METHOD FOR HOISTING AND TRANSPORTING ASSEMBLIES IN UNDERGROUND NUCLEAR POWER PLANT
20180002144 ยท 2018-01-04
Inventors
- Xinqiang NIU (Wuhan, CN)
- Qigui YANG (Wuhan, CN)
- Feng LI (Wuhan, CN)
- Lijun SU (Wuhan, CN)
- Xuehong YANG (Wuhan, CN)
- Xin ZHAO (Wuhan, CN)
- Xia HUA (Wuhan, CN)
- Shudong WANG (Wuhan, CN)
- Fuzhen DING (Wuhan, CN)
- Fei YU (Wuhan, CN)
- Yi SU (Wuhan, CN)
- Guoqiang ZHANG (Wuhan, CN)
- Shiyu XIE (Wuhan, CN)
- Tao ZHANG (Wuhan, CN)
Cpc classification
B66C2700/01
PERFORMING OPERATIONS; TRANSPORTING
E04G21/00
FIXED CONSTRUCTIONS
International classification
Abstract
A method for hoisting and transporting assemblies in an underground nuclear power plant, the method including: 1) pouring concrete onto a reactor cavern to form a rock anchor beam; hoisting a circular bridge crane to the reactor cavern through a hoist shaft on a top of the reactor cavern; mounting the circular bridge crane on the rock anchor beam by using a truck crane; 2) installing a containment cylinder and a track beam of a polar crane in the reactor cavern using the circular bridge crane; hoisting a gantry crane on one end of a polar crane girder and sending the polar crane girder to the reactor cavern; hoisting the other end of the polar crane girder using the circular bridge crane; allowing the polar crane girder to be horizontal; and mounting the polar crane girder on the track beam.
Claims
1. A method for hoisting and transporting assemblies in an underground nuclear power plant, the method comprising: 1) pouring concrete onto a reactor cavern to form a rock anchor beam; hoisting a circular bridge crane to the reactor cavern through a hoist shaft on a top of the reactor cavern; mounting the circular bridge crane on the rock anchor beam by using a truck crane; 2) installing a containment cylinder and a track beam of a polar crane in the reactor cavern using the circular bridge crane; hoisting a gantry crane on one end of a polar crane girder and sending the polar crane girder through the hoist shaft to the reactor cavern; hoisting the other end of the polar crane girder using the circular bridge crane; allowing the polar crane girder to be horizontal under a combined effect of the gantry crane and the circular bridge crane; and mounting the polar crane girder on the track beam; 3) employing the track beam and the polar crane girder as supporting points of an assembly jig of a steel lining on a containment dome, and hoisting processed pieces of the steel lining to the reactor cavern through the hoist shaft; soldering and assembling the pieces on the assembly jig; and 4) transporting permanent equipment from a nuclear reactor to the containment cylinder through a transport corridor which is connected to the reactor cavern; and turning over the permanent equipment and hoisting the permanent equipment to working areas using the polar crane girder.
2. The method of claim 1, wherein when performing 1), a combined cavern is excavated and following steps are performed: mounting bridge cranes on a corbel which is disposed lengthwise on an upper part of the combined cavern by the truck crane; transporting nuclear power auxiliary devices through a primary traffic tunnel to an installation platform which is disposed at one side or one end of the combined cavern; and hoisting the nuclear power auxiliary devices to working positions by the bridge cranes.
3. The method of claim 1, wherein when performing 2), a combined cavern is excavated and following steps are performed: mounting bridge cranes on a corbel which is disposed lengthwise on an upper part of the combined cavern by the truck crane; transporting nuclear power auxiliary devices through a primary traffic tunnel to an installation platform which is disposed at one side or one end of the combined cavern; and hoisting the nuclear power auxiliary devices to working positions by the bridge cranes.
4. The method of claim 1, wherein when performing 3), a combined cavern is excavated and following steps are performed: mounting bridge cranes on a corbel which is disposed lengthwise on an upper part of the combined cavern by the truck crane; transporting nuclear power auxiliary devices through a primary traffic tunnel to an installation platform which is disposed at one side or one end of the combined cavern; and hoisting the nuclear power auxiliary devices to working positions by the bridge cranes.
5. The method of claim 1, wherein when performing 4), a combined cavern is excavated and following steps are performed: mounting bridge cranes on a corbel which is disposed lengthwise on an upper part of the combined cavern by the truck crane; transporting nuclear power auxiliary devices through a primary traffic tunnel to an installation platform which is disposed at one side or one end of the combined cavern; and hoisting the nuclear power auxiliary devices to working positions by the bridge cranes.
6. The method of claim 1, wherein when performing 1), 2), 3), and 4), a combined cavern is excavated and following steps are performed: mounting bridge cranes on a corbel which is disposed lengthwise on an upper part of the combined cavern by the truck crane; transporting nuclear power auxiliary devices through a primary traffic tunnel to an installation platform which is disposed at one side or one end of the combined cavern; and hoisting the nuclear power auxiliary devices to working positions by the bridge cranes.
7. The method of claim 1, further comprising: 5) excavating a combined cavern, mounting bridge cranes on a corbel which is disposed lengthwise on an upper part of the combined cavern by the truck crane; transporting nuclear power auxiliary devices through a primary traffic tunnel to an installation platform which is disposed at one side or one end of the combined cavern; and hoisting the nuclear power auxiliary devices to working positions by the bridge cranes.
8. The method of claim 2, wherein the combined cavern comprises an auxiliary powerhouse cavern, the two safe powerhouse caverns, and a nuclear fuel powerhouse cavern; the auxiliary powerhouse cavern, the two safe powerhouse caverns, and the nuclear fuel powerhouse cavern are disposed lengthwise in a line; the auxiliary powerhouse cavern, a first safe powerhouse cavern, the nuclear fuel powerhouse cavern, and a second safe powerhouse cavern are connected in that order; the auxiliary powerhouse cavern, the two safe powerhouse caverns, and the nuclear fuel powerhouse cavern each are connected to the primary traffic tunnel; and an outer end surface of the auxiliary powerhouse cavern and one side of the nuclear fuel powerhouse cavern each are provided with the installation platform, and each of the installation platform is connected to the primary traffic tunnel.
9. The method of claim 3, wherein the combined cavern comprises an auxiliary powerhouse cavern, the two safe powerhouse caverns, and a nuclear fuel powerhouse cavern; the auxiliary powerhouse cavern, the two safe powerhouse caverns, and the nuclear fuel powerhouse cavern are disposed lengthwise in a line; the auxiliary powerhouse cavern, a first safe powerhouse cavern, the nuclear fuel powerhouse cavern, and a second safe powerhouse cavern are connected in that order; the auxiliary powerhouse cavern, the two safe powerhouse caverns, and the nuclear fuel powerhouse cavern each are connected to the primary traffic tunnel; and an outer end surface of the auxiliary powerhouse cavern and one side of the nuclear fuel powerhouse cavern each are provided with the installation platform, and each of the installation platform is connected to the primary traffic tunnel.
10. The method of claim 4, wherein the combined cavern comprises an auxiliary powerhouse cavern, the two safe powerhouse caverns, and a nuclear fuel powerhouse cavern; the auxiliary powerhouse cavern, the two safe powerhouse caverns, and the nuclear fuel powerhouse cavern are disposed lengthwise in a line; the auxiliary powerhouse cavern, a first safe powerhouse cavern, the nuclear fuel powerhouse cavern, and a second safe powerhouse cavern are connected in that order; the auxiliary powerhouse cavern, the two safe powerhouse caverns, and the nuclear fuel powerhouse cavern each are connected to the primary traffic tunnel; and an outer end surface of the auxiliary powerhouse cavern and one side of the nuclear fuel powerhouse cavern each are provided with the installation platform, and each of the installation platform is connected to the primary traffic tunnel.
11. The method of claim 5, wherein the combined cavern comprises an auxiliary powerhouse cavern, the two safe powerhouse caverns, and a nuclear fuel powerhouse cavern; the auxiliary powerhouse cavern, the two safe powerhouse caverns, and the nuclear fuel powerhouse cavern are disposed lengthwise in a line; the auxiliary powerhouse cavern, a first safe powerhouse cavern, the nuclear fuel powerhouse cavern, and a second safe powerhouse cavern are connected in that order; the auxiliary powerhouse cavern, the two safe powerhouse caverns, and the nuclear fuel powerhouse cavern each are connected to the primary traffic tunnel; and an outer end surface of the auxiliary powerhouse cavern and one side of the nuclear fuel powerhouse cavern each are provided with the installation platform, and each of the installation platform is connected to the primary traffic tunnel.
12. The method of claim 6, wherein the combined cavern comprises an auxiliary powerhouse cavern, the two safe powerhouse caverns, and a nuclear fuel powerhouse cavern; the auxiliary powerhouse cavern, the two safe powerhouse caverns, and the nuclear fuel powerhouse cavern are disposed lengthwise in a line; the auxiliary powerhouse cavern, a first safe powerhouse cavern, the nuclear fuel powerhouse cavern, and a second safe powerhouse cavern are connected in that order; the auxiliary powerhouse cavern, the two safe powerhouse caverns, and the nuclear fuel powerhouse cavern each are connected to the primary traffic tunnel; and an outer end surface of the auxiliary powerhouse cavern and one side of the nuclear fuel powerhouse cavern each are provided with the installation platform, and each of the installation platform is connected to the primary traffic tunnel.
13. The method of claim 7, wherein the combined cavern comprises an auxiliary powerhouse cavern, the two safe powerhouse caverns, and a nuclear fuel powerhouse cavern; the auxiliary powerhouse cavern, the two safe powerhouse caverns, and the nuclear fuel powerhouse cavern are disposed lengthwise in a line; the auxiliary powerhouse cavern, a first safe powerhouse cavern, the nuclear fuel powerhouse cavern, and a second safe powerhouse cavern are connected in that order; the auxiliary powerhouse cavern, the two safe powerhouse caverns, and the nuclear fuel powerhouse cavern each are connected to the primary traffic tunnel; and an outer end surface of the auxiliary powerhouse cavern and one side of the nuclear fuel powerhouse cavern each are provided with the installation platform, and each of the installation platform is connected to the primary traffic tunnel.
Description
BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The invention is described hereinbelow with reference to the accompanying drawings, in which:
[0019]
[0020]
[0021]
[0022]
DETAILED DESCRIPTION OF THE EMBODIMENTS
[0023] For further illustrating the invention, experiments detailing a method for hoisting and transporting assemblies in an underground nuclear power plant are described below. It should be noted that the following examples are intended to describe and not to limit the invention.
[0024] As shown in
[0025] As shown in
[0026] The combined cavern comprises an auxiliary powerhouse cavern 8, two safe powerhouse caverns 9, and a nuclear fuel powerhouse cavern 10. The auxiliary powerhouse cavern, the two safe powerhouse caverns, and the nuclear fuel powerhouse cavern are disposed lengthwise in a line. The auxiliary powerhouse cavern 8, one safe powerhouse cavern 9, the nuclear fuel powerhouse cavern 10, and the other safe powerhouse cavern 9 are connected in that order. The auxiliary powerhouse cavern 8, two safe powerhouse caverns 9, and the nuclear fuel powerhouse cavern 10 each are connected to the primary traffic tunnel 13. An outer end surface of the auxiliary powerhouse cavern 8 and one side of the nuclear fuel powerhouse cavern 10 each are provided with the installation platform 11, and each of the installation platform is connected to the primary traffic tunnel 13.
[0027] As shown in
[0032] As shown in
[0033] The construction of 5) and the construction of 1), 2), 3), or 4) are simultaneously carried out, or the construction of 5) and the construction of 1), 2), 3), and 4) are simultaneously carried out.
[0034] The method fully utilizes existing devices in the large-size underground nuclear power plant, and combines the features of underground space and underground construction, so that the difficulty of hoisting and transporting large-scale assemblies in an underground nuclear power plant is solved, providing a new idea for the construction in the underground space.
[0035] While particular embodiments of the invention have been shown and described, it will be obvious to those skilled in the art that changes and modifications may be made without departing from the invention in its broader aspects, and therefore, the aim in the appended claims is to cover all such changes and modifications as fall within the true spirit and scope of the invention.