89. The connection point is supported and protected from torsional and tensive forces by a connector 86, possibly a clamp, or sheath, or the like, that permits reduced movement of the flexible riser 80, with the resistance of the connector 86 to movement optionally increasing towards the end that connects to the rigid spool 84. Thus, movement of the flexible riser 80 relative to the rigid spool 84 decreases towards the connection point of the riser 80 and the spool 84. The rigid spool 84 is anchored, clamped, or otherwise secured to the dynamic riser support structure to mitigate movement of the rigid spool 84, and potential detachment from the fluid pathway. The rigid spool 84 can form a u-bend within the dynamic riser support structure 89, such that it passes outside of the dynamic riser support structure 89 and passes vertically downwards to the roof of the tank assembly 1. The rigid spool 84 then bends at 90 degrees and travels horizontally along a portion of the roof of the tank assembly 1 to a valve 83.
[0137] The valve 83 connects the first rigid spool 84a with a second rigid spool 84b, which then travels across the remaining portion of the roof of the tank assembly 1, bending at 90 degrees to travel vertically towards the seabed S, before bending at 90 degrees again to connect to a pipeline 88 laid on the seabed S.
[0138] Portions of the first and second rigid spools 84a, 84b, and the valve 83 connecting them, are protected by a protective housing 85 that is adapted to encase or house the valve 83 and at least a portion of the rigid spools 84a, 84b in order to protect the components from damage. The protective housing 85 is formed from plastic, metal, or another rigid material that is capable of withstanding the pressure of water at the installation depth of the tank assembly 1, as before.